Product Work Log 2012­2013


 Name: Sydney Solano             Date:


 Product: Saxophone Quartet



 Date                  Time      Activity                 Comments

 September 10, 2012    4:30 pm   Auditions                I only had 3 people
                       2 hours                            arrive for auditions. 2
                                                          of the 3 were
                                                          incapable of playing
                                                          at the level of the
                                                          work.

 September 17, 2012    3:50 pm   First Interest Meeting   This was also used
                       1 hour                             as a makeup for
                                                          auditions in case
                                                          someone was still
                                                          interested. No one
                                                          showed up for the
                                                          interest meeting.

 September 20, 2012    6 pm      Last meeting, last       I was hoping that
                       1 hour    minute auditions.        somebody would
                                                          show up, but nobody
                                                          did. I had to now alter
                                                          the entire project.

 September 20, 2012    10pm      First email with         I needed to explain to
                                 Senior Project           her that I did not have
                                 Facilitator              any participants for
                                                          my project. That I
                                                          now had no one to
                                                          perform, and I had to
                                                          change the project
                                                          completely.

 September 22, 2012    11am      Skype call with my       During this time we
                       6 hours   senior project           went over
                                 facilitator.             possibilities for the
                                                          project, and
                                                          alternatives. During
                                                          this time, we
                                                          concluded that the
                                                          product will just have
to be the piece in
                                                             itself. There is no way
                                                             to make players fall
                                                             out of thin air. New
                                                             project: Composing a
                                                             saxophone quartet
                                                             piece without
                                                             performers.

September 23, 2012    10am          Composing
                      4 hours

September 24, 2012    Nothing       Nothing                  This time was jam
through October 19,                                          packed with
2012.                                                        marching band. After
                                                             school, during
                                                             school, and
                                                             weekends were
                                                             absorbed with
                                                             Marching band, so no
                                                             real productive
                                                             amount of time was
                                                             spent composing
                                                             during this time.

October 25, 2012      4:16 pm       Updated Senior
                                    Project facilitator on
                                    composition.

October 27, 2012      6pm           First run through        This was the first
                      2 hours                                crucial edit to the
                                                             piece. I used the
                                                             program “Noteflight”
                                                             so that she could
                                                             view the project as it
                                                             progressed. She
                                                             checked for errors
                                                             and told me if I could
                                                             continue or not.

November 3, 2012      10am          Composition              This was a rough
                      4 hours                                time. I started and
                                                             restarted
                                                             compositions at least
                                                             14 times.

November 10, 2012     10am          Composition
                      4 hours

November 10, 2012     4pm 2 hours   Run through              Melanie told me that
everything I was
                                                  writing was out of
                                                  order. So, at this
                                                  time, I realized that I
                                                  cannot go such a
                                                  long time without
                                                  contacting her in
                                                  order to conserve
                                                  time and prevent
                                                  giant hiccups.

November 24, 2012   9am       Composition Skype   This time was spent
                    7 hours   call with Melanie   going back and forth
                                                  over the CORRECT
                                                  way to write. During
                                                  this time, I learned so
                                                  much about myself
                                                  and how to write.

November 25, 2012   5pm       Composition
                    1 hour

November 26, 2012   6pm       Composition
                    1 hour

November 27, 2012   11pm      Composition
                    1 hour

November 29, 2012   9pm       Skype call run      Melanie was very
                    2 hours   through             pleased about what I
                                                  had, and I could
                                                  finally move forward
                                                  confidently.

December 3, 2012    7pm       Composition
                    1 hour

December 4,         Nothing                       This time was spent
2012­January 29,                                  with my church and
2012                                              missions team. I lead
                                                  2 praise bands, 2
                                                  youth groups, a GED
                                                  class, a young
                                                  woman’s bible study,
                                                  and I am with my
                                                  mission’s team. This
                                                  Holiday time is a time
                                                  of giving back to the
                                                  community. I spent a
                                                  huge amount of time
in the community
                                                      serving and feeding
                                                      the homeless in Holly
                                                      Springs, caroling at
                                                      the nursing home,
                                                      involved in dramas at
                                                      my church to portray
                                                      the Christmas story,
                                                      and serving in all
                                                      services at the
                                                      church
                                                      instrumentally, and
                                                      vocally.


January 31, 2013    7pm       Run through Skype       Picked up on
                    3 hours   call                    composition and
                                                      touched base with
                                                      Melanie about where I
                                                      was in my project.

February 6, 2013    8pm       Composition and         This is the end of the
                    6 hours   finishing touches and   composition process.
                              run throughs with
                              Melanie

February 8, 2013    9pm       Email                   Melanie explains to
                                                      me that my counter
                                                      Alto line is in the
                                                      wrong key and I need
                                                      to start over on the
                                                      Alto line. I made sure
                                                      to get EXACTLY what
                                                      she wanted to
                                                      prevent future
                                                      mistakes.

February 10, 2013   10am      Tried to get in contact I finished the
                              with Melanie, no        alterations, but I could
                              reach.                  not get in touch with

                                                      Melanie.
February 11,                  Tried to get in contact I called, texted, and
2013­February 20,             with Melanie.           emailed Melanie
2013                                                  almost religiously
                                                      with no response.

February 21, 2013   3:17 pm   Email                   Melanie emails me

February 24, 2013   2:14 am                           Melanie passed
away.

March 3, 2013    12:16 pm   Phone call            I got Robert Brown to
                                                  step in as my project
                                                  facilitator.

March 5, 2013    7pm        Meeting with Robert   All parts of the
                 1 hour                           composition are
                                                  correct. Project
                                                  complete.

March 11, 2013   8am        Printed parts

March 11, 2013   7pm        Laminated and
                            framed parts

More Related Content

Viewers also liked

Viewers also liked (12)

Statins (report biopharm) Pravastatin and Rosuvastatin
Statins (report biopharm) Pravastatin and RosuvastatinStatins (report biopharm) Pravastatin and Rosuvastatin
Statins (report biopharm) Pravastatin and Rosuvastatin
 
Dyslipidaemia
DyslipidaemiaDyslipidaemia
Dyslipidaemia
 
Crestor Presentation
Crestor PresentationCrestor Presentation
Crestor Presentation
 
Rosuvastatin final marketing plan
Rosuvastatin final marketing planRosuvastatin final marketing plan
Rosuvastatin final marketing plan
 
Statin
StatinStatin
Statin
 
Lipid lowering trials ppt
Lipid lowering trials pptLipid lowering trials ppt
Lipid lowering trials ppt
 
Pharmacology: Anti hyperlipidemic drugs flashcards
Pharmacology: Anti hyperlipidemic drugs flashcardsPharmacology: Anti hyperlipidemic drugs flashcards
Pharmacology: Anti hyperlipidemic drugs flashcards
 
Dyslipidemia
DyslipidemiaDyslipidemia
Dyslipidemia
 
Hyperlipidemia
HyperlipidemiaHyperlipidemia
Hyperlipidemia
 
Hyperlipidemia
Hyperlipidemia Hyperlipidemia
Hyperlipidemia
 
Hyperlipidemia
HyperlipidemiaHyperlipidemia
Hyperlipidemia
 
Hyperlipidemia and drug therapy for hyperlipidemia
Hyperlipidemia and drug therapy for hyperlipidemiaHyperlipidemia and drug therapy for hyperlipidemia
Hyperlipidemia and drug therapy for hyperlipidemia
 

More from sydsolano

Product Pictures
Product PicturesProduct Pictures
Product Picturessydsolano
 
Sp solanosydney7@gmail.com - gmail
Sp   solanosydney7@gmail.com - gmailSp   solanosydney7@gmail.com - gmail
Sp solanosydney7@gmail.com - gmailsydsolano
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Postersydsolano
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Postersydsolano
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Postersydsolano
 
Senior Project Commitment Poster
Senior Project Commitment Poster Senior Project Commitment Poster
Senior Project Commitment Poster sydsolano
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Postersydsolano
 
Senior Project Proposal Form 2012 13
Senior Project Proposal Form 2012 13Senior Project Proposal Form 2012 13
Senior Project Proposal Form 2012 13sydsolano
 

More from sydsolano (8)

Product Pictures
Product PicturesProduct Pictures
Product Pictures
 
Sp solanosydney7@gmail.com - gmail
Sp   solanosydney7@gmail.com - gmailSp   solanosydney7@gmail.com - gmail
Sp solanosydney7@gmail.com - gmail
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Poster
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Poster
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Poster
 
