India’s Capacity Addition Targets                                          Target (in MW)Plan         Year                ...
“Coal shall remain India’s most   important energy source till  2031-32 and possibly beyond”– Report of the Expert Committ...
• As per the Integrated Energy Policy (IEP)  Report, Indian Coal Requirement in 2031 - 32  is projected to be between 1580...
India’s Coal Demand Forecast by Forbes             in million tons
• Indigenous coal resources enable economic  development and can be transformed to guard  against import dependence and pr...
Coal Supply Demand Gap  Fin            Gap           Increase in Gap  Year      (Million Tonnes)     (wrt ’08-09)2008 – 09...
The Bottlenecks causing               Coal Supply – Demand GapStringent environmental laws causing considerable delay in o...
• Under New Coal Distribution Policy (NCDP)  framework, CIL would only commit up to 50%  of TPPs Annual Coal Quantity (ACQ...
Global Coal Trade Flows       (as on 2004)                      Source: International Energy Agency
World Main Fossil Fuel Reserves (Gigatons of oil equivalent)                                               Source: World C...
USA: World’s largest coal reserve• US leads the pack with 237.3 billion tons, i.e. 22.6% of Global  proven coal reserve.• ...
Kazakhstan: Central Asia’s largest coal reserve• Survey of Energy Resources by World Energy  Council in 2010 revealed Kaza...
Facts & Figures…1. The electricity supply-demand gap in terms of   both capacity (MW) and energy (MWh) has   been steadily...
Peak Demand Projections                       Peak Demand EstimatePlan        Year                             (in MW)12th...
With increase in demand, inthe present system thefollowing are augmented:1) Distribution Infrastructure2) Transmission   I...
Increased generation capacity implies fasterconsumption of energy resources. This shalllead to faster depletion of resourc...
CEA, in The National Electricity Plan (Vol I)published in January 2012, cites Demand SideManagement as a solution.DSM aims...
DSM framework in India• Demand Response: Create additional capacity  during peak hours by voluntary load curtailment  by c...
DSM framework as cited by  CEA calls for Smart Gridtechnology already in vogue,         globally.
Smart Grid Characteristic                     Demand Dispatch Synergy                                  Demand Dispatch wil...
Source: Smart from Start, PwC
Case Study 1: Singapore• In November 2009, the Energy Market Authority (EMA) of Singapore  launched a pilot smart grid tes...
Case Study 2: Norway• The Norwegian Water Resources and Energy Directorate  (NVE), adopted on 24 June 2011 new rules that ...
Case Study 3: Sweden• In 2003 Sweden became the first EU country to mandate smart  metering (indirectly) by legislating ne...
Source: Energy Statistics 2012, National Statistical Organisation, Govt of India
Wind Power• The Indian wind energy sector has an installed capacity of  14158.00 MW (as on March 31, 2011). In terms of wi...
Source: MNRE, Govt of India
Wind Power: Gross Potential Capacity              in MW
Ranking on Wind Index by Ernst & Young            as on May 2012
SOLAR POWER•   India has nearly 300 sunny days in most regions, and average    incident solar radiation ranges between 4 t...
• Indian industries have responded positively to the  Mission.• There were over 400 projects applications in the first  go...
National Solar Mission 2010 - 2022                                  Off-Grid      Solar Hot    Solar lantern /   Solar    ...
India’s solar sector is expected to receive a boost asinvestors and developers turn their attention away from atroubled Eu...
Ranking on Solar Index by Ernst & Young            as on May 2012
HYDRO POWER
• Only 23% of India’s hydro power potential has  been harnessed so far.• Additional hydropower capacity is desirable in  I...
Limitations of Hydro Projects• Away from load centres; evacuation of power is big problem• Environmental/ Ecological & RR ...
State wise distribution of 4711 completed & 390 under              construction dams in India                             ...
Ocean Energy• Tidal Range Energy – converting energy potential of Tidal variations  into power• Floating Offshore wind tur...
Biomass Energy• Biomass energy is the utilization of organic  matter present and can be utilized for various  applications...
Biomass Energy in India•   India produces about 450-500 million tonnes of biomass per year. Biomass provides    32% of all...
