Quick Changeover SMED

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    4 Favorites

    Quick Changeover SMED - Presentation Transcript

    1. QUICK CHANGE OVER
      Single
      Minute
      Exchange of
      Dies
    2. Changeover time
      Traditional setup
      Single Minutes Exchange of Dies
      QUICK CHANGE OVER
      SMED Process Steps
      Ideas for Improvement
      CONTENTS
    3. INTRODUCTION
      Setup
      Time
      Mold Change
      Colour Change
      EQUIPMENT
      SIX BIG LOSSES
      Mold change
      Inspect/Adjust
      0
      Breakdowns
      Last good part
      1st Piece Time
      (good or bad)
      1st Good
      Piece Time
      Available time
      Setup/
      adjustment
      Changeover time:
      Definition
      Available operating time
      Idling/minor stoppages
      The time elapsed between when the last good pieceof product A comes off
      and the first good piece of product B starts.
      Speed
      Actual operating time
      Defects in process rework
      Effective
      Operating time
      Start-up losses
    4. INTRODUCTION
      History : Land costs in Japan were very high, therefore it was not feasible to store large inventories of vehicles
      QUICK
      CHANGE OVERS
      “A rapid and efficient way of converting a process from running the current product to running the next product “
      Developed by Shigeo Shingo
      ( in the late 1950’s and early 1960’s) chief engineer of Toyota
      Reduces the waste of inventory by creating shorter production runsthat better align with customer demand
    5. QUICK CHANGEOVER IN LEAN
    6. TRANSFORMATION
      TRADITIONAL
      VS
      SMED
      How long does it take to change the tire???
    7. 6 “Traditional” Setup Steps
    8. INTRODUCTION
      What is “World-Class”
      in Quick Changeovers?
      SMED:
      Single Minute Exchange of Die
      Concept that says all setups should and can take less than 10 minutes
      OTED:
      One Touch Exchange of Die
      Concept that says all setups should and can take less than 100 seconds!
    9. The SMED Process
      • Reduce inventory
      • Reduce batch sizes
      • Reduce changeover time
      • Reduce impact on equipment utilization
      • Improve quality after changeover
      • Improve repeatability
      • Improve throughput
      • Improve flexibility
      GOALS
      Document internal and external procedures
      Convert internal activities to external activities
      Separate internal and external activities.
      Observe and record
      Streamline all activities
    10. THE SMED PROCESS
      1. OBSERVE AND RECORD
      REMEMBER!!!
      These activities are not conducted for the purpose of eliminating jobs or reducing people!
      We should always:
      • Notify the party to be observed ahead of time
      • Explain why we are conducting an observation
      • We’re observing the activity not the person
      • What we are trying to accomplish
      • Explain the possible benefits for them and the company
      • Review the observation with the individual
      • Coaching
      • Clarification
      • Identify internal and external elements,
      • waste/lost time,
      • variances from the standard process
    11. THE SMED PROCESS
      Run
      All Setup
      Activities
      I
      I
      I
      I
      E
      E
      E
      E
      Run
      Internals
      Externals
      Run
      2. SEPARATE INTERNAL AND EXTERNAL ACTIVITIES
      Internal elements:
      operations that must be performed while the machine/process is stopped
      Post-setup
      External elements:
      operations that can be performed while the machine/process is running
      Externals
      externals
    12. THE SMED PROCESS
      Internals
      Externals
      Run
      Internals
      Run
      Externals
      Internals
      3. CONVERT INTERNALS TO EXTERNALS ACTIVITIES
      Internals
      Externals
      Run
      Internals
      Externals
      Run
      Eliminate adjustment
      Run
      Externals
    13. THE SMED PROCESS
      How to convert externals to internals ?
      • Eliminate search-and-find work
      • Arrange tools & materials beforehand
      • Complete prep work before starting changeover
      • Standardize settings
      • Make visual marks vs. trial and error adjustments
      • Eliminate trial runs
      • Postpone “put away” work
    14. THE SMED PROCESS
      4. STREAMLINE ALL ACTIVITIES
      BEFORE
      Last good piece of product A
