Bulk Solar Power Generation :CSP and CPV technologies

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

5 comments

Comments 1 - 5 of 5 previous next Post a comment

  • + dangthanh1 dangthanh1 1 month ago

  • + fnuno fernando nuño 2 years ago
    Desalination using CSP / CPV.

    The concept of combined heat and power (CHP, also known by cogeneration) using a CSP power plant seems attractive for applications such as desalination. Indeed, instead of assuming a big duty for condensers, it would be more useful to use this residual heat to generate a worthy product.

    Multiple Effect Desalination (MED) would be the appropriate technology to be coupled with CSP plant. The required thermal energy is 50-100 kWh/m3, which comes from the steam at 0.35 bar from steam turbine. This leads to a reduction in Rankine cycle efficiency of about 5% to 10%. Electrical energy requirement is 1,5 – 2,5 kWh/m3.

    Reverse Osmosis (RO) only needs electrical energy: 4 to 6 kWh/m3, depending on salinity.

    In these conditions MED make sense coupled with CSP. RO could operate with CPV. Desalination would provide a good solution for solar variability, as demand can be modulated. Additional flexibilities exist with CSP, such as thermal storage and fossil or biomass fuel complement.

    A good benchmark report is available at : http://www.dlr.de/tt/aqua-csp
  • + fnuno fernando nuño 2 years ago
    In dry climates cooling is assured by air heat exchangers (avoiding the high water consumption from wet cooling towers). This solution needs a very high ventilation, which increases considerably the auxiliary electricity consumption. Additionally, the efficiency of Rankine cycle is reduced, as the outlet pressure of steam turbine is relatively higher (due to higher cooling temperature : ambient air – in general 30ºC to 45ºC – plus delta T from heat exchanger – 10ºC or more - ).
  • + fnuno fernando nuño 2 years ago
    Dear Mr Lausten,

    Water consumption figure comes from a reference Project under construction in Puertollano (Spain) by Iberdrola Renovables. The main characteristics are :
    • Installed Power : 50 MWe
    • Electricity generation : 114,2 GWh/year
    • Electricity consumption for auxiliaries : 11 GWh/year
    • Natural Gas support : 15% - 59 GWh / year
    • Capacity factor : 2062 hours (out of 8760)
    • Water consumption : 570 000 m3/year
    • Construction began : March 2007
    • Start operation in : end 2008

    From a thermodynamic point of view, considering a rankine cycle with efficiency of 25%, the generation of 1 MWh of electricity needs a heat evacuation of 3 MWh. This needs the vaporization of 4,4 m3 of water in a cooling tower. So we have already 4.4 m3. Add some water for mirrors cleaning and miscellaneous use and you reach very quickly 5 m3 / MWh.

    Please contact me for further inquiries (fng@eurocopper.org)

    Kind regards

    Fernando Nuño
  • + guestc25478 guestc25478 2 years ago
    Mr. Nuno:



    Question for you on Slide 30. Water consumption of 6m^3 / MWh seems high. How do you arrive at that consumption rate?



