MUNICIPAL CORPORATION OF       HYDERABAD
SAVE MUSI CAMPAIGN             ACTION TAKEN• Sri Hafeez Contractor leading Architect from  Mumbai has been appointed as a ...
Save Musi Campaign                                                                        Action Plan for the             ...
Road Infrastructure  1 River Drives & Junction Improvements    a Preparation of RDPs                              1    b D...
Rehabilitation  1 Relocation of Existing River Bed Activities    a Identification & Enumeration                  1    b Fo...
5 Restoration of Ethnic Markets    a Identification & Detailed Survey       1    b Design & PPP formulation               ...
BEFORELEVELING OF MUSI RIVER BED
BEFORELEVELING OF MUSI RIVER BED
BEFORELEVELING OF MUSI RIVER BED
AFTERLEVELING OF MUSI RIVER BED
AFTERLEVELING OF MUSI RIVER BED
AFTERLEVELING OF MUSI RIVER BED
AFTERLEVELING OF MUSI RIVER BED
AFTERLEVELING OF MUSI RIVER BED
NALAS
PROBLEM Inadequate drainage system    Annual rain fall :      750 mm;    Maximum intensity of rain fall in Hyderbad: 40...
 Hyderabad has a history of floods – 1908; 1930; 1962;1970; & 2000 Kirloskar consultants studied the problem and gave re...
 Major flood prone areas:   • Low laying area of Hussain Sagar;   • Saroor Nagar Tank;   • Errakunta; Balkapur;   • Kawad...
 Kirloskar consultants identified deficiency of all sections of drainage  system (more than 75% of deficiency found) Maj...
 Improvements proposed:   • Widening & deepening of nalas   • Construction of retaining walls on both side of nalas   • R...
 Issues involved:   • Cost of project (Modernization of the total system): Rs. 450     crores   • Rehabilitation   of   p...
REMOVAL OF ENCROACHMENT AT     HAKEEMPET NALA
REMOVAL OF ENCROACHMENT AT     HAKEEMPET NALA
REMOVAL OF ENCROACHMENT AT     HAKEEMPET NALA
REMOVAL OF ENCROACHMENT AT    PRAKASHNAGAR NALA
REMOVAL OF ENCROACHMENT AT    PRAKASHNAGAR NALA
REMOVAL OF ENCROACHMENT AT    PRAKASHNAGAR NALA
ROAD WIDENINGAND JUNCTION IMPROVEMENT IN  THIRTY ROADS ON PRIORITY
FLY OVERS• WORK IN PROGRESS AT CHANDRAYANAGUTTA• FORMAL LAUNCH AT GREEN LANDS, PUNJAGUTTA  AND NALGONDA CROSS ROADS ON 17....
Musi River Beautification Project progress
Musi River Beautification Project progress
Musi River Beautification Project progress
Musi River Beautification Project progress
Musi River Beautification Project progress
Musi River Beautification Project progress
Upcoming SlideShare
Loading in...5
×

Musi River Beautification Project progress

2,047

Published on

GHMC Presentation on Musi River Beautification Project progress

Published in: News & Politics
0 Comments
3 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
2,047
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
0
Comments
0
Likes
3
Embeds 0
No embeds

No notes for slide

Transcript of "Musi River Beautification Project progress"

