Your SlideShare is downloading. ×
Mitsunobu - Status of KEKB EP System
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×

Introducing the official SlideShare app

Stunning, full-screen experience for iPhone and Android

Text the download link to your phone

Standard text messaging rates apply

Mitsunobu - Status of KEKB EP System

476
views

Published on

http://www.surfacetreatments.it/thinfilms …

http://www.surfacetreatments.it/thinfilms

Status of KEKB Electropolishing system (Shinji Mitsunobu - 15')
Speaker: Shinji Mitsunobu - KEK Tsukuba-Shi Ibaraki-Ken Japan | Duration: 15 min.
Abstract
Long time KEK superconducting cavities were treated by electro polish at Nomura plating Co.. For developing more reliable EP for ILC SC cavity,KEK decided to construct in-house new EP system. One L-band system and one universal system for 500 MHz and L-band system are gathered in one place.
L-band system have been used routinely ILC cavities EP successfully.
Anther new EP system for 500 MHz KEKB SC cavity have been constructed. KEKB test cavity was successfully processed.

Published in: Technology

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
476
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
8
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Status of KEKB EP System S.Mitsunobu,Y.Funahashi,T.Furuya,A. Kabe,Y. Morita,M. Nishiwaki, M. Sawabe,S. Takano and K.Ueno KEK
  • 2. New EP system
    • KEK SC cavities were processed by Electro Polish at Nomura Plating Co..
    • For more reliable EP for ILC cavity, KEK decided to have in-house new EP system.
    • One L-band system and universal system for 500 MHz and L band system are gathered in one place.
    • 500 MHz system reuse old one as possible and move from Nomura to KEK.
  • 3. Conceptual drawing of EP (Proff.Kojima’s car battery) Teflon
  • 4. Vertical EP Furuya et al
  • 5. Saito et al
  • 6.  
  • 7. KEKB Superconducting Cavity
  • 8. Nb Cavity
  • 9. Rotating Equipment for EP at Nomura Plating Co. 超伝導空洞の電解研磨
  • 10. New EP bed at KEK
  • 11. First test using TRISTAN Single Cell (TM110 mode test)
  • 12. Ultrasonic tank and shower tank
  • 13. New acid tank (500 L)
  • 14. New EP area
  • 15. Acid gas cleaning system
  • 16. Modification
    • Automatic controlling system
    • Separating Heat Exchanger
    • Exchange Z- seal
    • Move air intake valve on rotational Joint
    • Add Water over flow pipe
    • Add Butterfly type valves over flow line
  • 17.  
  • 18. EP condition
    • Acid Temperature 20~30 degC
    • Cathode Voltage -20 ~ -30 V
    • Current density 30~50mA(EP1>EP2)
    • Acid flow rate 40L/min
    • 10 mm over center
    • KEKB cavity use O3 rinsing
  • 19.  
  • 20. 4 bar shower rinsing O 3 rinsing Hotwater and U sonic rinsing
  • 21.  
  • 22. Conclusion of New EP system
    • New EP system has been constructed in KEK.
    • KEKB Test cavity was successfully treated by new EP system.
    • KEKB Test Cavity reached Eacc>12.7MV/m.
    • Three NSRRC KEKB Type cavities will use this EP system next year.
    • L-band cavity and crab cavity(CERN upgrade) also can be use this system by small modification.