    Thanks,



    Mark W Lausten

    mark.lausten@ee.doe.gov
Post a comment
Embed Video
Edit your comment Cancel

12 Favorites & 1 Group

Bulk Solar Power Generation :CSP and CPV technologies - Presentation Transcript

  1. June 08 Bulk Solar Power Generation : CSP and CPV technologies Fernando Nuño European Copper Institute [email_address]
  2. Index
    • Solar energy : why should it make sense?
    • Definitions
    • CSP review
      • Technology
      • Project Development Issues
      • Generation costs – Market perspectives – Support schemes
    • CPV review
      • Technology
      • Generation costs – Market perspectives
    • Ratios and comparisons
  3. Solar resource available : much more than we need The Earth receives from solar radiation in 10 days as much energy as the known fossil reserves
  4. Solar roadmap – Increasing role in the coming years
  5. Where does concentration technology make sense? Annual Direct Normal Irradiation Source : NASA
  6. Where does concentration technology make sense? Source : Schott Solar
  7. The potential of Mediterranean basin
    • North Africa has an enormous potential. Interconnections with Europe could be then developed
    Sources : Eurelectric 2007 German Federal Ministry for the Environment, Nature Conservation and Nuclear Safety
  8. Why solar energy fits well in hot climates Spanish average load profile vs average irradiation Source : Red Eléctrica de España
  9. Index
    • Solar energy : why should it make sense?
    • Definitions
    • CSP review
      • Technology
      • Project Development Issues
      • Generation costs – Market perspectives – Support schemes
    • CPV review
      • Technology
      • Generation costs – Market perspectives
    • Ratios and comparisons
  10. Solar technologies and market share
  11. Utility scale technologies CSP CPV
    • CONCENTRATION SOLAR POWER : thermal process
      • Heating a fluid
      • Generating mechanical power through a thermodynamic cycle (rankine, brayton, stirling…)
      • Converting mechanical power into electrical power (alternator)
    • CONCENTRATION PHOTOVOLTAICS : photovoltaic process
      • Concentrate solar radiation on the PV cell
      • Direct generation of electrical power
  12. Index
    • Solar energy : why should it make sense?
    • Definitions
    • CSP review
      • Technology
      • Project Development Issues
      • Generation costs – Market perspectives – Support schemes
    • CPV review
      • Technology
      • Generation costs – Market perspectives
    • Ratios and comparisons
  13. CSP Technology overview Parabolic Troughs Parabolic Dishes with Stirling Engine Central Tower Fresnel Concentrators
  14. CSP Technology review Parabolic Troughs Structure Parabolic Mirror Receiver
  15. CSP Technology review Parabolic Troughs Solar Field Power Block
  16. CSP Technology review HFT (Heat Transfer Fluid) Technology in commercial operation Parabolic Troughs Melted Salts Hot Storage Solar Field Melted Salts Cold Storage Steam Generator Steam Turbine Superheated Steam (100 bar, 380ºC) Reheated Steam (17 bar, 371ºC) Condenser Pre-heater Re-heater Oil Expansion Tank Deaerator Oil 395ºC Oil 295ºC
  17. CSP – Technology review
    • Steam is generated directly in the collecting solar field, so no need for heat exchange, reducing costs and increasing efficiency
    Parabolic Troughs DSG (Direct Steam Generation) Coming soon…
  18. CSP : Project Development – Site issues Meteorological compliance
    • DNI > 1800 kWh/m2/year
    • Measurement campaign required
    Access to electricity and gas grid Access to water Flat land available
    • No special interest zone (urban, industrial, environmental protection)
    • Absolutely flat for parabolic troughs
    Local authorities
    • Should accept and support the project
    • In sunny places there is strong competition for water use!
    • Impact of cost of building a dedicated electrical line to reach the main grid
    • Gas : required to maintain temperatures during the night (other fuels can be considered for isolated zones)
  19. CSP : Project Development – Site issues Typical configurations Solar Field Power Block
  20. CSP : Project Development – Administrative issues Request for Administrative Authorisation Environmental impact analysis Public Information Obtaining Administrative Authorisation Consultation to affected entities
    • Responses to this publication
    • Reply to responses
    Request for Project Approval Construction permits Maturing period : 18 months
  21. CSP : Project Development – Engineering, Procurement & Construction Preliminary Basic Engineering Basic Equipment Purchase Construction contracts In-Depth Engineering Supply of equipment - Construction Commissioning and test period Execution period : 24 months Maturing + Execution period : 36 - 44 months
  22. CSP : Project Development – Grid Access Guarantee: 20 €/kW Request to recognition of dispatchability RE – PO 08/2007 (see next slide) Request for Access to the grid TSO provides the conditions for grid access Spanish System Project Developer presents its project Project Developer asks for connection point TSO provides connection point
  23. CSP : Project Development – Grid Access Dispatchability RE – PO 08/2007 Spanish System
    • Installation controlled from the dedicated TSO dispatching center
    • Program reliability:
    • 90% at 24 h horizon
    • 95% at 6h horizon
    Required conditions
    • Storage ability: 4h
    • Energy restitution efficiency : 60%
    • Voltage dip ride-through ability (voltage dip up to 1 second)
    Benefits
    • Less requirements and more guarantees to obtain access to the grid
