Former NAS Moffett Field
September 10, 2009 - Moffett RAB Meeting
     Groundwater Program Update
       Presented by Juli...
Presentation Overview
•   Basewide groundwater
     • 2008 annual groundwater report results
     • 2009 groundwater eleva...
Basewide Groundwater - Topics
2008 annual groundwater report submitted in June 2009
   • November and December 2008 ground...
Basewide GW - Plumes

2007 TCE Plume                      2008 TCE Plume
                     Site 28
                 TCE...
Basewide GW - Plumes cont.

2007 TCE Plume                      2008 TCE Plume
                     Site 26
              ...
Basewide GW - WATS
West-side Aquifers Treatment System (WATS)
  2008 operation summary
   • Up-time: 98.9%
   • Treated an...
Basewide GW Report

2008 annual groundwater report highlights
   • Site 28 – collected samples from more wells than previo...
Basewide GW 2009 Work
2009 performed:                       Site 26 Potentiometric Surface Map

Collected basewide
groundw...
Site 26 Pilot Test Status

Background
• Objective is to evaluate the effectiveness of EHC to reduce VOC
  contamination at...
Site 26 Pilot Test - Location




              Note – inset location not to scale   10
Site 26 Pilot Test - Location




                                11
Site 26 Pilot Test Status cont.

Insert a graph or two showing concentration over time




                               ...
Site 26 Pilot Test Status cont.

Preliminary results and trends
• PCE and TCE destroyed to < MCLs at some treatment zone w...
Site 26 Pilot Test Status cont.

Preliminary conclusions
• EHC appears to be effective at completely reducing VOCs to
   i...
Site 28 Pilot Test Approach

Background
• VOC plume commingled with contamination from MEW and NASA
   – Began preparation...
Questions?




             16
Upcoming SlideShare
Loading in …5
×

Moffett Base-Wide Groundwater Update, September 10, 2009

618
-1

Published on

Former Moffett Federal Airfield Base-Wide Groundwater Program Update: Presentation to the Moffett Restoration Advisory Board Meeting September 10, 2009

Published in: Technology
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
618
On Slideshare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
7
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide

Moffett Base-Wide Groundwater Update, September 10, 2009

  1. 1. Former NAS Moffett Field September 10, 2009 - Moffett RAB Meeting Groundwater Program Update Presented by Julie Crosby-Brooks
  2. 2. Presentation Overview • Basewide groundwater • 2008 annual groundwater report results • 2009 groundwater elevation measurements • Site 26 pilot test update • EHC injection complete • Groundwater sampling in progress • Site 28 pilot test update • Pilot test approach 2
  3. 3. Basewide Groundwater - Topics 2008 annual groundwater report submitted in June 2009 • November and December 2008 groundwater sampling • March and November 2008 groundwater elevation measurements • WATS operation summary • Report highlights and conclusions 2009 groundwater elevation measurements 3
  4. 4. Basewide GW - Plumes 2007 TCE Plume 2008 TCE Plume Site 28 TCE GW Plumes Upper Portion of the A Aquifer N 4
  5. 5. Basewide GW - Plumes cont. 2007 TCE Plume 2008 TCE Plume Site 26 TCE GW Plumes Upper Portion of the A Aquifer N 5
  6. 6. Basewide GW - WATS West-side Aquifers Treatment System (WATS) 2008 operation summary • Up-time: 98.9% • Treated and discharged over 36 million gallons of water • Removed approximately 365 pounds of volatile organic compounds (VOCs) • 96% of mass removed is TCE and DCE • Submitted NPDES permit renewal January 2009 • Existing permit is effective in interim • New permit – 10/2/09 6
  7. 7. Basewide GW Report 2008 annual groundwater report highlights • Site 28 – collected samples from more wells than previous year, better definition of plume boundary • Site 26 – pilot test on-going 2008 annual groundwater report conclusions • Site 28 - plume generally stable, overall decreasing VOC trend, groundwater flow continues to be to the north • Site 26 – plume generally stable, overall decreasing VOC trend, groundwater flow continues to be to north - northwest 7
  8. 8. Basewide GW 2009 Work 2009 performed: Site 26 Potentiometric Surface Map Collected basewide groundwater elevation measurements in March 2009 2009 planned/in progress: Well maintenance (locks, bolts, etc.) at wells noted as having deficiencies Basewide GW sampling in November & December Basewide GW elevation measurements in November N 8
  9. 9. Site 26 Pilot Test Status Background • Objective is to evaluate the effectiveness of EHC to reduce VOC contamination at Site 26 – Collect site specific data – Verify ability to cost-effectively reduce VOC contamination to below ROD cleanup levels in a reasonable amount of time Approach • Inject EHC at higher-concentration lobe near Hangar 3 • Collect groundwater samples to evaluate contaminant degradation (baseline, one-month, and quarterly) • Collect performance boring samples to visually confirm radius of EHC injection • Summarize and evaluate in final pilot test/treatability study report 9
  10. 10. Site 26 Pilot Test - Location Note – inset location not to scale 10
  11. 11. Site 26 Pilot Test - Location 11
  12. 12. Site 26 Pilot Test Status cont. Insert a graph or two showing concentration over time 12
  13. 13. Site 26 Pilot Test Status cont. Preliminary results and trends • PCE and TCE destroyed to < MCLs at some treatment zone wells • DCE concentrations increasing • VC – no big change • Performance borings show that EHC was distributed to at least 7 feet from injection point over 80-90% of the vertical profile • Complete dechlorination evident – ethene and ethane production 13
  14. 14. Site 26 Pilot Test Status cont. Preliminary conclusions • EHC appears to be effective at completely reducing VOCs to innocuous chemicals based on ethane and ethene concentrations • DCE is increasing Path Forward • Finish quarterly sampling • Submit final report that evaluates data and recommends path forward 14
  15. 15. Site 28 Pilot Test Approach Background • VOC plume commingled with contamination from MEW and NASA – Began preparation of regional Feasibility Study (FS) – Several parties are conducting pilot tests to augment FS Approach • Additional characterization of potential DNAPL areas – Membrane Interface Probe (MIP) sampling in 3 areas – Navy, EPA, WB, Shaw evaluate data & trends • Inject substrate (EHC?) to reduce VOC concentrations • Groundwater sampling to evaluate effectiveness • Final report 15
  16. 16. Questions? 16
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×