SlideShare a Scribd company logo
1 of 26
NYSE MKT: URG • TSX: URE
August 2015
NYSE MKT: URG • TSX: URE
This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur in the future. Such statements include
without limitation the Company’s timeframe for the completion of ramp up of production at Lost Creek to steady-state operations and nameplate capacity; timing of making product deliveries;
the technical and economic viability of Lost Creek (including the production and cost projections contained in the preliminary economic analysis of the Lost Creek Property); whether higher-
than-expected headgrades will continue to be realized throughout Lost Creek; the ability to complete additional favorable uranium sales agreements and ability to reduce exposure to volatile
market; the potential of exploration targets throughout the Lost Creek Property (including the continuing ability to expand resources); the further exploration, development and permitting of
Company projects including at PMC Shirley Basin project); the technical and economic viability of Shirley Basin (including the production and cost projections contained in the preliminary
economic analysis of the Shirley Basin project; completion of (and timing for) regulatory approvals and other development at Shirley Basin; and the long term effects on the uranium market of
events in Japan in 2011 including supply and demand projections; and whether a re-rating of the Company will occur with establishment of production credentials. These statements are based
on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and
contingencies. Numerous factors could cause actual events to differ materially from those in the forward-looking statements. Factors that could cause such differences, without limiting the
generality of the following, include: risks inherent in exploration activities; volatility and sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact
of exploration competition; the ability to raise funds through private or public equity financings; imprecision in resource and reserve estimates; environmental and safety risks including
increased regulatory burdens; unexpected geological or hydrological conditions; a possible deterioration in political support for nuclear energy; changes in government regulations and policies,
including trade laws and policies; demand for nuclear power; weather and other natural phenomena; delays in obtaining or failures to obtain required governmental, environmental or other
project approvals; and other exploration, development, operating, financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking
statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this presentation. Ur-Energy Inc. disclaims any intention or obligation
to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise.
Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and, accordingly, the estimates and assumptions
underlying the projections are inherently highly uncertain, based on events that have not taken place, and are subject to significant economic, financial, regulatory, competitive and other
uncertainties and contingencies beyond the control of Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors,
there can be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially, from those projected.
The attention of investors is drawn to the Risk Factors set out in the Company's Annual Report on Form 10-K, filed March 2, 2015, which is filed with the U.S. Securities and Exchange
Commission on EDGAR (http://www.sec.gov/edgar.shtml) and the regulatory authorities in Canada on SEDAR (www.sedar.com).
Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the terms "measured", "indicated" and "inferred"
mineral resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission
does not recognize these terms. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral
reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally minable.