Solar Thermal EnergyVarious commercial power plant developmentprojects with unit outputs of 50 to 310 MWe andlarge solar f...
• Greece: 50 MWe solar thermal power plant THESEUS on the  Crete island; promoted by German and Greece companies; solar  f...
• India: 140 MWe naphtha-fired ISCCS plant in  Mathania/Rajasthan; 35 MWe equivalent solar capacity;  promoted by industri...
Future after Fukushima
Nuclear Energy :            Future after Fukushima• In view of the looming climate crisis and dwindling fossil fuels  rese...
Nuclear Energy :                        Safety Issues• A commercial-type power reactor simply cannot, under any circumstan...
Nuclear Energy :               Climate Change Debate• Contrary to popular belief, CO2 emissions of nuclear energy in  conn...
Country Perspective: BrazilBrazil’s power demand is mostlycatered by Hydro-electricity.Angra 1 (657 MW) & Angra 2 (1350MW)...
Country Perspective: Brazil                               continuedThe experience gathered from the design, construction, ...
Country Perspective: GermanyOn 14th March 2011, 3 days after Fukushima disaster, a three-monthmoratorium was announced as ...
Country Perspective: IndiaNuclear power was being given priority by the Indian Govt, as evidentfrom the ambitious 18 GW ta...
Future of the Indian power sector
Future of the Indian power sector
Future of the Indian power sector
Future of the Indian power sector
Future of the Indian power sector
Future of the Indian power sector
Future of the Indian power sector
Upcoming SlideShare
Loading in...5
×

Future of the Indian power sector

3,596

Published on

Published in: Business
0 Comments
5 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
3,596
On Slideshare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
336
Comments
0
Likes
5
Embeds 0
No embeds

No notes for slide

Future of the Indian power sector

  1. 1. India’s Capacity Addition Targets Target (in MW)Plan Year Thermal Hydro Nuclear Total11th 2007 - 2012 50,757 8,237 3,380 62,37412th 2012 - 2017 67,686 9,204 2,800 79,69013th 2017 - 2022 49,200 12,000 18,000 79,200* 11th Plan target revised after Mid Term Appraisal (MTA)
  2. 2. “Coal shall remain India’s most important energy source till 2031-32 and possibly beyond”– Report of the Expert Committee on Integrated Energy Policy, Aug’06, Planning Commission, Govt. of India
  3. 3. • As per the Integrated Energy Policy (IEP) Report, Indian Coal Requirement in 2031 - 32 is projected to be between 1580 – 2555 Million Tons.• But CIL has set a target of domestic coal production to 839 Million Tons (maximum) by 2025.• CIL target is therefore way below the annual coal requirement.
  4. 4. India’s Coal Demand Forecast by Forbes in million tons
  5. 5. • Indigenous coal resources enable economic development and can be transformed to guard against import dependence and price shocks.• India is the 5th largest proven coal reserve in the world and contributes to around 6% of global coal production.• But, there still exists a supply – demand gap.• Supply demand Gap has increased at a CAGR of 38.47% from 2008 – 09 to 2011 – 12.
  6. 6. Coal Supply Demand Gap Fin Gap Increase in Gap Year (Million Tonnes) (wrt ’08-09)2008 – 09 60.83 –2009 – 10 90.50 48.77 %2010 – 11 132.00 117.00 %2011 – 12 161.50 165.50 %
  7. 7. The Bottlenecks causing Coal Supply – Demand GapStringent environmental laws causing considerable delay in obtainingforestry clearances.Tenancy Land Acquisition and associated Resettlement & Rehabilitation(RR) issues.Growing Naxalism & prominence of coal mafia.Skewed concentration of Coal Deposits.Lack of proper transportation infrastructure & considerable slow progress indevelopment of the same.Monopolistic pattern of the Indian Coal Sector (CIL having 94% marketshare)Outdated mining technologies & poor maintenance of associated equipmentPoor geophysical mapping (~ 3%) & geochemical mapping (~ 4%) ofIndia’s hard rock area. Institution with a broader scope then GSI required.