    • Participation in ancillary services markets
    • Project Developper can make the choice to go for storage or not, so making its installation dispatchable or not.
    • If not dispatchable, grid access seems more difficult to obtain and would be subject to curtailments when in operation
  24. CSP : Project Development – Technological issues Mirrors
    • Some companies developing solar projects are developing its own technology, or buying mirror manufacturers
    Absorber Tube Support Structure Thermal storage
    • Manufacturers oligopoly
    • Extremely critical and technical product (lasting vacuum, layers stability, high transmissivity of glass, high absorptivity and low emissivity of absorber, junctions metal/glass, dilatation management…)
    • Several structures available in the market
    • Continuous evolution to comply with alignment requirements at the lowest cost
    • Liquid salts is the technology used for the moment, but many other are in development
  25. CSP - Project Development – Storage optimisation
  26. CSP - Project Development – Contractual structure and Project Finance CONTRACTS Engineering Procurement & Construction (EPC) Turn Key Contract Separated Packages negotiated by Project Developer Operation & Maintenance Grid Connection Fuel Procurement
  27. CSP - Project Development – Contractual structure and Project Finance Turn Key Contract
    • One Main Contractor assumes the whole project and outsource the various packages to other companies
    • Price is negotiated ex-ante and is firm
    • Deadline is negotiated ex-ante and is firm (penalty otherwise)
    • Responsibility : only one visible head
    • One Main Contractor assumes the whole project and outsource the various packages to other companies
    • Responsibility : only one visible head
    • The Main Contractor assumes the work of supervision and coordination
    • 20% more expensive than the option “separated packages negotiated by project developer”
    • To be financed by banks, it is the only contract structure acceptable
    • Financing Entity will obtain from Main Contractor the required guarantees
  28. CSP - Project Development – Contractual structure and Project Finance Contractual Structure Project Developer Financial Entity Legal Advisor Technical Advisor Insurance Advisor Environmental Advisor Turn Key Main Contractor Solar Field Thermal Storage Power Block Civil Work Electrical Systems PROJECT Fuel O&M Insurance Electricity Sales
  29. CSP - Project Development – Contractual structure and Project Finance Main risks associated to CSP seen by Financial Entities
    • Melted Salts Storage
    • Expected generation :
      • Availability and Quality of solar radiation data
      • Thermal storage
      • Hybridizing with NG or biomass
    • Availability of main components (mirrors, absorber tubes)
    • Experience of Main Contractor
    • Regulatory risk: once reached the targets set by the Ministry, no more support is available
  30. CSP - Some ratios 50 MW - Without storage
    • Investment : 3000 €/kW
    50 MW - With storage
    • Annual production : 2050 hours for South Spain
    • Water consumption : 6m3/MWh
    • Gas consumption : 60 GWh /year
    • Collecting surface : 287000 m2, 52 linear km
    • Investment : 4500 €/kW up to 6000 €/kW
    • Annual production : 3000 to 4000 hours – South Spain
    • Collecting surface : increased according to the storage capability
    • Water consumption : 6m3/MWh - 1600 m3/day
    • Gas consumption : > 60 GWh / year
  31. CSP - Support Schemes Spain
    • CSP :
      • Target : 500 MW in 2010
      • Tariff : 278 €/MWh or market price + 262 €/MWh lasting : 25 years
        • After 25 years : 222 €/MWh or market price + 210 €/MWh
    • CPV : integrated to general PV
      • Target of 371 MW reached in 2007 (waiting for provisions for the period up to 2010)
      • Tariff : up to 2007 431 €/MWh – expected 300 €/MWh from September 2008. Lasting : 25 years + reduced tariff after that period
      • Expectations to discriminate CPV from general PV
    • Feed-in tariffs have provided the required confidence to carry out huge investments up to 6000 €/kW
  32. CSP - Support Schemes North Africa
    • Call to bid from national electricity agencies
    • ISCC : Integrated Solar Combined Cycle
      • Excellent way to recover solar energy and optimize its thermodynamic efficiency thanks to higher temperatures reached by burning natural gas
      • ISCC by Abengoa Solar : Morocco 470 MW, Algeria 150 MW
  33. CSP - Support Schemes USA
    • State requirements RPS (Renewable Portfolio Standards) + remuneration based on PPA negotiation (Power Purchase Agreements) + pluri-annual Federal ITC application (Investment Tax Credit)
    • April 2008 : Pacific Gas & Electric Company (PG&E) subscribes a firm contract to buy electricity generated by solar plants in Mojave Desert : 500 MW + 400 MW optional
    • February 2008 : Arizona Public Service (APS) signs a contract with Abengoa Solar to buy electricity from a 280 MW solar power plant
    • SEGS series from 80’s : more than 300 MW with more than 2 0 years experience on parabolic trough technology
  34. CSP – Current growth
    • Only in Spain, there will be confirmed firmly more than 1000 MW during 2008
  35. CSP – Market expectations
    • According to German Aerospace Center (DLR), CSP has a growth potential of 40 GW by 2030
  36. CSP – Market expectations
    • Much more optimistic, ESTELA, the European Solar Thermal Electricity Association, sees room for 60 GW by 2030 only in Europe…
  37. CSP – Cost expectations
