Your SlideShare is downloading. ×
0
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
CA : Supplemental Dwgs
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

CA : Supplemental Dwgs

1,155

Published on

Published in: Design
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
1,155
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
13
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Supplemental Drawings p r e s e n t a t i o n April 18, 2007 eu:a eppstein uhen architects 1
  • 2. Presentation Outline  Supplemental Drawings  ADT Process  Revit Demonstration  Construction Bulletins April 18, 2007 eu:a eppstein uhen architects 2
  • 3. Supplemental Drawings Supplemental Drawings:  The graphic deliverable to identify revisions.  Included with front-end documentation which describes the revision. Revisions:  Modifications, clarifications, or interpretations made to the Construction Documents  Bidding Phase:  Addendum  Construction Administration:  Construction Bulletin (CB) April 18, 2007 eu:a eppstein uhen architects 3
  • 4. Revision Work Flow Incorporated in GC & Contract Change Order Subs Const Docs Bidding Construction DESIGN ADDENDUM CB TEAM CONTRACT April 18, 2007 eu:a eppstein uhen architects 4
  • 5. Supplemental Drawings Sheet Formats 8.5” x 11”  TB - CA 8.5 x 11 (Landscape)  TB - CA 8.5 x 11 (Portrait) 11” x 17”  TB - CA 11 x 17 (Landscape)  TB - CA 11 x 17 (Portrait) April 18, 2007 eu:a eppstein uhen architects 5
  • 6. Sheet Formats April 18, 2007 eu:a eppstein uhen architects 6
  • 7. Supplemental Sheet Info Construction Set or Bid Set #1 MM/DD/YY e.g. 04/18/07 Per Vision April 18, 2007 eu:a eppstein uhen architects 7
  • 8. Supplemental Sheet Info Acme Warehouse 1234 Main Street Anywhere, WI 54321 April 18, 2007 eu:a eppstein uhen architects 8
  • 9. Supplemental Sheet Info Abbreviation + Number Construction Bulletin CB #000 Addendum ADD #00 Request for Information RFI #000 April 18, 2007 eu:a eppstein uhen architects 9
  • 10. Supplemental Sheet Info Date of Revision Different from “ISSUANCE DATE” Date of CB or Addendum or RFI April 18, 2007 eu:a eppstein uhen architects 10
  • 11. Supplemental Sheet Info Axxx : Sheet Number •A105 5th Flr Plan •A200 Exterior Elevations X01 : Consecutive Revision •X01 1st Revision •X15 15th Revision April 18, 2007 eu:a eppstein uhen architects 11
  • 12. Nomenclature: Supplemental Dwgs CD sheet + Dash + X suffix + (2) Sequential Numbers A0000-X00 A1001-X01 A00-X00 A201-X13 A0-X00 A5-X02 Naming convention: Modifications : a. Construction Bulletin CB #000 b. Construction Change Directive CCD #000 c. Proposal Request PR #000 Clarifications a. Addendum ADD #00 b. Architectural Supplemental Information ASI #000 c. Field Directives FD #000 Interpretations a. Request for Information RFI #000 April 18, 2007 eu:a eppstein uhen architects 12
  • 13. Supplemental Dwgs Architectural Examples  G103-X11 11th revision to sheet G103 - First Floor Life Safety Plan  A101-X01 1st revision to sheet A101 - First Floor Plan  A1021-X03 3rd revision to sheet A1021 - Twenty-First Floor Plan  A501-X29 29th revision to sheet A501 - Exterior Plan Details Consultant Examples  Would follow this same naming convention:  S103-X06 6th revision to sheet S103 - Third Floor Framing Plan  E101-X01 1st revision to sheet E101 - First Floor Electrical Plan  H1021-X03 3rd revision to sheet A1021 - Twenty-First Floor HVAC Plan  P105-X11 11th revision to sheet P105 - Fifth Floor Plumbing Plan April 18, 2007 eu:a eppstein uhen architects 13
  • 14. ADT Process  Cloud the revision in the MS (model space) of the source drawing (plan, elevation, section, etc) on layer A-Anno-Revs  Open the sheet affected (GXXX.dwg, AXXX.dwg, etc)  Copy view from the “Main” Sheet tab into a Supplemental Sheets’ tab.  Resize the view to fit the page.  Print Supplemental Sheet to PDF (AXXX-00.pdf)  Save to 00000-00DocumentsCAConstruction Bulletins  Once CB’s itemized proposal has been received & accepted: Bluebeam Staple all associated PDF’s into a single PDF (CB-000) Copy Supplemental Drawing PDF’s (only!) into: Record DocumentsContract DrawingsSupplemental Dwgs April 18, 2007 eu:a eppstein uhen architects 14
  • 15. Revit Demonstration April 18, 2007 eu:a eppstein uhen architects 15
  • 16. Conclusion Questions??? Comments??? Concerns??? Suggestions??? April 18, 2007 eu:a eppstein uhen architects 16

×