• Share
  • Email
  • Embed
  • Like
  • Save
  • Private Content
Huntingdonshire Regional college Refurbishment
 

Huntingdonshire Regional college Refurbishment

on

  • 568 views

Huntingdonshire Refurbishment project.

Huntingdonshire Refurbishment project.

Statistics

Views

Total Views
568
Views on SlideShare
568
Embed Views
0

Actions

Likes
0
Downloads
1
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Huntingdonshire Regional college Refurbishment Huntingdonshire Regional college Refurbishment Presentation Transcript

    • Front block refurbishment
      Joe Greenway
      Projects Manager
      YOUR LEARNING
      YOUR COLLEGE
    • Project Manager ?
      Lecturer in Biology - 1980 to 1992
      Section Leader – 1992 to 1995
      Head of Faculty – 1995 to 2001
      Assistant Principal – 2001 to 2003
      Vice Principal – 2003-2008
      Capital Project Manager(!) 2008 to date
    • New build?
      One of the 140 colleges in the LSC Capital programme debacle
      Plan to build two new campuses in two new locations for c.£50 M
      Involved acquisition of two new sites, sale of two existing sites as well as two new builds.
      Appointed as CPM in August 2008 with AiP submitted to LSC in September 2008
    • What now?
      Work ceased in March 2009
      Work on an alternative property strategy commenced September 2009
      CPM & Estates Manager met with all departments to ascertain alternatives and priorities (Sept to Nov 2009)
      Senior team proposals grafted to front of departmental suggestions
    • Current campus
    • Current Campus
    • Current campus
      1963
      Concrete frame with pre-cast aggregate fascia panels
      Crittal windows – single glazed
      Flat roofs
    • The Alternative Property Strategy
      12 projects identified for the period 2010 to 2013, to be delivered in 3 phases.
      Financial plan worked out for phases 1 and 2 of c. £7 M.
      (no financial plan for phase 3; too far in future)
      Approved by Governors January 2010.
    • Two strands
      Summer works 2010
      Refurbishment of the front block and external approaches with provisional programme July 2011 to December 2011.
    • Summer works 2010
      Relocation of IT Services to central part of campus & upgrade of servers
      Conversion of Library to a Learning Resource Centre
      Conversion and upgrading of rooms and two corridors to install new fire exits, cable trays, new lighting, doors etc.
      Re-roofing of two areas.
      C. £1 M
    • Refurbishment of Front block
      Brief written by CPM, Estates Manager & Principal
      QS from aborted project employed to work out a cost from the brief.
      Value Engineering to bring the cost into budget
      Governor approval to proceed to a Feasibility Study (March 2010)
      Saunders Boston Associates appointed
    • Artists ImpressionArc
      YOUR LEARNING
      YOUR COLLEGE
    • New Entrance and Reception
      New Admissions and Student Services
      Two new classrooms and 3 new seminar rooms
      Large breakout space and social area
      Refurbished Refectory
      Reorganised frontage and car parking spaces
      YOUR LEARNING
      YOUR COLLEGE
      Consists of:
    • Feasibility outcomes
      £2.66 M project
      248 m2 new build and 607m2 refurbishment
      Design development July 2010 to June 2011
      On site July 2011 to December 2011
      Financial plan in place to procure
      Governor approved June 2010
      Tender exercise to appoint Architect and QS
    • Design Team
      Saunders Boston - Architects
      Cunnington Clark - M & E
      Richard Hermann Associates – Structural
      Davis Langdon – QS, Employers Agent, CDMC
      Procurement by 2 stage Design & Build
      Tender Exercise for contractor appointment August 2010
    • THE GRANT!
      Timescale! – must be complete by by Sept 2011. Programme changed to Feb 2011 to Aug 2011 on site
      Maximise funding – up to £1 M available
      Included 2 of the summer works projects in the application
      Brought forward kitchen/refectory refurbishment from phase 2
      Application submitted on time
    • September 2010
      £1 M Grant from SFA
      Appointment of ISG Jackson and main contractor
      SFA ‘budget’ £3.041M
      Project budget £2.7 M
    • October –December 2010
      Design development
      Decanting plan
      Stage D report inc cost plan
      Stage D Project budget £2.84M
      Contract sum agreed with contractor 22 December
      Final budget £2.82M
    • What does it look like?
      College web site link:
      http://www.huntingdon.ac.uk/
    • January to February 2011
      Decanting of various college departments
      Senior Executive Team, HR, Finance, Marketing, Print Services, Student Services, Admissions, ALS, Caretakers, Reception
    • February 2011
      On site 21 February
      Due to handover 26 August
      Up to Easter on programme and on budget
      Now encountered structural issues
    • College/Contractor web-site
      http://www.isgjcommunity.com/huntingdonshire/