      First good piece of product B
      Streamlined
      External
      elements
      Streamlined
      External
      elements
      Last good piece of product A
      First good piece of product B
      AFTER CHANGE OVER
      Streamlined
      internal
      elements
      Machine
      running
      Machine
      running
      Last good piece of product A
      First good piece of product B
      External elements
      External elements
      Total
      setup
      Machine
      running
      Machine
      running
      Internal
      elements
      Machine
      running
      Machine
      running
      Internal and external elements
      STREAM
      LINE
      Total setup
      Total setup
    15. THE SMED PROCESS
      STREAMLINE
      INTERNAL PROCESS
      STREAMLINE
      EXTERNAL PROCESS
      Create Parallel steps – completed at the same time
      Reduce complexity and eliminate waste
      • Use functional fixtures and jigs
      one motion fasteners
      levered or one-turn fasteners
      interlocking wedge or slot
      • Eliminate adjustments
      use angle and flat
      use preset pins, guides, notches etc.
      • Eliminate need to leave the machine
      Use POUS and water spider
      Adopt functional standards
      • Visual factory locations for tools
      • Color coding
      • Standard set ups
      • Checklists
      ADOPT
      QUICK DIE CHANGEOVER
      ( QDC) HARDWARE
    16. THE SMED PROCESS
      5. DOCUMENT INTERNAL & EXTERNAL PROCEDURES
      • Make adjustments, as needed
      • Re-test, if necessary
    17. THE SMED PROCESS
      5. DOCUMENT INTERNAL & EXTERNAL PROCEDURES
      • Make adjustments, as needed
      • Re-test, if necessary
    18. THE SMED PROCESS
      5. DOCUMENT INTERNAL & EXTERNAL PROCEDURES
      • Make adjustments, as needed
      • Re-test, if necessary
    19. WHEN SHOULD YOU AUTOMATE??
      • Criterion 1:
      The operation has already been dramatically simplified
      • Criterion 2:
      Begin with semi automation to achieve 80% benefit at 20% cost
      • Criterion 3:
      The automation is cost-effective
    20. IDEAS FOR IMPROVEMENT
      Gauges
      Set blocks
      Stop gauges
      Setup sheet
      Prints
      Special instructions
      Special tools
      SET-UP TOOL CARTS
    21. IDEAS FOR IMPROVEMENT
      Rollers
      SET-UP
      DIE CARTS
      T
      ools
      T
      urntable
      Documentation
    22. IDEAS FOR IMPROVEMENT
      Slide
      Slot
      Model
      value
      address
      ORGANIZE & STORE IN PROXIMITY
      Block
      gauge #
      Cover
      Line #
      Part
      Slot address labels
    23. IDEAS FOR IMPROVEMENT
      Clamping height
      Add
      spacers
      here
      Cut away
      here
      STANDARDIZE CLAMPING HEIGHT
    24. IDEAS FOR IMPROVEMENT
      Dial gauge
      Linear gauge
      & pointer
      Adjusting
      screw
      Adjusting
      wedge
      Adjusting
      pin
      Better Still
      Better
      Interior space
      Spring
      (inaccessible)
      plate
    25. L
      clamp
      Socket wrench
      removes screw
      Socket head cap screw
      Nut is not removed
      for setup!
      4-piece clamp
      4
      3
      2
      IDEAS FOR IMPROVEMENT
      AFTER
      Die heights vary
      Standardize clamp heights on dies
      Streamlined 1-Piece Clamp
      Spring
      Spring
      BEFORE
      1
      Die
      Die
      Bolster
      Plate
      Bolster
      Plate
    26. Before
      IDEAS FOR IMPROVEMENT
      Mold
      Cam
      lock
      Stopper
      After
      TOGGLE LOCK DOWN CLAMP
      QUICK RELEASE CAM LOCK
      Eliminate bolts
    27. IDEAS FOR IMPROVEMENT
      Die
      Before
      Top view
      Bolster
      Die
      Slot
      2. Tighten
      After
      Side view
      Bolster
      1. Lift
      Bolt & Slot
      Centering Jig
      Hinged Bolt
    28. Are you ready to face the
      “World Class” challenge?
    SlideShare Zeitgeist 2009

    + starish 333starish 333 Nominate

    custom

    454 views, 4 favs, 1 embeds more stats

    Quick Change Over - on the base of Single Minutes E more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 454
      • 451 on SlideShare
      • 3 from embeds
    • Comments 0
    • Favorites 4
    • Downloads 64
    Most viewed embeds
    • 3 views on http://eng.managerservices.nl

    more

    All embeds
    • 3 views on http://eng.managerservices.nl

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories