Your SlideShare is downloading. ×
0
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Moffett RAB Site 25 Update
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

Moffett RAB Site 25 Update

388

Published on

Update on Site 25 stormwater retention pond clean-up by Bryce Bartelma at the August 9, 2012, meeting of the Moffett Restoration Advisory Board.

Update on Site 25 stormwater retention pond clean-up by Bryce Bartelma at the August 9, 2012, meeting of the Moffett Restoration Advisory Board.

Published in: Education, Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
388
On Slideshare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Former NAS Moffett FieldSite 25 Remedial Action Update Bryce Bartelma, PG Navy BRAC PMO West August 9, 2012 RAB Meeting
  • 2. IR Site 25IR Site 25 encompasses approximately 230 acres and was constructed for use as part of the Moffett Field storm water management system since 1953 AOI-14 The Navy is coordinating remedial action activities with NASA as they prepare to conduct their cleanup activities at Area of Investigation (AOI)-14 2
  • 3. Remedial Design and Remedial Action Work Plan• Final Remedial Design and Remedial Action Work Plan (RD/RAWP) distributed on March 30• Removal of over 32,500 cubic yards of sediment from nearly 32 acres• Planned excavation depths of 0.5 – 1.5 feet below ground surface• Restore vegetated areas with pickleweed and other native grass 3
  • 4. April 2012 Conditions at IR Site 25 4
  • 5. Step 1: Temporarily Re-routeStorm Water & WATS effluent Storm Water Settling Vault Catch Basin 5
  • 6. August 2012 Conditions at IR Site 25 6
  • 7. August 2012 Conditions at IR Site 25 7
  • 8. Step 2: Additional Water Management?• No immediate plans to coffer dam the site if weather stays dry• Water table just beneath ground surface• Working with USFWS to potentially lower water table locally in ponds adjacent to site 8
  • 9. Balancing the Water Table 9
  • 10. Biological Observations at Site 25 NESTING• Alameda Song Sparrow• Western Harrier• Mockingbird, marsh wren, bushtit and killdeer OBSERVED• Harvest Mice (unidentified subspecies)• Deer Mice & Voles• California Least Tern (in flight)• Black Rail (vocalizing)• Fox, jackrabbit, and gopher snake NOT OBSERVED• Western Pond Turtle (WPT)• Western Snowy Plover• California Clapper Rail 10
  • 11. Biological Protection Measures PROTECTION MEASURES 1. Visually inspect/clear vegetation prior to removal 2. Hand remove pickleweed 3. Silt fencing along access points and suitable habitat areas 4. Continuous biological monitoring 5. Coordination with CDFG and USFWS 11
  • 12. Sediment Excavations • Planned excavation depths of 0.5 – 1.5 feet below ground surface • Field verification for dig depth • Grid confirmation sampling 12
  • 13. Vegetation Restoration• All vegetation areas removed during Remedial Action will be Pickleweed restored (excludes EDM and Salicornia inundated mud flats) virginica• Two main types of vegetation• Minimum of two years monitoring and maintenance Saltgrass• Options for irrigation services and Distichlis additional plantings spicata 13
  • 14. Schedule• Vegetation Removal Prep Nearing Completion• Biological Surveys and Sediment Excavations Ongoing• Vegetation Restoration Fall 2012• Submit Remedial Action Completion Report Spring 2013 14
  • 15. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 15

×