Gateway @ CoFA

Construction Liaison Committee
              11 February 2010
Opening Remarks



  Prof Ian Howard
  Dean of COFA, UNSW
Suzanne Moore
Independent Facilitator
Construction Liaison Committee
                Purpose

• Convened by University of NSW
• Project Team to advise community...
Construction Liaison Committee
                 Protocols
• Approximately 20 members
• Membership focus – adjacent propert...
Construction Liaison Committee
                 Principles


1.   Communicate simply and succinctly
2.   Provide an opport...
Key Focus of Meeting
• To table a report – Pedestrian and Traffic Management
  Plan for Demolition, Excavation and Constru...
Peter McGeorge
- Acting Director, Facilities Management
                   UNSW
Key Focus of Presentation


• To provide a summary to the CLC of the
• Pedestrian Traffic Management Plan for Demolition,
...
Project Stages and Timing

Demolition – 2 months


         Shoring and Excavation – 3+ months


               Stage 1 – ...
Truck Routes
Requirements of Demolition
                 Statistics
                 1150 m3 of in-situ material translati...
Truck Routes
Requirements of Shoring and Excavation
                       Statistics
                       • 16000 m3 of...
Truck Routes
Requirements of Construction
                  Statistics

                  Minimal truck traffic on Selwyn ...
Site Access Through
    Building F Fully Investigated
- Deemed Not Feasible for Demolition
                      Reasons
 ...
Issues and Mitigating Strategies
Issues              Mitigating Strategies
People Safety       + Certified Traffic Control...
Issues and Mitigating Strategies
Issues                Mitigating Strategies
Trees                 + Protected in accordan...
Suzanne Moore
- Independent Facilitator
CLC Feedback Process
• CLC members (and others attending tonight) invited to
  complete a written feedback form
• Form may...
What Happens Next?

•   All CLC feedback attached to Final Pedestrian Construction Traffic
    Management Plan

•   Final ...
Q&A
Community Hotline
  1 800 109 451
Upcoming SlideShare
Loading in...5
×

Co Fa 11 Feb 2010 Clc

241

Published on

Presentation by COFA and UNSW to the community and Construction Liaison Committee outlining their new, comprehensive Traffic Management Plan

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
241
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Co Fa 11 Feb 2010 Clc

