SlideShare a Scribd company logo
1 of 11
Assembly Line Balancing
Introduction to Industrial
Engineering
The Line Balancing Problem
 The problem is to arrange the individual
processing and assembly tasks at the
workstations so that the total time
required at each workstation is
approximately the same.
 Nearly impossible to reach perfect
balance
Things to consider
 Sequence of tasks is restricted, there is
a required order
 Called precedence constraints
 There is a production rate needed, i.e.
how many products needed per time
period
 Design the line to meet demand and
within constraints
Terminology and Definitions
 Minimum Work Element
 Total Work Content
 Workstation Process time
 Cycle Time
 Precedence Constraints
 Balance Delay
Minimum Work Element
 Dividing the job into tasks of a
rational and smallest size
 Example: Drill a hole, can’t be
divided
 Symbol – Time for element j:
 is a constant
ejT
ejT
Total Work Content
 Aggregate of work
elements
∑=
=
n
j
ejwc TT
1
Workstation Process time
 The amount of time for an individual
workstation, after individual tasks have
been combined into stations
 Sum of task times = sum of workstation
times
Cycle time
 Time between parts coming off the line
 Ideally, the production rate, but may
need to be adjusted for efficiency and
down time
 Established by the bottleneck station,
that is station with largest time
Precedence Constraints
 Generally given, determined by the
required order of operations
 Draw in a network style for
understanding
 Cannot violate these, an element must
be complete before the next one is
started
Balance Delay
 Measure of line
inefficiency due to
imbalances in
station times
c
wcc
nT
TnT
d
−
=
Method – Largest Candidate Rule
 List elements in descending order of T
 Assign elements to first station, from top
to bottom of list, minding constraints, and
not causing sum to exceed cycle time
 Continue assigning elements to stations
where each station < cycle time, largest
assigned first, until all assigned
 EXAMPLE

More Related Content

What's hot

79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancingJoseph Konnully
 
Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyMd Abu Bakar Siddique
 
Line balancing
Line balancingLine balancing
Line balancinggeetha_64
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulationavijit biswas
 
Line balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarLine balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarWakil Kumar
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line BalancingAlan Wei Teck
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation managementSaravanan Murugan
 
07 Line Balancing
07 Line Balancing07 Line Balancing
07 Line BalancingArif Rahman
 
Operations Management : Line Balancing
Operations Management : Line BalancingOperations Management : Line Balancing
Operations Management : Line BalancingRohan Bharaj
 
Ranked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementRanked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementTransweb Global Inc
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing examplePrakash Kale
 
Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)shady anwer
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurementEr. Vaibhav Agarwal
 

What's hot (20)

79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancing
 
Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case Study
 
Line balancing
Line balancingLine balancing
Line balancing
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Line balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarLine balancing ppt By Wakil Kumar
Line balancing ppt By Wakil Kumar
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
 
07 Line Balancing
07 Line Balancing07 Line Balancing
07 Line Balancing
 
Operations Management : Line Balancing
Operations Management : Line BalancingOperations Management : Line Balancing
Operations Management : Line Balancing
 
Method Study
Method Study Method Study
Method Study
 
Work study
Work studyWork study
Work study
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Ranked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementRanked Positional Weight Method | Management
Ranked Positional Weight Method | Management
 
Method study
Method studyMethod study
Method study
 
Unit 1 manufacturing system design
Unit   1 manufacturing system designUnit   1 manufacturing system design
Unit 1 manufacturing system design
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing example
 
Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)Assembly line balancing using Rank positional weight (RPW)
Assembly line balancing using Rank positional weight (RPW)
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
 
Work study method study-work measurement
Work study method study-work measurementWork study method study-work measurement
Work study method study-work measurement
 

Similar to Assembly Line Balancing Techniques for Industrial Engineering

Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pliDhyey Shukla
 
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...Saleh211376
 
Process design layout ppt bec doms
Process design layout ppt bec domsProcess design layout ppt bec doms
Process design layout ppt bec domsBabasab Patil
 
Chapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.pptChapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.pptKuvaneshWaran
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysisvideoaakash15
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraADD VALUE CONSULTING Inc
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxMukhtarMohamedAbdila
 