Senior Project Commitment Poster
Senior Project Commitment Poster Senior Project Commitment Poster
Senior Project Commitment Poster
 
Senior Project Commitment Poster
Senior Project Commitment PosterSenior Project Commitment Poster
Senior Project Commitment Poster
 
Senior Project Proposal Form 2012 13
Senior Project Proposal Form 2012 13Senior Project Proposal Form 2012 13
Senior Project Proposal Form 2012 13
 

Untitleddocument

  • 1. Product Work Log 2012­2013 Name: Sydney Solano Date: Product: Saxophone Quartet Date Time Activity Comments September 10, 2012 4:30 pm Auditions I only had 3 people 2 hours arrive for auditions. 2 of the 3 were incapable of playing at the level of the work. September 17, 2012 3:50 pm First Interest Meeting This was also used 1 hour as a makeup for auditions in case someone was still interested. No one showed up for the interest meeting. September 20, 2012 6 pm Last meeting, last I was hoping that 1 hour minute auditions. somebody would show up, but nobody did. I had to now alter the entire project. September 20, 2012 10pm First email with I needed to explain to Senior Project her that I did not have Facilitator any participants for my project. That I now had no one to perform, and I had to change the project completely. September 22, 2012 11am Skype call with my During this time we 6 hours senior project went over facilitator. possibilities for the project, and alternatives. During this time, we concluded that the product will just have
  • 2. to be the piece in itself. There is no way to make players fall out of thin air. New project: Composing a saxophone quartet piece without performers. September 23, 2012 10am Composing 4 hours September 24, 2012 Nothing Nothing This time was jam through October 19, packed with 2012. marching band. After school, during school, and weekends were absorbed with Marching band, so no real productive amount of time was spent composing during this time. October 25, 2012 4:16 pm Updated Senior Project facilitator on composition. October 27, 2012 6pm First run through This was the first 2 hours crucial edit to the piece. I used the program “Noteflight” so that she could view the project as it progressed. She checked for errors and told me if I could continue or not. November 3, 2012 10am Composition This was a rough 4 hours time. I started and restarted compositions at least 14 times. November 10, 2012 10am Composition 4 hours November 10, 2012 4pm 2 hours Run through Melanie told me that
  • 3. everything I was writing was out of order. So, at this time, I realized that I cannot go such a long time without contacting her in order to conserve time and prevent giant hiccups. November 24, 2012 9am Composition Skype This time was spent 7 hours call with Melanie going back and forth over the CORRECT way to write. During this time, I learned so much about myself and how to write. November 25, 2012 5pm Composition 1 hour November 26, 2012 6pm Composition 1 hour November 27, 2012 11pm Composition 1 hour November 29, 2012 9pm Skype call run Melanie was very 2 hours through pleased about what I had, and I could finally move forward confidently. December 3, 2012 7pm Composition 1 hour December 4, Nothing This time was spent 2012­January 29, with my church and 2012 missions team. I lead 2 praise bands, 2 youth groups, a GED class, a young woman’s bible study, and I am with my mission’s team. This Holiday time is a time of giving back to the community. I spent a huge amount of time
  • 4. in the community serving and feeding the homeless in Holly Springs, caroling at the nursing home, involved in dramas at my church to portray the Christmas story, and serving in all services at the church instrumentally, and vocally. January 31, 2013 7pm Run through Skype Picked up on 3 hours call composition and touched base with Melanie about where I was in my project. February 6, 2013 8pm Composition and This is the end of the 6 hours finishing touches and composition process. run throughs with Melanie February 8, 2013 9pm Email Melanie explains to me that my counter Alto line is in the wrong key and I need to start over on the Alto line. I made sure to get EXACTLY what she wanted to prevent future mistakes. February 10, 2013 10am Tried to get in contact I finished the with Melanie, no alterations, but I could reach. not get in touch with Melanie. February 11, Tried to get in contact I called, texted, and 2013­February 20, with Melanie. emailed Melanie 2013 almost religiously with no response. February 21, 2013 3:17 pm Email Melanie emails me February 24, 2013 2:14 am Melanie passed
  • 5. away. March 3, 2013 12:16 pm Phone call I got Robert Brown to step in as my project facilitator. March 5, 2013 7pm Meeting with Robert All parts of the 1 hour composition are correct. Project complete. March 11, 2013 8am Printed parts March 11, 2013 7pm Laminated and framed parts