  8. 8. • Under New Coal Distribution Policy (NCDP) framework, CIL would only commit up to 50% of TPPs Annual Coal Quantity (ACQ) from domestic sources only.• Therefore the TPPs are left with no other option but to realize the remaining coal requirement through imports.• Importing thermal coal seems imperative if a +8% of GDP growth is to be sustained.
  9. 9. Global Coal Trade Flows (as on 2004) Source: International Energy Agency
  10. 10. World Main Fossil Fuel Reserves (Gigatons of oil equivalent) Source: World Coal Association
  11. 11. USA: World’s largest coal reserve• US leads the pack with 237.3 billion tons, i.e. 22.6% of Global proven coal reserve.• The Powder River Basin of Montana and Wyoming is the single largest source of coal in the US.• Montana has 74.81 billion tons of estimated recoverable reserves, the most in the US, and Wyoming has 39.19 billion tons of estimated recoverable reserves, second highest reserves in the U.S• Peabody Energy & Arch Coal are eyeing the Chinese & Indian markets.• Peabody has stated that global coal shipments to the Asia-Pacific region could reach 140 million metric tons per year, by 2015• India can therefore have a sizeable chunk of its annual coal requirement from the US
  12. 12. Kazakhstan: Central Asia’s largest coal reserve• Survey of Energy Resources by World Energy Council in 2010 revealed Kazakhstan to have 33.6 billion tons of recoverable coal reserves, 3rd in Asia after China & India.• By 2014 Kazakhstan plans to boost its annual coal exports to 32 Million tons from present 20 – 22 million tons.• Evident from the geographical proximity, India can surely exercise the option of importing coal from Kazakhstan
  13. 13. Facts & Figures…1. The electricity supply-demand gap in terms of both capacity (MW) and energy (MWh) has been steadily growing in India.2. Gap as on December 2011 was 13.9%3. Transmission and distribution losses stood at 35 – 45% .
  14. 14. Peak Demand Projections Peak Demand EstimatePlan Year (in MW)12th 2012 - 2017 218,00013th 2017 - 2022 300,000 Source: Economic Times, Feb 10, 2012
  15. 15. With increase in demand, inthe present system thefollowing are augmented:1) Distribution Infrastructure2) Transmission Infrastructure3) Generation CapacityIncreased T&D Infrastructurecauses increased T&D losses.Generation capacity needs tobe increased to supply theincreased demand as well asthe increased T&D losses.
  16. 16. Increased generation capacity implies fasterconsumption of energy resources. This shalllead to faster depletion of resources, therebyposing a serious threat to the national energysecurity. To finance increase in T&D &Generation infrastructure, electricity priceswill escalate.This will definitely burn holes in the commonman’s pocket.But, electricity demand is bound to increase ina growing economy.So what is the solution?
  17. 17. CEA, in The National Electricity Plan (Vol I)published in January 2012, cites Demand SideManagement as a solution.DSM aims to induce lower consumption of electricenergy by reduction in the consumption bycustomers in response to an increase in the price ofelectric energy or to incentive payments. In otherwords, it shall create a market for Negawatts.DSM program can reduce energy costs for utilitiesand in the long term, it can limit the requirement forfurther generation capacity augmentation andstrengthening of transmission and distributionsystem
  18. 18. DSM framework in India• Demand Response: Create additional capacity during peak hours by voluntary load curtailment by consumers, load shifting or by energy efficiency measures.• Load Management Programs: real time pricing based on supply & demand, time-of-use rate structure• Smart meters: Enabling communication between customer & DISCOMs informing about rates, demand & supply; enabling accurate real time measurements; load connect-disconnect facility
  19. 19. DSM framework as cited by CEA calls for Smart Gridtechnology already in vogue, globally.
