Project Monitoring & Control Systems

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    2 Favorites

    Project Monitoring & Control Systems - Presentation Transcript

    1. PROJECT MONITORING & CONTROL SYSTEMS
    2. PROJECT MONITORING
      • Project Monitoring
      • - Tracking Progress
      • -Comparing actual to predicted
      • -Analyzing impact
      • - Making Adjustments
    3. REQUIREMENTS
      • Forecast problems early enough to take corrective actions.
      • Stimulate alternate plans
      • Integrate time, cost & performance considerations.
      • Accurate
      • Cost effective
    4. GANTT CHART
    5. GANTT CHART
    6. NETWORK ANALYSIS
      • Shows the interdependence of tasks
      • Estimates the project duration
      • Determine the critical path
      • Determine slack in the paths
    7. PERT
      • Basis for planning & predicting : Resource utilization
      • Handle uncertainties : Impact of delay in project completion
      • Basis for estimating resource requirements
      • Basis for reporting information
    8. STEPS TO DEVELOP NETWORK
      • WBS
      • Establish interdependence of all tasks
      • Precedence table
    9. NETWORK COMPONENTS
    10. NETWORK COMPONENTS
      • EVENT : Point in time of start or end of an activity .An event is achieved when all activities leading to the event are completed.
      • ACTIVITY : Design, procurement, production , decision making etc. Indicates use of time, manpower ,utilities, space etc. Activities represent work & waiting time .
    11. DEPENDENCIES
      • Mandatory dependency : roof & wall
      • Discretionary dependency : Bill of material before purchase
      • External dependency : Beyond the control of the project manager
    12. DUMMY ACTIVITY
    13. ELAPSED TIME
      • Optimistic time – a
      • Most likely time – m
      • Pessimistic time – b
      • te = (a+4m+b)/6
    14. ACTIVITY
    15. EXAMPLE 1
    16. EXAMPLE 1
    17. EXAMPLE 1
    18. EXAMPLE 1
    19. EXAMPLE 1
    20. NEGATIVE SLACK
    21. NEGATIVE SLACK
      • Original plan was optimistic
      • Customer’s end date was unrealistic
      • One or more activities slipped during project implementation
      • The assigned resources did not possess the required skill
      • The required resources will not be available until a later date
    22. CRITICAL PATH METHOD
      • Arrow diagram
      • Activities as nodes.
      • For each activity normal time, crash time & related costs are estimated.
    23. TIME COST RELATIONSHIP
    24. DEFINITIONS
      • Normal time
      • Normal cost
      • Crash time
      • Crash Cost
    25. ASSUMPTIONS
      • Time-cost trade-off points are on a linear curve
      • Buying time on one activity is independent of the same in any other activity
    26. CPM
      • Emphasis is on activities
      • Activities as nodes
      • Both time & cost are considered
      • Start with the minimum crashing cost
    27. ENVIRONMENT
      • Well defined projects
      • Easy to measure % completion
      • Relatively less uncertainties
      • One geographical location of the project
    28. OPTIMAL ACCELERATION PLAN
      • Critical path
      • Examine slope of each activity in critical path
      • Attain minimum time
      • If another path becomes critical, revaluate the new critical path.
    29. CPM
    30. CPM

    + Srinu MSrinu M, 3 years ago

    custom

    6670 views, 2 favs, 2 embeds more stats

    Project Monitoring & Control Systems

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 6670
      • 6551 on SlideShare
      • 119 from embeds
    • Comments 0
    • Favorites 2
    • Downloads 624
    Most viewed embeds
    • 117 views on http://www.projectmanagementcampus.com
    • 2 views on http://www.gigamon.com

    more

    All embeds
    • 117 views on http://www.projectmanagementcampus.com
    • 2 views on http://www.gigamon.com

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories