Moffett Federal Facilities Agreement - Presentation Transcript
Federal Facilities Agreement Schedule
Restoration Advisory Board
Former NAS Moffett Field
November 12, 2009
Kathryn Stewart, PE
BRAC Environmental Coordinator
BRAC Program Management Office West
1
Federal Facilities Agreement
• Moffett Field FFA- Negotiated legal agreement
– Effective Aug 1990, Amended Dec 1993
– Between the USEPA, the State of CA, and the Navy
• Purposes
– Ensures Navy investigates environmental impacts and and takes
appropriate action
– Establishes procedural framework and schedule
– Facilitates cooperation, exchange of information, and
participation
2
Schedules
• Timetables and deadlines for submittal of draft primary
documents
– Primary documents- major, discrete portions of RI/FS or RD/RA
activities
– Secondary documents- Feeder documents
• Generally:
– Navy submits draft report by established deadline
– 60 day Agency review and comment period
– 60 day period for Navy response to comments and submission
of the draft final
– Draft final becomes final if no party invokes dispute resolution
within 30 days
3
FFA Schedule Update
• Updated Annually
• Schedule for Fiscal Year 2010 submitted 2 October 2009
– FFA Schedule
– Petroleum Site Schedule
• Dates of Note:
– Site 25 ROD Signature: Nov 2009
– Site 26 Pilot Test Tech Memo: Aug 2010
– Site 27 RACR: Jan 2010
– Site 28 Pilot Test Work Plan: Dec 2009
– Site 29 Removal Action: Feb 2010
– Site 14 Work Plan: Dec 2009
4