  20. 20. Smart Grid Characteristic Demand Dispatch Synergy Demand Dispatch will provide incremental motivation for Enable active participation consumer participation by creating opportunities to reduce1) by the consumers cost, generate revenues & reduce environmental impacts Accommodate all Provides a mechanism for increased penetration of distributed generation & storage2) & renewable resources on the grid options Enable new products, New Demand Dispatch markets attracts consumers &3) services & markets innovations Provide quality power for Demand Dispatch applications can include control of power4) digital economy quality and voltage regulation at the feeder level Enables complete system optimization by allowing grid Optimize asset utilization5) operators to coordinate supply & demand to meet reliability, and operate efficiently efficiency, economic & environmental goals Anticipate & respond to Demand dispatch monitoring & control of demand resources6) system disturbance (Self enhances the self healing nature of the smart grid. This will Heal) virtually eliminate chances of cascading outages Demand dispatch monitoring & control of demand resources Operate resiliently against7) allows faster restoration from outages. Increased penetration attack & natural disaster of distributed resources reduces grid vulnerability.
  21. 21. Source: Smart from Start, PwC
  22. 22. Case Study 1: Singapore• In November 2009, the Energy Market Authority (EMA) of Singapore launched a pilot smart grid test program, the Intelligent Energy System (IES), to develop and test new smart grid technologies and solutions• IES will permit both providers and consumers the opportunity to make more informed decisions about electricity use.• IES would enable outage management systems, integration of a growing number of small and variable sources of power into the grid in a ‘plug- and-play’ manner, time-of-use pricing, load shifting in line with time related tariffs.• The trial achieved an average reduction of overall electricity consumption of 2.4% and a 3.9% reduction in peak usage.• The trial revealed that not only are the customers benefitted but also peak demand was lowered easing the pressure on generation plants – making for savings in terms of energy infrastructure spend for Singapore.
  23. 23. Case Study 2: Norway• The Norwegian Water Resources and Energy Directorate (NVE), adopted on 24 June 2011 new rules that targets to equip all customers with smart meters by 1 January 2017.• Introducing smart metering will allow electricity consumers to get more precise consumption data, a more accurate billing and to better consumption management.• Electricity suppliers (or DISCOMs) will be able to reinforce their relationship with customers through more interaction and additionally provide new services• The Central Maine Power Company has already completed installation of smart meters in its area creating thousands of jobs for the Maine economy, while ensuring long-term grid reliability and efficient grid management.
  24. 24. Case Study 3: Sweden• In 2003 Sweden became the first EU country to mandate smart metering (indirectly) by legislating new national metering regulations• The smart metering scheme has enabled hourly metering• It has enabled customers to have the information about the time- of-use tariffs a day ahead via emails/ sms• The load was reduced by an average of no less than 50% at times of high electricity prices• The peak load was reduced with 2% due to the new power tariff which has a fixed part and a power part based on the average consumption for the three maximum consumption hours per month, for work days 07:00-19:00
  25. 25. Source: Energy Statistics 2012, National Statistical Organisation, Govt of India
  26. 26. Wind Power• The Indian wind energy sector has an installed capacity of 14158.00 MW (as on March 31, 2011). In terms of wind power installed capacity, India is ranked 5th in the World. Today India is a major player in the global wind energy market.• The potential is far from exhausted. Indian Wind Energy Association has estimated that with the current level of technology, the ‘on-shore’ potential for utilization of wind energy for electricity generation is of the order of 65,000 MW. The unexploited resource availability has the potential to sustain the growth of wind energy sector in India in the years to come.• The wind energy generation is expected to increase at an average growth rate of 9% per annum and is expected to reach 7 billion units during FY2011-12
  27. 27. Source: MNRE, Govt of India
  28. 28. Wind Power: Gross Potential Capacity in MW
  29. 29. Ranking on Wind Index by Ernst & Young as on May 2012
  30. 30. SOLAR POWER• India has nearly 300 sunny days in most regions, and average incident solar radiation ranges between 4 to 7 kWh/day/sq.meter — much higher than most other countries.• The largest state in India, Rajasthan, is roughly the same size as Germany, yet it receives twice the intensity of solar radiation for more than twice the number of days as Germany, which is the world’s current solar power leader.• In 2010, India’s solar power capacity was less than 20 MW and the 2020 target was larger than the 19,000 MW of existing solar power worldwide. Now global solar capacity has doubled to 40,000 MW and continues to be one of the world’s fastest growing power technologies. India could aim even higher, given the potential and growing demand for clean energy.