  1. 1. Gateway @ CoFA Construction Liaison Committee 11 February 2010
  2. 2. Opening Remarks Prof Ian Howard Dean of COFA, UNSW
  3. 3. Suzanne Moore Independent Facilitator
  4. 4. Construction Liaison Committee Purpose • Convened by University of NSW • Project Team to advise community of progress and construction related impacts from the site so that they can be dealt with “expeditiously and co-operatively” • For members of the CLC to feed back any issues they have with the reports tabled
  5. 5. Construction Liaison Committee Protocols • Approximately 20 members • Membership focus – adjacent properties and properties opposite • Monthly meetings • Ad hoc meetings as required • Meetings one hour duration • Project team to provide monthly reports to CLC regarding the construction program, progress and impending works • Minutes to be kept – record of issues captured • Minutes to be made available on the COFA website • Minutes issued to Council within seven days of meeting • 24 hour contact number to be provided • Complaints register to be tabled at each monthly meeting
  6. 6. Construction Liaison Committee Principles 1. Communicate simply and succinctly 2. Provide an opportunity for everyone to participate and provide feedback 3. Treat other meeting participants with courtesy
  7. 7. Key Focus of Meeting • To table a report – Pedestrian and Traffic Management Plan for Demolition, Excavation and Construction of College of Fine Arts Campus, Paddington • For the CLC to provide feedback on the report
  8. 8. Peter McGeorge - Acting Director, Facilities Management UNSW
  9. 9. Key Focus of Presentation • To provide a summary to the CLC of the • Pedestrian Traffic Management Plan for Demolition, Excavation and Construction of the College of Fine Arts Campus, Paddington • prior to lodging it with Council for assessment and determination.
  10. 10. Project Stages and Timing Demolition – 2 months Shoring and Excavation – 3+ months Stage 1 – 12 months Stage 2 – 10 months Overall Project Duration – 27+ months
  11. 11. Truck Routes Requirements of Demolition Statistics 1150 m3 of in-situ material translating to 2430 m3 of loose material to be removed from site Average of 7 truck cycles/day in peak period Total 270 truck loads @ 9m3/load 4 trucks – Week 1 20 trucks/week – Weeks 2-4 40-50 trucks/week – Weeks 5-9
  12. 12. Truck Routes Requirements of Shoring and Excavation Statistics • 16000 m3 of in-situ excavation material Approx 20 truck cycles per day, then removal of material would take approx 22 weeks Minimal truck traffic on Selwyn or Albion, main focus Greens Road 2200 truck loads required to remove loose material from the site Sewer Diversion and Temporary Access Construction adds an Additional 16 weeks to Construction
  13. 13. Truck Routes Requirements of Construction Statistics Minimal truck traffic on Selwyn or Albion, main focus Greens Road Construction Method: Electric crane proposed (over a diesel powered crane) to minimise noise disturbance Crane lifting points all from Greens Road Access Smaller Loads Transported through Basement to Materials Hoist Concrete Pumping all from Greens Road Access from Selwyn Street for those things that can’t be lifted by the crane and related to the establishment and dis- establishment of the crane itself
  14. 14. Site Access Through Building F Fully Investigated - Deemed Not Feasible for Demolition Reasons Design Development - Loading Dock now not being constructed Geotech Report - Additional excavation to create an underpass would be in rock Vehicle Movement – Turning Circes not Available Between Building F and Shoring of Building C North Access to Demolition Site – Blocked by Building C South Staging – Need to stage Development as not able to Decant functions from Building F – Need to keep in tact for Stage 1 Temporary Works – Major temporary works would be required significantly extending program and generating their own environmental impacts Craning Over Building F – Unable to establish crane base early, unable to create a structurally sound crane base, safety issues, approx. 3 month extension to project
  15. 15. Issues and Mitigating Strategies Issues Mitigating Strategies People Safety + Certified Traffic Controllers Managing All Traffic Movements + Footpath Management + Avoiding Craning over Occupied Buildings Noise + Reducing Council-Approved Operating Hours for Demolition Phase vs + Minimising Construction Duration + Selection of Electric Crane (for construction works) in lieu of Diesel Crane + Compliance with Council’s Noise Regulations Dust + Suitable Demolition Methodology + Dust Screens on Site Perimeter + Watering Down + Covered Truck Loads + Wash Bays for Trucks Leaving Site Vibration + Augered Piers in lieu of Hammered Piles + Suitable Demolition Methodology + Slow Truck Movement on Residential Streets + Dilapidation Reports for Surrounding Houses
  16. 16. Issues and Mitigating Strategies Issues Mitigating Strategies Trees + Protected in accordance with Council’s requirements + Level 5 Arborist appointed to ensure protection requirements are adhered to Parking + Selwyn Street - 3 spaces lost in Selwyn Street during Demolition Hours only for first few weeks + Spaces potentially lost at end of Napier Street + Albion Avenue - 1-2 spaces for during Demolition Hours only + Public Transport – Construction Staff and Students + Minimising Construction Zone in Greens Road Mud on Public Roads + Temporary Concrete and/or Timber Plank and/or Road Base Driveways + Grated Entrance Zone + High Pressure Water Cleaning of Truck Tyres Before Leaving Site + Street Sweeping if Required
  17. 17. Suzanne Moore - Independent Facilitator
  18. 18. CLC Feedback Process • CLC members (and others attending tonight) invited to complete a written feedback form • Form may be completed individually or in pairs, no names are required • 15 minutes will be allowed for completion • Forms will be collected and attached to the Plan to be provided to Sydney City Council tomorrow, 12 February 2010. • If time permits each participant can share one key issue and suggested mitigation strategy from their feedback form.
  19. 19. What Happens Next? • All CLC feedback attached to Final Pedestrian Construction Traffic Management Plan • Final Pedestrian Construction Traffic Management Plan (for Whole Project Phase only) lodged with Council • Council issued with Minutes of CLC Meeting • Council to advise adjacent properties of Plan and call for further comment • Council to consider and approve / disapprove Construction Traffic Management Plan for Whole Project
  20. 20. Q&A Community Hotline 1 800 109 451
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×