John Cooper, Ur-Energy Project Geologist, P.Geo., SME Registered Member and Qualified Person as defined by National Instrument 43-101, reviewed and approved the technical
information contained in this presentation.
2
NYSE MKT: URG • TSX: URE 3
See Disclaimer re Forward-looking Statements and Projections (slide 2)
 Lost Creek ISR – our 100% Owned Uranium
Production Facility – Initiated Production 3Q2013
• Produced 1,000,000th pound of U308 2Q2015
• State of the art flagship project
• Results demonstrate that Lost Creek is a reliable, low
cost production center
 Pathfinder - Shirley Basin, our Next Development
• PEA completed in January 2015
• Applications for permits anticipated 3Q2015
 Realizing better sales prices through long term sales agreements
 1H2015 sales revenue of US$25.6 million
2014 sales revenue of US$26.5 million
 Resource Growth – First 2015 Update
• MU1 gross increase of 2.31 million lbs measured resource
• Resources from exploration drilling: 100,000lbs Measured &Indicated; 300,000lbs Inferred
NYSE MKT: URG • TSX: URE 4
Share Capital & Cash Position
As of 6/30/15
Shares Outstanding 130.48M
Stock Options & RSUs 8.52M
Warrants 8.37M
Fully Diluted 147.37M
Market Cap (8/3/15) US$89.71M
Cash (7/30/15) US$3.6M
Share Price (8/3/15) US$0.69
52 Week Range US$.58 - $1.18
Avg. Daily Volume ~373,000
(3-mo URG & URE 8/3/15)
Member of S&P/TSX SmallCap Index
Geographical Distribution as of 6/30/15
United States ~65%
Canada ~19%
Other ~16%
NYSE MKT: URG
TSX: URE
NYSE MKT: URG • TSX: URE
Ur-Energy Inc. is followed by the analysts listed above. This list, including the firms and individual analysts at these firms, is subject to
change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or recommendations regarding Ur-Energy
Inc. performance made by these analysts are theirs alone and do not represent opinions, estimates, forecasts, conclusions,
recommendations or predictions of Ur-Energy Inc. or its management. Ur-Energy Inc. does not by its reference above or in any other manner
imply its endorsement of or concurrence with such information, conclusions or recommendations.
5
United States
H.C. Wainwright Heiko Ihle (New York, NY) 1.212.356.0510
Roth Capital Partners Joseph Reagor (Newport Beach, CA) 1.949.720.7106
Canada
Cantor Fitzgerald Rob Chang (Toronto, ON) 1.416.849.5008
Dundee Securities David Talbot (Toronto, ON) 1.416.350.3082
Haywood Securities Colin Healey (Vancouver, BC) 1.604.697.7400
L.B. Securities Chris Chang (Toronto, ON) 1.416.865.5798
Raymond James David Sadowski (Vancouver, BC) 1.604.659.8255
NYSE MKT: URG • TSX: URE
Board of Directors
Executive Director
 Jeffrey T. Klenda,* Board Chairman, Executive Director, Acting CEO (Mining Finance)
Non-Executive Directors
 W. William Boberg,* Former President & CEO (Professional Geologist)
 James M. Franklin,* Chair-Technical Committee (Professional Geologist)
 Paul Macdonell,* Chair-Compensation and Corp. Governance & Nominating Committees
(Private Mediator)
 Thomas H. Parker, Lead Director, Chair-Audit Committee (Professional Engineer)
 Gary C. Huber, Director (Professional Geologist; Mining Executive)
Officers
 Roger L. Smith, Chief Financial Officer & Chief Administrative Officer (CPA & MBA)
 Steven M. Hatten, VP Operations (Mining Engineer)
 John W. Cash, VP Regulatory Affairs (Geologist & Geophysicist)
 James A. Bonner, VP of Geology (Professional Geologist)
 Penne A. Goplerud, Corporate Secretary & General Counsel (JD)
* Founding Directors
6
NYSE MKT: URG • TSX: URE
 Highly experienced technical and management team
 ~180 years of direct uranium production experience
• ISR operations experience – Nebraska, Texas & Wyoming
7
NYSE MKT: URG • TSX: URE
 437 operable reactors world wide
with 375 GWe capacity
 66 New Nuclear Reactors under
construction in 14 countries
• 90 net new reactors by 2022
• 168 planned
• 322 proposed
8
*Source: UxC Uranium Market Outlook
 Renewed prospect of restarting Japan’s reactor fleet (timing unknown)