    • According to ESTELA, the European Solar Thermal Electricity Association, only a moderate reduction in the levelized cost of energy can be expected due to high increase of raw materials such as steel and concrete
  38. Index
    • Solar energy : why should it make sense?
    • Definitions
    • CSP review
      • Technology
      • Project Development Issues
      • Generation costs – Market perspectives – Support schemes
    • CPV review
      • Technology
      • Generation costs – Market perspectives
    • Ratios and comparisons
  39. CPV - General features
    • In spite of its childhood (much less mature than CSP), already several MW installed around the world
    • The big cost reduction is still to come thanks to mass production
    • Doesn’t need cooling water (except some special applications)
    • Modular and scalable technology
  40. CPV – The strategy
    • Substitution of the expensive semiconductor material with a cheap optical system and low-cost mechanics
    • Use of best efficiency cells
  41. CPV - Advantages No water needs Time to Operation Less sensitive to hot climates Modular / Scalable
  42. CPV - Disadvantages Sensitivity to clouds No easy storage ability
    • These two issues together should be solved, as TSO cannot accept sharp fluctuations in the generated power
  43. CPV – Components: Cells - Triple junction cells
    • The principle is that each material operates at different wavelengths, the three covering a large spectrum
  44. CPV – Components: Cells - Technology evolution
    • In 2009 an average production efficiency higher than 40% will be the rule for multijunction cells
  45. CPV – Components: Concentrator - Technologies Lens Mirror Low Concentration Cassegrain
  46. CPV – Components: Concentrator - Technologies Central tower CPV Developed by Solar Systems in Australia
  47. CPV – Components: Tracking system
    • Light need to be focused at the cell, not close to the cell
    • The higher concentration ratio, the lower angle tolerance
    • In practice, 0.1% accuracy is currently reached
    • Solid structures are required
    • New structural concepts are being developed
    Need for increased accuracy
  48. CPV – Potential for cost reduction Flat PV : module reaches 45% of cost share 40% of remaining costs are proportional to area
    • Reductions in module cost and required area would lead to drastic decrease of Levelized Cost of Energy
    Source : Concentrix
  49. CPV – Area reduction For the same surface, almost 50% more installed power To reach the same power, 30% less need for materials
  50. CPV – Cost reduction expectations Investment costs to be cut by 3 in 10 years Source : Concentrix
  51. CPV – Cost reduction targets
  52. CPV – Market growth – some examples EMCORE
  53. CPV – Market growth – some examples GUASCOR FOTON
  54. CPV – Market growth – some examples SOL 3G
  55. Index
    • Solar energy : why should it make sense?
    • Definitions
    • CSP review
      • Technology
      • Project Development Issues
      • Generation costs – Market perspectives – Support schemes
    • CPV review
      • Technology
      • Generation costs – Market perspectives
    • Ratios and comparisons
  56. Comparative CSP - CPV 2 2 2 – 2,5 (more if storage) 2,5 – 3 (more if storage) Land use (Ha / MW) No water No water Similar to parabolic trough 6 m3/MWh Water consumption No Possible (any fuel) Possible (any fuel) Possible (any fuel) Hybrid design No ? Thermal : Possible Thermal : Possible Integrated Storage Yes, with huge amounts of MW available in coming years Only prototypes Soon Yes Commercially available Current : 25 % Soon : > 30 % 31% 23% 21% System Efficiency (electricity / solar) PV effect, no thermal 700ºC 600ºC 395ºC Operating Temperature 10 kW – 20 kW per tracker. Scalable 5 – 40 kW per dish. Scalable 20 – 100 MW 20 – 300 MW Power Range CPV Stirling parabolic dish Central tower Parabolic troughs
  57. Comparative CSP - CPV 120 – 150 €/MWh in South Europe. Lower in sunnier locations In line with parabolic troughs In line with parabolic troughs 200 €/MWh in South Europe. Lower in sunnier locations Expected LCOE by 2020 300 €/MW in Souht Europe. Lower in sunnier locations ? ? 260 €/MWh in South Europe – 180 €/MWh in MENA Current LCOE (Levelized Cost of Energy) 6 – 7 €/W 14 €/W 4 – 6,5 €/W 4 – 6 €/W (according to storage size) Current investment cost CPV Stirling parabolic dish Central tower Parabolic troughs
  58. References
    • CSP summit – Madrid February 2008 – Intereconomía Conferencias
    • CPV summit, Madrid 1-2 April 2008 (http://www.cpvtoday.com/index.shtml)
    • http://www.schott.com/csp/english/download/schott_memorandum_e.pdf
    • http://www.wbgu.de/wbgu_publications_annual.html
    • http://www.eupvplatform.org/
    • http://www.csptoday.com/
  59. Thank you!

+ Hans De KeulenaerHans De Keulenaer, 2 years ago

custom

10624 views, 12 favs, 4 embeds more stats

Thin film, silicon, concentrated solar power (CSP), more

More info about this document

© All Rights Reserved

Go to text version

  • Total Views 10624
    • 10306 on SlideShare
    • 318 from embeds
  • Comments 5
  • Favorites 12
  • Downloads 1127
Most viewed embeds
  • 314 views on http://www.leonardo-energy.org
  • 2 views on http://leonardo-energy.org
  • 1 views on http://dev.leonardo-energy.org
  • 1 views on http://colfaxtest.wordpress.com

more

All embeds
  • 314 views on http://www.leonardo-energy.org
  • 2 views on http://leonardo-energy.org
  • 1 views on http://dev.leonardo-energy.org
  • 1 views on http://colfaxtest.wordpress.com

less

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

Cancel
File a copyright complaint
Having problems? Go to our helpdesk?

Categories