  31. 31. • Indian industries have responded positively to the Mission.• There were over 400 projects applications in the first government auction, though only 37 projects were selected.• India’s largest industrial conglomerates (Reliance, Tata & Birla) are increasing solar investments, new players have emerged, and government entities (ONGC, NTPC, and Bharat Heavy Electricals Limited) are implementing large-scale projects• The key to scaling up solar power lies in its ability to be cost competitive. KPMG-India predicts that with policy support and investment, solar energy could achieve grid-parity with fossil fuels by 2019-20
  32. 32. National Solar Mission 2010 - 2022 Off-Grid Solar Hot Solar lantern / Solar Grid Connected solar water lightingTechnology / rooftop applications collectors systems PHASE I 1000 – 2000 7 million(2010 - 2013) 200 MW N/A MW sq. miles PHASE II 4000 – 10,000 15 million(2013 - 2017) 1000 MW N/A MW sq. miles PHASE III 20 million 20 million(2017 - 2022) 20,000 MW 2000 MW sq. miles systems
  33. 33. India’s solar sector is expected to receive a boost asinvestors and developers turn their attention away from atroubled European market in search of high-growthdeveloping markets. India’s strong project pipeline anduntapped resource potential means it is likely to benefit fromthis shift in global solar investment.Indeed, there are already signs that this is starting tohappen. Of the US $10.3b (€7.7b) in clean energyinvestment in 2011, the largest increase came from theUS$4.2b (€3.1b) funding across the solar industry,representing a sevenfold increase on 2010.Areva, in April 2012, announced to have won ReliancePower’s 250 MW Solar CSP plant Source: Renewable energy country attractiveness indices, Ernst & Young, May 2012 Green power 2012, KPMG …………………..
  34. 34. Ranking on Solar Index by Ernst & Young as on May 2012
  35. 35. HYDRO POWER
  36. 36. • Only 23% of India’s hydro power potential has been harnessed so far.• Additional hydropower capacity is desirable in India’s generation mix, as it provides the system operator with technically vital flexibility to meet the changes in demand. The high density of household demand in India means that the system can experience a peaking load of anything between 20,000 to 30,000 MW. This sudden spurt in demand can be best met by hydropower plants which have the ability to start up and shut down quickly
  37. 37. Limitations of Hydro Projects• Away from load centres; evacuation of power is big problem• Environmental/ Ecological & RR problems due to submergence/ construction activities• Difficulty in Investigations/ Implementation due to remoteness of the area• Long Gestation periods• Lack of availability of long term finance• Geological surprises resulting in time and cost over-runs• Hydro projects suffer from production risks since the project is planned based on the historical data which may not occur in future
  38. 38. State wise distribution of 4711 completed & 390 under construction dams in India Source: International Conference on Advances in Civil Engineering, Oct 2011
  39. 39. Ocean Energy• Tidal Range Energy – converting energy potential of Tidal variations into power• Floating Offshore wind turbines – harnessing strong & steady wind power, placed mid-sea.• Tidal Energy – converting kinetic energy of ocean & tidal currents into power.• Wave Energy – capable of operating in both deep & shallow water zones, holds significant potential 29,500 TWh/yr.• Ocean Thermal Energy Conversion (OTEC) – operates on a min. 20degC temperature difference between warm surface waters & cooler deep waters. Capable of producing renewable energy on a continuous basis.• Osmotic Energy – Uses energy available in differences between salt concentrations of sea water & fresh water, installation in fjords & estuaries
  40. 40. Biomass Energy• Biomass energy is the utilization of organic matter present and can be utilized for various applications: – Biomass can be used to produce heat and electricity, or used in combined heat and power (CHP) plants. – Biomass can also be used in combination with fossil fuels (co-firing) to improve efficiency and reduce the build up of combustion residues. – Biomass can also replace petroleum as a source for transportation fuels
  41. 41. Biomass Energy in India• India produces about 450-500 million tonnes of biomass per year. Biomass provides 32% of all the primary energy use in the country at present.• The potential in the short term for power from biomass in India varies from about 18,000 MW, when the scope of biomass is as traditionally defined, to a high of about 50,000 MW if one were to expand the scope of definition of biomass.• The current share of biofuels in total fuel consumption is extremely low and is confined mainly to 5% blending of ethanol in gasoline, which the government has made mandatory in 10 states.• Currently, biodiesel is not sold on the Indian fuel market, but the government plans to meet 20% of the country’s diesel requirements by 2020 using biodiesel.• Plants like Jatropha curcas, Neem, Mahua and other wild plants are identified as the potential sources for biodiesel production in India.• There are about 63 million ha waste land in the country, out of which about 40 million ha area can be developed by undertaking plantations of Jatropha. India uses several incentive schemes to induce villagers to rehabilitate waste lands through the cultivation of Jatropha.• The Indian government is targeting a Jatropha plantation area of 11.2 million ha by 2012.