 In 2014, world nuclear industry consumption was ~171 million lbs and
production was only ~145 million lbs
See Disclaimer re Forward-looking Statements and Projections (slide 2)
*Sources: Nuclear Energy Institute; World Nuclear Association
NYSE MKT: URG • TSX: URE
 HEU secondary supply concluded in 2013
• Provided 24 Mlbs/yr equivalent for past 20 years
 Large scale production uneconomical at current prices
• Rossing – reduced production rates (6.0 Mlbs/yr)
• Paladin – Kayelekera production halted (3.0 Mlbs/yr)
 Key supply deferrals
• BHP Billiton – Olympic Dam expansion
• Cameco – Kintyre and Millennium
• Areva – Trekkopje and Imouraren
• Many more
 Current uranium pricing cannot sustain high cost producers
9
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NYSE MKT: URG • TSX: URE 10
NYSE MKT: URG • TSX: URE
 US demand is not met by US production
• US domestic production ~4.9M lbs of uranium/yr1
• US utilities consume ~53M lbs of uranium/yr1
 Ur-Energy is well positioned to capitalize on this opportunity
11
See Disclaimer re Forward-looking Statements and Projections (slide 2)
1U.S. Energy Information Administration 2014
Uranium originating in Kazakhstan, Russia and Uzbekistan accounted for
39% of the 53 million pounds purchased by US utilities
NYSE MKT: URG • TSX: URE
 Eleven long term contracts spanning
2013-2021 timeframe, post Fukushima
 De-risking by securing future revenue
stream in an uncertain market
• 2014: 517,760 lbs U3O8 at average
realizable sales price of $51.22/lb -
$26.5M gross revenues
• 2015: 630,000 lbs U3O8 at average
realizable sales price of $50.10/lb -
$31.5M gross revenues
12
 Exclusive representation by Jim Cornell of NuCore Energy, LLC in
negotiations of off-take purchase agreements
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NYSE MKT: URG • TSX: URE
 Environmentally sound production method
 Well understood by Wyoming state regulators
 Cost effective, low capital costs
 Governor signed bill to become an “Agreement State”
13
(Place cursor on photo and click to view video)
NYSE MKT: URG • TSX: URE 14
 Ur-Energy is a
“Pipeline Producer”
• Target larger and
scalable projects
• Not just “Pounds in
the Ground”
• Following the “Smith
Ranch” model
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Wyoming, USA
NYSE MKT: URG • TSX: URE
Resource Update NI 43-101 Technical Report*
15
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Measured: 7.18 Mlbs eU3O8 (in 7.301 Mt @ 0.049%)1
Indicated: 3.90 Mlbs eU3O8 (in 4.18 Mt @ 0.047%)
Inferred: 5.04 Mlbs eU3O8 (in 5.15 Mt @ 0.049%)
Based on grade cutoff of 0.02% eU3O8 and GT cutoffs of 0.2 and 0.3
1Measured resources not reduced by the 978,821 lbs. produced from MU1
Lost Creek Property ~42,000 acres
On-property exploration targets
provide potential for additional
resource growth
*Technical Report for the Lost Creek Property, Sweetwater County, Wyoming prepared by TREC Inc. – June 17, 2015 (posted on SEDAR).
March 2011 February
2012
April 2012 December
2013
June 2015
5,230,000
5,765,300
8,348,200 8,655,000
11,084,000
780,000
2,017,800
2,869,100
4,740,000 5,040,000
Resources
Lost Creek Resource Growth 2011-2015
Measured & Indicated Inferred
NYSE MKT: URG • TSX: URE
June 17, 2015 Technical Report* updates resources
 Estimates 9.2 million pounds recoverable over life of mine
 Project Economics (2013 PEA based on then-known resource)
• Gross revenues of US$588M LOM
• Net cash flow US$319M
• Internal rate of return (IRR) at 74.5%
 Lowest quartile Uranium Production Costs
• Estimates direct operating costs at US$11.54/lb.
• Cash operating cost including sustaining development US$21.61/lb.
• LOM project cost including initial capital and reclamation US$29.13/lb.
• Projected head grades at 42 ppm
 Capital requirement of US$49M
• US$46.5 initial capital completed prior to 2013 PEA
16
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Cautionary Statement: This Technical Report is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the economic
considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this Technical Report is based on both site-
specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery at this level will be achieved.
*Technical Report for the Lost Creek Property, Sweetwater County, Wyoming prepared by TREC Inc. – June 17, 2015 (posted on SEDAR).
Lost Creek Processing Plant
NYSE MKT: URG • TSX: URE 17
A Construction and Operational Success
 Operations commenced and all production circuits
commissioned in 2013
 Surpassing production targets
• Peak production grade 3X-4X 2013 PEA projections
See Disclaimer re Forward-looking Statements and Projections (slide 2)
Mine Unit 1
Finished Yellowcake Product
Projected Head Grades 42 ppm
2014 Head Grades 150 ppm
2015 Q1 Head Grades 110 ppm
2015 Q2 Head Grades 108 ppm Ion Exchange Vessels for
Uranium Recovery
Interior of Header House
NYSE MKT: URG • TSX: URE 18
2013 Q4 2014 2015 Q1 2015 Q2
141K lbs captured 596K lbs captured 192K lbs captured 207K lbs captured
131K lbs drummed 548K lbs drummed 177K lbs drummed 184k lbs drummed
$21.98/lb
cash cost*
$19.73/lb
cash cost*
$18.86/lb
cash cost*
$16.15/lb
cash cost*
Uranium production
December 2013 2014 2015 Q1 2015 Q2
$5.7 million $26.5 million $7.4 million $18.2 million
90K lbs at
$62.92/lb sold
518K lbs at
$51.22/lb sold
146K lbs at
$50.55/lb sold
404k lbs at
$45.08/lb sold
Revenues from operations
$19.73 – 2014 average cash cost/lb sold before severance and ad valorem taxes
*Excludes severance and ad valorem cost per pound, which for 2014 averaged $2.48 per pound
NYSE MKT: URG • TSX: URE
 Purchase closed in December 2013
 On patented mining claims – we own the ground
 8.8 million pounds, shallow, high grade roll front deposit
 ISR amenable mineralization
Baseline data gathering nearing completion. Licensing and permitting being amended for
in-situ. Expect applications for permits to be filed 3Q 2015.
19
See Disclaimer re Forward-looking Statements and Projections (slide 2)
1. Sum of Measured and Indicated tons and pounds may not add to the reported total due to rounding.
2. Based on grade cutoff of 0.02 percent eU3O8 and a grade x thickness cutoff of 0.25 GT.
3. Measured and Indicated Mineral Resources as defined in Section 1.2 of NI 43-101 (the CIM Definition Standards (CIM
Council, 2014)).
4. All reported resources occur below the historic pre-mining static water table.
RESOURCE
AREA
MEASURED INDICATED
AVG GRADE
% eU3O8
SHORT TONS
(X 1000)
POUNDS
(X 1000)
AVG GRADE
% eU3O8
SHORT
TONS
(X 1000)
POUNDS
(X 1000)
FAB
TREND
0.280 1,172 6,574 0.119 456 1,081
AREA 5 0.243 195 947 0.115 93 214
TOTAL 0.275 1,367 7,521 0.118 549 1,295
MEASURED & INDICATED 0.230 1,915 8,816
Mineral Resource Estimate Summary July 2014
*Preliminary Economic Assessment Shirley Basin Uranium Project, Carbon County, Wyoming prepared by Western Water Consultants, Inc.,
d/b/a WWC Engineering – January 27, 2015 (posted on SEDAR).
NYSE MKT: URG • TSX: URE
January 27, 2015 PEA*
 Satellite construction estimated to begin January 2017, with production
commencing October 2017
 Estimates 6.3 million pounds will be produced from the Project
 Project Economics
• Gross revenues of US$230.1M LOM
• Net cash flow US$215.9M
• Internal rate of return (IRR) at 117.0%
 Uranium Production Costs
• Estimates direct operating costs at US$14.54/lb.
• Total cost of production including severance taxes and operational and capital
spending is estimated at US$31.26/lb.
 Capital requirement of US$30.6M
20
See Disclaimer re Forward-looking Statements and Projections (slide 2)
*Preliminary Economic Assessment Shirley Basin Uranium Project, Carbon County, Wyoming prepared by Western Water Consultants, Inc., d/b/a WWC Engineering – January
27, 2015 (posted on SEDAR).
Cautionary Statement: This Preliminary Economic Assessment is preliminary in nature and includes mineral resources. Mineral resources that are not mineral reserves do not have
demonstrated economic viability. The estimated mineral recovery used in this Preliminary Economic Assessment is based on site-specific laboratory recovery data as well as URE
personnel and industry experience at similar facilities. There can be no assurance that recovery of mineral resources at this level will be achieved. There is no certainty that the
preliminary economic assessment will be realized.
NYSE MKT: URG • TSX: URE
 2015 US$1.25M Budget (Estimated)
• Complete four quarters of baseline data gathering
• Submit application converting license from conventional to ISR
• Ongoing permitting and licensing throughout 2015
 2016 US$1.5M Budget (Estimated)
• Complete all permitting and licensing activities
• Initiation of financing for capital expenditures
• Begin early stage work
21
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NYSE MKT: URG • TSX: URE
 Lucky Mc – Gas Hills
• Historic estimate of resources: 4.7 Mlbs U3O8*
• Strategic opportunities with nearby developers
 ISR by-product disposal facility
• Revenue generating asset
• Fully licensed for operation
• Multiple disposal agreements in place
• Scarce asset – 1 of 4 commercial facilities of this type in the US
 Historical US uranium exploration database
• Hundreds of project descriptions located in twenty-three states
• More than 15,000 drill logs; technical and economic evaluations
• Strong addition to Ur-Energy’s existing project database
22
See Disclaimer re Forward-looking Statements and Projections (slide 2)
*Ur-Energy is not treating the historic reports as current mineral resources or mineral reserves, because a Qualified Person has not yet conducted sufficient
work to classify the estimates as such. Lucky Mc resource estimate is based on an internal 1996 PMC polygonal method estimation.
NYSE MKT: URG • TSX: URE
 M&I resource average GT of
1.1 (17.2 ft @ 0.065% U3O8)
 Shallow: 240 feet deep
 Over 3,700 drill holes define deposit
23
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NI 43-101 Resource, July 2006
Measured & Indicated: 12.2 Mlbs eU3O8
(in 9.4 Mt @ 0.065%)
Inferred: 1.8 Mlbs eU3O8
(in1.6 Mt @ 0.055%)
 Can be licensed with NRC as amendment to Lost Creek license
(Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR)
Lost Soldier Property
NYSE MKT: URG • TSX: URE
 Growth oriented technical & management team
 Proven track record of bringing projects to production
• Low-cost uranium production center at Lost Creek
• Top producing new project in the US
 Development (not exploration) project pipeline
 Shirley Basin
 Lost Soldier
 Multiple long-term uranium sales agreements
• Reducing Company exposure to volatile marketplace
 Cash flowing project to secure financial picture
 Continued re-rating likely as Ur-Energy proves production credentials
24
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NYSE MKT: URG • TSX: URE
1. Advance Lost Creek to nameplate production
• Maintain “steady state” production
• Efficient cost management of mining operations
2. Pathfinder Mines – Shirley Basin
• Transition to operating and regulatory activities
• Resources NI 43-101 compliant
• NI 43-101 PEA completed January 2015
3. Demonstrate growth in production profile
• Expand Lost Creek Property resources – June 2015 Technical Report
• Further update to Lost Creek resources – anticipated 4Q 2015
• New Initiatives
4. Corporate finance – positive cash position
• Lost Creek production revenues
• Leader in innovative finance activities
25
See Disclaimer re Forward-looking Statements and Projections (slide 2)
NYSE MKT: URG • TSX: URE
For more information, please contact:
Jeff Klenda, Board Chairman & Executive Director, Acting CEO
Rich Boberg, Senior Director of Investor and Public Relations
By Mail:
Ur-Energy Corporate Office
10758 W. Centennial Rd., Suite 200
Littleton, CO 80127 USA
By Phone:
Office 720.981.4588
Toll-Free 866.981.4588
Fax 720.981.5643
By E-mail:
jeff.klenda@ur-energy.com
rich.boberg@ur-energy.com
26

