Former NAS Moffett FieldHangar 1 Removal Action Update        Bryce Bartelma, PG       Navy BRAC PMO West         August 9...
Project Objective• Control release of PCBs from Hangar 1 in accordance  with EE/CA (July 2008) and Action Memorandum  (Dec...
Continued Monitoring and                Protection Measures• Continued biological activity and  nesting deterrents• Mainta...
April 2012    4
July 2012   5
Final Material Removed – July 19, 2012                  6
Fixing the Holiday Star              • Replacement of                electrical components          7
Remaining Tasks          • Scaffolding deconstruction          • Mezzanine prep and coat          • Final touch ups, clean...
Schedule• Complete Fieldwork and  Deconstruct Scaffolding  October 2012• Final Cleaning and  Demobilize  November 2012• Su...
Hangar 1 Interactive CD                   CLICK HERE FOR DEMO          10
Questions?             Point of Contact:               Scott Anderson            BRAC Environmental                  Coord...
Upcoming SlideShare
Loading in...5
×

Moffett RAB Hangar One Update

3,107

Published on

Update on Hangar One by Bryce Bartelma at the August 9, 2012, meeting of the Moffett Restoration Advisory Board.

Published in: Education, Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
3,107
On Slideshare
0
From Embeds
0
Number of Embeds
3
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Moffett RAB Hangar One Update

  1. 1. Former NAS Moffett FieldHangar 1 Removal Action Update Bryce Bartelma, PG Navy BRAC PMO West August 9, 2012 RAB Meeting 1
  2. 2. Project Objective• Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)  Demolition of interior structures  Removal of contaminated siding  Application of weather-resistant coating to steel frame 2
  3. 3. Continued Monitoring and Protection Measures• Continued biological activity and nesting deterrents• Maintain storm water and ground surface protection• Navy and NASA air monitoring data demonstrates control of air emissions 3
  4. 4. April 2012 4
  5. 5. July 2012 5
  6. 6. Final Material Removed – July 19, 2012 6
  7. 7. Fixing the Holiday Star • Replacement of electrical components 7
  8. 8. Remaining Tasks • Scaffolding deconstruction • Mezzanine prep and coat • Final touch ups, cleaning and surface soil removal 8
  9. 9. Schedule• Complete Fieldwork and Deconstruct Scaffolding October 2012• Final Cleaning and Demobilize November 2012• Submit After Action Completion Report Winter/Spring 2013 9
  10. 10. Hangar 1 Interactive CD CLICK HERE FOR DEMO 10
  11. 11. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 11