  42. 42. Solar Thermal EnergyVarious commercial power plant developmentprojects with unit outputs of 50 to 310 MWe andlarge solar fields of parabolic trough collectorsare currently promoted or are in a progressiveplanning stage by European and U.S. projectdevelopers with grants of the World Bank/GEFor other co-funds world – wide.
  43. 43. • Greece: 50 MWe solar thermal power plant THESEUS on the Crete island; promoted by German and Greece companies; solar field of approximately 300,000 m2;, 112 GWh of pure solar electricity per year• Spain: Various 50 MWe plants group in southern Spain; promoted by international industrial group; based on the new Royal Decree on the support of renewable electricity generation• Egypt: 135 MWe natural-gas-fired ISCCS plant in Kuraymat at the Nile river; 30 MWe equivalent solar capacity; promoted by industrial groups; with allocated 40 to 50 million US$ GEF grant.• Morocco: 150 MWe natural-gas-fired ISCCS plant project; 30 to 50 MWe equivalent solar capacity; promoted by industrial groups; with allocated 40 to 50 million US$ GEF grant.
  44. 44. • India: 140 MWe naphtha-fired ISCCS plant in Mathania/Rajasthan; 35 MWe equivalent solar capacity; promoted by industrial groups; with allocated 49 million USDollar GEF grant and 100 million US-Dollar loan of the German KfW-bank• Iran: Feasibility study for the implementation of a 100 MW natural gas fired combined cycle plant with a 200 000 – 400 000m² parabolic trough field in the desert of Yazd contracted with its own national funds.• Mexico: 310 MWe natural-gas-fired ISCCS plant in the Northern Mexican desert; 40 MWe equivalent solar capacity; promoted by industrial groups; with allocated 40 to 50 million US-Dollar GEF grant.
  45. 45. Future after Fukushima
  46. 46. Nuclear Energy : Future after Fukushima• In view of the looming climate crisis and dwindling fossil fuels reserves – peak oil just to mention one – nuclear energy was propagated in the past decade as a CO2-free, safe and secure, cheap solution to global energy problems.• But post-Fukushima, international energy policy is at a crossroads. There have been more or less clear signs of rethinking on the parts of governments in a number of countries, including Germany, Switzerland, China and now even Japan, indicating that they are considering picking up the pace in a fundamental change in energy policy.• Japan and Germany, the 3rd & the 4th largest economies in the world have decided to phase out nuclear energy and base future growth more on renewable energies.
  47. 47. Nuclear Energy : Safety Issues• A commercial-type power reactor simply cannot, under any circumstances, explode like a nuclear bomb - the fuel is not enriched beyond about 5%• Every country which operates nuclear power plants has a nuclear safety inspectorate and all of these work closely with the IAEA, responsible for global nuclear safety.• Apart from Chernobyl, no nuclear workers or members of the public have ever died as a result of exposure to radiation due to a commercial nuclear reactor incident. Most of the serious radiological injuries and deaths that occur each year (2-4 deaths and many more exposures above regulatory limits) are the result of large uncontrolled radiation sources, such as abandoned medical or industrial equipment• No industrial activity can be represented as entirely risk-free. Incidents and accidents may happen, and as in other industries, & will lead to progressive improvement in safety.• But there is a concern about nuclear waste disposal.
