EDIFICIO AUGUSTO
Upcoming SlideShare
Loading in...5
×
 

EDIFICIO AUGUSTO

on

  • 881 views

Avance de obra hasta el 26 de julio de 2011

Avance de obra hasta el 26 de julio de 2011

Statistics

Views

Total Views
881
Views on SlideShare
881
Embed Views
0

Actions

Likes
0
Downloads
5
Comments
0

0 Embeds 0

No embeds

Accessibility

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

EDIFICIO AUGUSTO EDIFICIO AUGUSTO Presentation Transcript

  • FOTOS AVACE DE OBRA AL 26 DE JULIO DE 2011
  • Futuro Quincho con pileta aprovechando la estructura existente
  • Comedor depto “C” con premarcos colocados View slide
  • Cañería calefacción para radiadores + Instalación cañería para AC/Split depto “C” View slide
  • Comedor depto “B” con premarcos colocados, salida al balcón y cañería AC
  • Comedor depto “A” con premarcos colocados, salida al balcón y cañería AC
  • Cabina medidores de gas en palieres + colocación abertura
  • Cocina depto “B” – Cañería gas, calefacción, electricidad y agua
  • Cocina depto “C” – cañería electricidad, agua, gas, calefacción, desagües + revoques
  • Distribución cañería calefacción en depto “B”
  • Detalle instalación equipos de AC/Split con desagües incluidos y alimentación eléctrica, se ven los premarcos de aluminio que se están colocando
  • Nivel piso 10
  • Hormigonado losa sobre piso 11, o sea, piso 12
  • Fachada hasta piso 12 Medianera Este realizada hasta piso 9. Las aberturas son de los baños de los deptos “B”
  • Contrafrente con barandas hasta piso 5 + vista balcón frente deptos “A” y “B”
  • Planta Baja