RWE- a sustainable electricity supply for the future - Presentation Transcript
RWE – a sustainable electricity supply for the future Dr. Hans-Peter Meurer, RWE AG TBLI Europe 2006, Paris, November 9/10, 2006
Key demands for a sustainable energy supply C E S C Competitiveness
Provision of a cost-efficient European energy supply
E Environmental compatibility
Climate protection
Minimization of classic emissions (NO X /SO 2 /dust)
Preservation of resources
S Security of supply
Consideration of whole value chain: fuel supply, generation, transport, distribution, service
The well-balanced application of target criteria ensures a sustainable, long term orientated energy supply.
Boundary conditions which determine RWE´s generation portfolio: Ressources
Fuel mix *) Advantage Challenge
Lignite 40,5% domestic source high CO 2 emissions low production costs medium SO 2 , NO x emissions
Hard coal 18,4% availability high CO 2 emissions moderate costs medium / high SO 2 , NO x emissions
Nuclear 24,1% availability nuclear safety CO 2 free electricity generation disposal of spent fuels and waste low production costs
Gas 14,6% low C0 2 emissions medium to high generation costs
Water 1,4% CO 2 free electricity generation extension nearly unpossible
Wind 0,6% CO 2 free electricity generation high generation and transport costs impact on landscape
*) contribution to own generation in 2005
Boundary conditions which determine RWE´s strategy: Regulatory framework
Germany:
100% liberalized market
LCPD alike pollutant legislation since 1980
Ownership of mining, generation, transport, distribution, retail
Access to transport grid supervised by Federal Grid Agency
Emissions trading installed
UK:
100 % liberalized market
Adaption to LCPD until 2008
Ownership of generation and retail
Emissions trading installed
RWE´s strategy: No regret
Maintain a broad based fuel mix
Increase efficiency in electricity generation
Develop new technical solutions for electricity generation and CO 2 abatement
Take into account future costs for CO 2 emissions
Support the efficient use of energy
Make use of emissions trading and JI/CDM
Flexibility is a key element to meet future challenges and to secure a no-regret-strategy.
Technology of today: New Power Plant Projects in Continental Europe Topping gas turbines Weisweiler 2 x 190 MW
Construction and operation permit received in Feb. 2005)
Start of construction in April 2005
Expected start of commercial operation: July 2006
Budget: €150m
BoA 2/3 twin unit Neurath 2 x 1,050 MW
Permit received in June 2005
Start of construction in January 2006
Expected start of commercial operation: January 2010
Budget: €2.2bn
Hard coal-fired power plant Hamm 2 x 800 MW
Announced in November 2005 (poss. with partners)
Expected commissioning: 2012
Budget: €1,500m
CCGT plant Lingen 850 MW
Construction option: kept open
Preliminary approval received in December 2004
Budget: €400m
Hard coal & bio mass fired power plant Netherlands 2 x 800 MW
Announced in April 2006
Expected commissioning: 2012 / 2013
Budget: €1,600m
Technology of today: Modernizing our UK power plant portfolio Replanting steam turbines at Aberthaw
Turbine contracts already placed
All three units will be retrofitted by 2008
Thermal efficiency will increase from 36.5% to 38.9%
Additional capacity of 69 MW
Replanting steam turbines at Tilbury
Programme of turbine improvements underway
All three available units will be upgraded by the end of 2007
Reduction of fuel input and emissions by up to 1.5%
Additional capacity of up to 15 MW per unit achievable
Flue gas desulphurization at Aberthaw
Retrofit three units to comply with "Large Combustion Plant Directive"
Preliminary enabling work has begun
Scheduled to be completed by 2008
Upgrading turbines at CCGT plants
Investigating options for improving efficiency and output at Didcot B and Little Barford
Target heat rate improvement of +1%
New build of a CCGT plant
Final decision not yet taken: investments will depend on environmental legislation and market conditions
Option 1: Applied for consent to build a 2,000 MW plant in Pembroke
Option 2: 1,500 MW consented site at Staythorpe
Technology of tomorrow: Increase in efficiency – the priority development target for CO 2 reduction
700°C power plant (hard coal & lignite)
Efficiency increase of 4%pts possible
Projects: COMTES700 – Component Test Facility for a 700°C Power Plant – initiated by a group of major European power generators (incl. RWE) and material tests in existing power plants of RWE and others
Technology successfully proved, from 1993 on, at an RWE pre-drying plant in Frechen
To introduce this technology on a commercial scale, RWE has started the construction of a lignite pre-drying prototype plant at the BoA 1 plant (Niederaussem). Operations will start at the end of 2007.
Budget: €50m for construction and operation
Lignite pre-drying plant at Frechen Extra investment will lead to significantly improved efficiency rates and lower fuel consumption, so that electricity production may be kept constant and CO 2 output be reduced
Technology of the Future: RWE to gain leadership in Europe in CO 2 -free power plant technology 1) IGCC: Integrated gasification combined cycle 2) CCS: carbon capture and storage RWE Power plans to develop and build a CO 2 -free 450 MW-coal-fired IGCC 1) plant including CO 2 transport and storage in Germany to demon-strate the whole CCS 2) -chain. Commissioning is scheduled for 2014. In parallel, CO 2 scrubbing for lignite and hard coal will be developed further for advanced conventional power plant technology, also as a retrofit option. 1 2 3 In addition, RWE npower will conduct a feasibility study for a clean coal 1000 MW hard coal fired power plant at Tilbury.
Time schedule for development of technology Efficiency increases Beyond CO 2 -free power plant with CO 2 sequestration and storage Today Exploitation of existing efficiency potential Tomorrow Increased efficiency due to new power plant technology Commissioning CO 2 sequestration and storage 2012 2016 2020
Down stream energy efficiency
Continue to invest in decentralized, good CHP (biomass and gas fired power plants)
Expand energy services and consultation of small and medium business customers to use energy effectively
Support campaigns to save energy in households and small business: - dena *) initiative in Germany - Energy Efficiency Commitment in UK *) dena: German Energy Agency
CDM/JI projects enable RWE to access cost-effective opportunities to reduce greenhousegas emissions
Options presently pursued:
Direct investment in CDM/JI projects: RWE Power has set up a budget totaling €150 million until 2012 for investments in greenhouse gas abatement projects like utilizing coal mine gas otherwise emitted to the atmosphere
Purchasing carbon credits from third party-projects: Means to make CDM/JI projects developed by third parties financially viable. Example: Decomposition of greenhouse gas emissions in chemical plants in China.
Participating in carbon funds: RWE has been contributing to the Prototype Carbon Fund of the World Bank since 2000. This fund kick-started the global carbon credit market.
Clean Development Mechanism (CDM): Emission reductions caused by investment of an industrialized country in a country without reduction commitments are credited to the emission account of the investor country Joint Implementation (JI): Emission reductions caused by investment of one industrialized country in a second industrialized country are credited to the emission account of the investor country Germany/UK Germany/UK China Emission rights Russia Emission rights
And what do others say:
Dow Jones Sustainability Indexes World and STOXX 2007: Industry Leader for Multiutilities
Climate Leadership Index of Carbon Disclosure Project 2006: „Best in Class“ in Utility Sector
0 comments
Post a comment