  48. 48. Nuclear Energy : Climate Change Debate• Contrary to popular belief, CO2 emissions of nuclear energy in connection with its production – depending on where the raw material uranium is mined and enriched – amounts to between 7 and 126 gCO2equ/kWh (GEMIS 4.7), one-third as much GHGs as large modern gas power plants.• So, nuclear energy is not free of CO2 emissions, as often they are touted.• Krypton 85 is produced in nuclear power plants and is released on a massive scale in reprocessing.• A product of nuclear fission, Krypton 85 ionizes the air more than any other radioactive substance• Though Krypton 85 levels in the atmosphere have reached a record high, surprisingly it has not received any attention in international climate-protection negotiations till date.
  49. 49. Country Perspective: BrazilBrazil’s power demand is mostlycatered by Hydro-electricity.Angra 1 (657 MW) & Angra 2 (1350MW) are the operating 2 Nuclear Wind Nuclearpower plants. Angra 3 is under 1.80% Power Biomass 0.70%construction is expected to begin 6.60%operating from 2015.According to the Brazilian NationalEnergy Plan, installed nuclear capacitywould be 33GW by 2030, accounting Thermal 18.60%for 4.9 % of total installed capacity. Toprevent melting of fuel rods due to Hydrofailure of reactor cooling pumps, as 72.30%was the case for Fukushima, smallhydroelectric plants & dedicated powertransmission lines are planned.
  50. 50. Country Perspective: Brazil continuedThe experience gathered from the design, construction, and operation ofAngra 1, 2, and 3, as well as having 5th largest uranium reserve in the world(309,000 tons), has made Brazil showcase Nuclear energy as a highlycompetitive energy alternative to a guaranteed energy self – sufficiency.Brazil has the potential of wind energy to the tune of 143 GW but only 794MW has been installed. The potential for co-generation using sugarcanebagasse is estimated at around 8 GW, in addition to the possibility for usingbiogas for electrical energy generation. Furthermore, the potential for usingsolar energy, both thermal and photovoltaic, is extraordinary. T&D lossesare 15% which can be reduced to 10%, adding 46,000 GWh every year tothe Brazilian Grid. Extensive R&M of hydroelectric plants that have beenoperating for more than 20 years can contribute to 8000 MW increasedgeneration.Thus, nuclear energy would become absolutely unnecessary as analternative for satisfying Brazil’s energy demands.
  51. 51. Country Perspective: GermanyOn 14th March 2011, 3 days after Fukushima disaster, a three-monthmoratorium was announced as an immediate measure, during whichthe seven oldest German nuclear power plants and the Krümmelreactor in Schleswig-Holstein, which was prone to malfunction, wereto be taken off the grid. This was exactly opposite to what was decidedby the Merkel govt. in September 2010, just 6 months prior toFukushima.Within a few days, 8,400 MW of nuclear capacity – approx. 41% ofthe total German nuclear power capacity (20,500 MW) – was nolonger available. Complete phase out of installed nuclear capacity isplanned to be within 2022.Though the decision is understood to be more political, it willinevitably entail a huge increase in the use of renewable energies andrapid improvements in energy efficiency.
  52. 52. Country Perspective: IndiaNuclear power was being given priority by the Indian Govt, as evidentfrom the ambitious 18 GW target set for 13th Plan. India has the worldshighest thorium reserves of 360,000 tons. Thorium can be used withrecycled uranium to fuel reactors. Thus, the argument for nuclear powercame from an energy security angle as well as a climate change angle.But future of the 9.9GW Jaitapur Nuclear Power Project, the US$9.3bnproject, seems bleak as the left and the right wings of civil society havejoined to create a formidable opposition, post Fukushima. NPCIL has notbeen able to provide concrete evidence to support the nuclear programenvisaged. The response of the Indian media is such that it cannot becategorized as being pro- or anti- nuclear, and therefore cannot help tobuild a concrete opinion.But again the growing economy as India is, energy security is required tofuel the economic growth. The lone option therefore remains as of now isto look for alternative energy resources, which India has plenty.