  1. 1. MUNICIPAL CORPORATION OF HYDERABAD
  2. 2. SAVE MUSI CAMPAIGN ACTION TAKEN• Sri Hafeez Contractor leading Architect from Mumbai has been appointed as a consultant for the project.• Works as per the time line in progress.• The ID sewers work in the heritage precinct: Tenders being settled by HMWS&SB.• Formal Launch of the project on 17.08.2005.
  3. 3. Save Musi Campaign Action Plan for the Heritage Precinct (Puranapul to Chaderghat Bridge - 3.98 Km)Prerequisites 1 Delineation of Riverfront Development Zone 2 Creation of SPV 3 Acquisition of Riverbed Land 4 Trasfer of Public Properties to MCH ComponentSl. Estimat ed Time May-06 Mar-06 Nov-05 Feb-06 Apr-06 Aug-05 Jan-06 Project Dec-05 Jun-06 Jul-06 Sep-05 Oct-05 Months) (inNo. ActionsI Environmental Upgradation of the River 1 Imliban Island Environmental Upgradation a Development of Imliban Park 3 b Relocation of Conflicting Activities 3 2 Check Dams a Structural Design & Detailed Estimation Completed b Construction 6 3 Landscaping & Recreation a Detailed Design 2 b Development of Promenades & Flood Plains 8 4 Open Spaces Revitalisation a Identification of Open Spaces 1 b Detailed Design & PPP Strategies 2 c Development 6
  4. 4. Road Infrastructure 1 River Drives & Junction Improvements a Preparation of RDPs 1 b Detailed Design of Roads & Junctions 2 c Development 9 2 Access Roads Improvements a Preparation of RDPs 1 b Detailed Design 2 c Development 6 3 Parking Faciltities a Identification of Off-Street Parking Locations 1 b Design of Parking Lots 1 c Development through PPPs 6Heritage & Conservation 1 Restoration of Bridges & Structures a Conservation Architectural Design 2 b Restoration of the heritage structures 6 2 Heritage Precinct Development a Detailed Conservation Plan 3 b Urban Design Guidelines 1 c Precinct Development 9
  5. 5. Rehabilitation 1 Relocation of Existing River Bed Activities a Identification & Enumeration 1 b Formulation of Policy 1 c Detailed Rehabilitation Plan 2 d Implementation 6 2 Rationalisation of Graveyards & Burning Ghats a Identification & Enumeration 1 b Formulation of Policy 1 c Detailed Rehabilitation Plan 1 d Implementation 3 3 Rationalisation of Religious Structures a Identification & Enumeration 1 b Formulation of Policy 1 c Detailed Rehabilitation Plan 2 d Implementation 9 4 Rehabilitation of Dhobi Ghats a Identification & Enumeration 1 b Formulation of Policy 1 c Detailed Rehabilitation Plan 1 d Implementation 3
  6. 6. 5 Restoration of Ethnic Markets a Identification & Detailed Survey 1 b Design & PPP formulation 2 c Implementation 6 6 Ganesh Immersion Ghat a Detailed Design 1 b Development of Access Roads 3 c Construction of the Ghat 6Administrative Actions 1 Asset Management Plan a Identification of Public Properties 1 b Preparation of Asset Management Plan 3
  7. 7. BEFORELEVELING OF MUSI RIVER BED
  8. 8. BEFORELEVELING OF MUSI RIVER BED
  9. 9. BEFORELEVELING OF MUSI RIVER BED
  10. 10. AFTERLEVELING OF MUSI RIVER BED
  11. 11. AFTERLEVELING OF MUSI RIVER BED
  12. 12. AFTERLEVELING OF MUSI RIVER BED
  13. 13. AFTERLEVELING OF MUSI RIVER BED
  14. 14. AFTERLEVELING OF MUSI RIVER BED
  15. 15. NALAS
  16. 16. PROBLEM Inadequate drainage system  Annual rain fall : 750 mm;  Maximum intensity of rain fall in Hyderbad: 40 mm/hr; this year : 30 mm/hr  Carrying capacity of existing drainage sytem : 12 mm/hr (i.e., only 1/3rd capacity) Surface run-off water drains into Major lakes; Nalas; Hussain Sagar; & Musi River Number of lakes drastically reduced & fore shore area encroached Hussain Sagar shrunk substantially
  17. 17.  Hyderabad has a history of floods – 1908; 1930; 1962;1970; & 2000 Kirloskar consultants studied the problem and gave recommendations in 2003 Major causes for floods/inundation: • Inadequate drainage system • Construction of houses in flood absorbing tanks; foreshore areas of lakes etc. • Massive encroachments of nalas, tank beds etc.,  shrinkage • Dumping of debris & garbage into open nalas • Diversion of water courses to accommodate colonies • Increased run-off due to paving of surface • Reduced flood absorbing capacity of tanks breaches & overflow into low lying areas
  18. 18.  Major flood prone areas: • Low laying area of Hussain Sagar; • Saroor Nagar Tank; • Errakunta; Balkapur; • Kawadiguda; Domalguda; • Ashok Nagar;Bhavani Nagar; • Ganaga Nagar; Begumpet; • Lunger House; Afzal Sagar; • Mallepally etc. Encroachers are both the cause and victims of flooding/inundation.
  19. 19.  Kirloskar consultants identified deficiency of all sections of drainage system (more than 75% of deficiency found) Major flood prone nalas: • Hussain Sagar Surplus Nala - 1 • Balkapur Channel • Durgam Cheruvu Nala • Afzal Sagar Nala • Kishanbagh Nala • Old City Nala • Murki Nala • Saroor Nagar Surplus Nala
  20. 20.  Improvements proposed: • Widening & deepening of nalas • Construction of retaining walls on both side of nalas • Removal of encroachments • Modification of cross drainage works • Regrading of storm water drainage system
  21. 21.  Issues involved: • Cost of project (Modernization of the total system): Rs. 450 crores • Rehabilitation of poor encroachers & removal of encroachments • Removal of permanent/big constructions all along the nalas • Proper enforcement of WALTA. • Prevention of further shrinkage of tanks & lakes • Creation of awareness • Enlightened political support
  22. 22. REMOVAL OF ENCROACHMENT AT HAKEEMPET NALA
  23. 23. REMOVAL OF ENCROACHMENT AT HAKEEMPET NALA
  24. 24. REMOVAL OF ENCROACHMENT AT HAKEEMPET NALA
  25. 25. REMOVAL OF ENCROACHMENT AT PRAKASHNAGAR NALA
  26. 26. REMOVAL OF ENCROACHMENT AT PRAKASHNAGAR NALA
  27. 27. REMOVAL OF ENCROACHMENT AT PRAKASHNAGAR NALA
  28. 28. ROAD WIDENINGAND JUNCTION IMPROVEMENT IN THIRTY ROADS ON PRIORITY
  29. 29. FLY OVERS• WORK IN PROGRESS AT CHANDRAYANAGUTTA• FORMAL LAUNCH AT GREEN LANDS, PUNJAGUTTA AND NALGONDA CROSS ROADS ON 17.08.2005

×