• Share
  • Email
  • Embed
  • Like
  • Save
  • Private Content
Scrum to Scrumban Migration
 

Scrum to Scrumban Migration

on

  • 3,401 views

Scrum to Scrumban Migration

Scrum to Scrumban Migration

Statistics

Views

Total Views
3,401
Views on SlideShare
2,671
Embed Views
730

Actions

Likes
4
Downloads
0
Comments
0

7 Embeds 730

http://skillsmatter.com 663
http://smash 38
http://www.slideshare.net 16
http://localhost 10
https://spitfire.ordnancesurvey.co.uk 1
http://blog.thirstybear.co.uk 1
http://sm-website-dev.herokuapp.com 1
More...

Accessibility

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Scrum to Scrumban Migration Scrum to Scrumban Migration Presentation Transcript

    • Scrum to Scrumban Confessions of a Kanban Virgin Chris Pitts Thursday, 11 March 2010
    • Scrum to Scrumban • How things were working & the problems • How to change • Pros and Cons • What next? Thursday, 11 March 2010
    • The starting point 1 week Thursday, 11 March 2010
    • A typical week •Every day standup •Every week Stakeholder demo Retrospective Planning Game Thursday, 11 March 2010
    • Thursday, 11 March 2010
    • Thursday, 11 March 2010
    • Q. How many columns? Thursday, 11 March 2010
    • Q. What are our WIP Limits? • 6 developers, 1 QA • Interested in limited pairing • Need to find the “Goldilocks Value” Thursday, 11 March 2010
    • Option 1 - 7 in flight Thursday, 11 March 2010
    • Option 2 - 4 in flight Thursday, 11 March 2010
    • Option 2 - 4 in flight Thursday, 11 March 2010
    • The Initial Board Thursday, 11 March 2010
    • Problems! WIP Violation Thursday, 11 March 2010
    • Problems! WIP Violation Thursday, 11 March 2010
    • Problems! BLOCKED! Thursday, 11 March 2010
    • Problems! BLOCKED! Thursday, 11 March 2010
    • Cycle Time Thursday, 11 March 2010
    • Cycle Time Thursday, 11 March 2010
    • Evolution Thursday, 11 March 2010
    • Side Effects • Weekly stakeholder demos retained • Weekly retrospectives retained • Team and Product Owner conversations happened naturally & frequently Thursday, 11 March 2010
    • Side Effects • Weekly stakeholder demos retained • Weekly retrospectives retained • Team and Product Owner conversations happened naturally & frequently • Confusion over how to explain to external Gantt chart fetishists... Thursday, 11 March 2010
    • Natural Evolution • Instead of holding weekly formal retrospectives, retrospect and fix problems as they happen. “KAIZEN” Thursday, 11 March 2010
    • Where are they now? Thursday, 11 March 2010
    • Questions? Thursday, 11 March 2010