WORK COST TIME RESOURCES Slide Title
TIME RESOURCES $ DAYS COST Slide Title
RESOURCES $ DAYS TIME COST Slide Title
1  8  11  16  20  A B C D E 0  5  10  15  20  Sequence of Tasks Slide Title Days
1  9  12  17  21  A B C D E 0  5  10  15  20  Delay on Task B Project Delayed Slide Title Days
1  5  8  11  16  20  A B C D E 0  5  10  15  20  Days F Float Time (15 days) Slide Title
1  5  8  11  16  20  A B C D E 0  5  10  15  20  Days F Float Time (3 days) Slide Title
1  8  9  12  17  21  A B C D E 0  5  10  15  20  Days Project Delayed F Slide Title
A F E D C B Slide Title
1  5  8  11  16  20   Slide Title A B C D E 0  5  10  15  20  F Total 4  6  6  6  6  3  3  3  2  2  2  2  2  2  2 3  3  3 ...
1  5  8  11  16  20   Slide Title A B C D E 0  5  10  15  20  F Allocation Total 4  6  6  6  6  3  3  3  2  2  2  2  2  2 ...
1  8  11  13  16  20   Slide Title A B C D E 0  5  10  15  20  F 1  3  3  3  3  3  3  3  5  5  5  3  3  2  2  2  2  3  3  ...
1  8  11  16  20   Slide Title A B C D E 0  5  10  15  20 F 3  5  5  5  5  5  5  5  2  2  2  2  2  2  2  1  3  3  3  3  3 ...
Upcoming SlideShare
Loading in …5
×

Pmw slides jan08

371 views

Published on

Some Slides form PM Training

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
371
On SlideShare
0
From Embeds
0
Number of Embeds
51
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide
  • Too many dotted lines on Task E original.
  • Pmw slides jan08

    1. 1. WORK COST TIME RESOURCES Slide Title
    2. 2. TIME RESOURCES $ DAYS COST Slide Title
    3. 3. RESOURCES $ DAYS TIME COST Slide Title
    4. 4. 1 8 11 16 20 A B C D E 0 5 10 15 20 Sequence of Tasks Slide Title Days
    5. 5. 1 9 12 17 21 A B C D E 0 5 10 15 20 Delay on Task B Project Delayed Slide Title Days
    6. 6. 1 5 8 11 16 20 A B C D E 0 5 10 15 20 Days F Float Time (15 days) Slide Title
    7. 7. 1 5 8 11 16 20 A B C D E 0 5 10 15 20 Days F Float Time (3 days) Slide Title
    8. 8. 1 8 9 12 17 21 A B C D E 0 5 10 15 20 Days Project Delayed F Slide Title
    9. 9. A F E D C B Slide Title
    10. 10. 1 5 8 11 16 20 Slide Title A B C D E 0 5 10 15 20 F Total 4 6 6 6 6 3 3 3 2 2 2 2 2 2 2 3 3 3 3 3 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Days Allocation
    11. 11. 1 5 8 11 16 20 Slide Title A B C D E 0 5 10 15 20 F Allocation Total 4 6 6 6 6 3 3 3 2 2 2 2 2 2 2 Exceeds Supply! 3 3 3 3 3 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Days
    12. 12. 1 8 11 13 16 20 Slide Title A B C D E 0 5 10 15 20 F 1 3 3 3 3 3 3 3 5 5 5 3 3 2 2 2 2 3 3 3 3 3 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Task F delayed to avoid conflict with Task B Days
    13. 13. 1 8 11 16 20 Slide Title A B C D E 0 5 10 15 20 F 3 5 5 5 5 5 5 5 2 2 2 2 2 2 2 1 3 3 3 3 3 3 3 2 2 2 2 2 2 2 Allocation reduced – duration increased 2 2 2 2 2 2 2 2 Days

    ×