Former NAS Moffett FieldHangar 1 Removal Action Update        Bryce Bartelma, PG       Navy BRAC PMO West         February...
Project Objective• Control release of PCBs from Hangar 1 in accordance  with EE/CA (July 2008) and Action Memorandum  (Dec...
Continued Monitoring and                Protection Measures• No observed biological impacts• Ramp up storm water and groun...
Hangar 1 Interactive CD• Navy provided  funding to NASA for  completion with all  interactive materials  on CD.• Planning ...
Zone 2 East Progress – September 7                5
Zone 2 East Progress – October 12               6
November…Progress?        7
Zone 3 East Progress – December 27                8
Zone 3 East Progress – January 23               9
Zone 2 West Progress – September 6                10
Zone 2 West Progress – October 12               11
November   12
Zone 3 West Progress – December 27                13
Zone 3 West Progress – January 23               14
Halfway Point     15
Exterior Coating & Touch-ups                  • Zones 2 & 3                  • Use of man lifts for                    low...
Interior View – South to Zone 1              17
Interior View – North to Zone 6              18
Zone 6 – Mansard Removal           19
Schedule• Fieldwork in zone 1  Completed• Fieldwork in zones 2 – 6  Ongoing• Complete fieldwork,  confirmation sampling  a...
Questions?             Point of Contact:               Scott Anderson            BRAC Environmental                  Coord...
Upcoming SlideShare
Loading in...5
×

Hangar One Update to Moffett RAB

642

Published on

Published in: Education, Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
642
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Transcript of "Hangar One Update to Moffett RAB"

  1. 1. Former NAS Moffett FieldHangar 1 Removal Action Update Bryce Bartelma, PG Navy BRAC PMO West February 9, 2012 RAB Meeting 1
  2. 2. Project Objective• Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)  Demolition of interior structures  Removal of contaminated siding  Application of weather-resistant coating to steel frame 2
  3. 3. Continued Monitoring and Protection Measures• No observed biological impacts• Ramp up storm water and ground surface protection during rainy season with Water Board coordination• Navy and NASA air monitoring data demonstrates control of air emissions 3
  4. 4. Hangar 1 Interactive CD• Navy provided funding to NASA for completion with all interactive materials on CD.• Planning web based version that will be hosted by NASA website! 4
  5. 5. Zone 2 East Progress – September 7 5
  6. 6. Zone 2 East Progress – October 12 6
  7. 7. November…Progress? 7
  8. 8. Zone 3 East Progress – December 27 8
  9. 9. Zone 3 East Progress – January 23 9
  10. 10. Zone 2 West Progress – September 6 10
  11. 11. Zone 2 West Progress – October 12 11
  12. 12. November 12
  13. 13. Zone 3 West Progress – December 27 13
  14. 14. Zone 3 West Progress – January 23 14
  15. 15. Halfway Point 15
  16. 16. Exterior Coating & Touch-ups • Zones 2 & 3 • Use of man lifts for lower level touch-ups 16
  17. 17. Interior View – South to Zone 1 17
  18. 18. Interior View – North to Zone 6 18
  19. 19. Zone 6 – Mansard Removal 19
  20. 20. Schedule• Fieldwork in zone 1 Completed• Fieldwork in zones 2 – 6 Ongoing• Complete fieldwork, confirmation sampling and demobilize Summer 2012• Submit After Action Completion Report Fall 2012 20
  21. 21. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 21

×