Operations Research -Sequencing Problems
Operations Research -Sequencing ProblemsOperations Research -Sequencing Problems
Operations Research -Sequencing ProblemsKasthuriRaja8
 
standardised-work-overview-and-documents
standardised-work-overview-and-documentsstandardised-work-overview-and-documents
standardised-work-overview-and-documentsAngelo Del Grosso
 
What is Sequencing.pptx
What is Sequencing.pptxWhat is Sequencing.pptx
What is Sequencing.pptxManish Agarwal
 
Chapter 4 product layout - 1st (3)
Chapter 4  product layout - 1st (3)Chapter 4  product layout - 1st (3)
Chapter 4 product layout - 1st (3)Shadina Shah
 

Similar to Assembly Line Balancing Techniques for Industrial Engineering (20)

Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
Line Balancing (2).pptx
Line Balancing (2).pptxLine Balancing (2).pptx
Line Balancing (2).pptx
 
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
dokumen.tips_me6703-computer-integrated-manufacturing-systems-2018-12-21-comp...
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
 
Tn6 facility layout
Tn6 facility layoutTn6 facility layout
Tn6 facility layout
 
Tn6 facility+layout
Tn6 facility+layoutTn6 facility+layout
Tn6 facility+layout
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
A line in apparel
A line in apparelA line in apparel
A line in apparel
 
Process design layout ppt bec doms
Process design layout ppt bec domsProcess design layout ppt bec doms
Process design layout ppt bec doms
 
Chapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.pptChapter5-Facility Layout_POM.ppt
Chapter5-Facility Layout_POM.ppt
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
 
vignesh conference
vignesh conferencevignesh conference
vignesh conference
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
 
Operations Research -Sequencing Problems
Operations Research -Sequencing ProblemsOperations Research -Sequencing Problems
Operations Research -Sequencing Problems
 
standardised-work-overview-and-documents
standardised-work-overview-and-documentsstandardised-work-overview-and-documents
standardised-work-overview-and-documents
 
What is Sequencing.pptx
What is Sequencing.pptxWhat is Sequencing.pptx
What is Sequencing.pptx
 
Chapter 4 product layout - 1st (3)
Chapter 4  product layout - 1st (3)Chapter 4  product layout - 1st (3)
Chapter 4 product layout - 1st (3)
 
LINE PACING ETC...ppt
LINE PACING  ETC...pptLINE PACING  ETC...ppt
LINE PACING ETC...ppt
 

Recently uploaded

TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 

Recently uploaded (20)

TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 

Assembly Line Balancing Techniques for Industrial Engineering

  • 1. Assembly Line Balancing Introduction to Industrial Engineering
  • 2. The Line Balancing Problem  The problem is to arrange the individual processing and assembly tasks at the workstations so that the total time required at each workstation is approximately the same.  Nearly impossible to reach perfect balance
  • 3. Things to consider  Sequence of tasks is restricted, there is a required order  Called precedence constraints  There is a production rate needed, i.e. how many products needed per time period  Design the line to meet demand and within constraints
  • 4. Terminology and Definitions  Minimum Work Element  Total Work Content  Workstation Process time  Cycle Time  Precedence Constraints  Balance Delay
  • 5. Minimum Work Element  Dividing the job into tasks of a rational and smallest size  Example: Drill a hole, can’t be divided  Symbol – Time for element j:  is a constant ejT ejT
  • 6. Total Work Content  Aggregate of work elements ∑= = n j ejwc TT 1
  • 7. Workstation Process time  The amount of time for an individual workstation, after individual tasks have been combined into stations  Sum of task times = sum of workstation times
  • 8. Cycle time  Time between parts coming off the line  Ideally, the production rate, but may need to be adjusted for efficiency and down time  Established by the bottleneck station, that is station with largest time
  • 9. Precedence Constraints  Generally given, determined by the required order of operations  Draw in a network style for understanding  Cannot violate these, an element must be complete before the next one is started
  • 10. Balance Delay  Measure of line inefficiency due to imbalances in station times c wcc nT TnT d − =
  • 11. Method – Largest Candidate Rule  List elements in descending order of T  Assign elements to first station, from top to bottom of list, minding constraints, and not causing sum to exceed cycle time  Continue assigning elements to stations where each station < cycle time, largest assigned first, until all assigned  EXAMPLE