More Related Content

What's hot

Ure corporate presentation 20150312 (final)
Ure corporate presentation 20150312 (final)Ure corporate presentation 20150312 (final)
Ure corporate presentation 20150312 (final)Urenergy
 
Ure corporate presentation 20150203 (final)
Ure corporate presentation 20150203 (final)Ure corporate presentation 20150203 (final)
Ure corporate presentation 20150203 (final)Urenergy
 
Ure corporate presentation 20150206(final)
Ure corporate presentation 20150206(final)Ure corporate presentation 20150206(final)
Ure corporate presentation 20150206(final)Urenergy
 
Ure corporate presentation 20150112(final)
Ure corporate presentation 20150112(final)Ure corporate presentation 20150112(final)
Ure corporate presentation 20150112(final)Urenergy
 
Ur-Energy June 2016 Corporate Presentation
Ur-Energy June 2016 Corporate PresentationUr-Energy June 2016 Corporate Presentation
Ur-Energy June 2016 Corporate PresentationBrooke Rock
 
Ure corporate presentation 20141203 (final)
Ure corporate presentation 20141203 (final)Ure corporate presentation 20141203 (final)
Ure corporate presentation 20141203 (final)Urenergy
 
Ur-Energy Q2 Webcast Presentation
Ur-Energy Q2 Webcast PresentationUr-Energy Q2 Webcast Presentation
Ur-Energy Q2 Webcast PresentationBrooke Rock
 
UR-Energy Q1 2016 Teleconference and Webcast
UR-Energy Q1 2016 Teleconference and WebcastUR-Energy Q1 2016 Teleconference and Webcast
UR-Energy Q1 2016 Teleconference and WebcastBrooke Rock
 
Ur-Energy's June 2017 Corporate Presentation
Ur-Energy's June 2017 Corporate PresentationUr-Energy's June 2017 Corporate Presentation
Ur-Energy's June 2017 Corporate PresentationUr-Energy
 
Ur-Energy Q3 Webcast & Teleconference Power Point
Ur-Energy Q3 Webcast & Teleconference Power PointUr-Energy Q3 Webcast & Teleconference Power Point
Ur-Energy Q3 Webcast & Teleconference Power PointBrooke Rock
 
Ure corporate presentation 20140901
Ure corporate presentation 20140901Ure corporate presentation 20140901
Ure corporate presentation 20140901Urenergy
 
Ure corporate presentation 20140903 (final)
Ure corporate presentation 20140903 (final)Ure corporate presentation 20140903 (final)
Ure corporate presentation 20140903 (final)Urenergy
 
Ure corporate presentation 20141003 (final)
Ure corporate presentation 20141003 (final)Ure corporate presentation 20141003 (final)
Ure corporate presentation 20141003 (final)Urenergy
 
Corporate presentation-jan-31-2017
Corporate presentation-jan-31-2017Corporate presentation-jan-31-2017
Corporate presentation-jan-31-2017Amber Lincoln
 
Corporate presentation jan 16, 2016
Corporate presentation   jan 16, 2016Corporate presentation   jan 16, 2016
Corporate presentation jan 16, 2016Adnet Communications
 

What's hot (20)

Ure corporate presentation 20150312 (final)
Ure corporate presentation 20150312 (final)Ure corporate presentation 20150312 (final)
Ure corporate presentation 20150312 (final)
 
Ur-Energy December 2015 Corporate Presentation
Ur-Energy December 2015 Corporate PresentationUr-Energy December 2015 Corporate Presentation
Ur-Energy December 2015 Corporate Presentation
 
Ure corporate presentation 20150203 (final)
Ure corporate presentation 20150203 (final)Ure corporate presentation 20150203 (final)
Ure corporate presentation 20150203 (final)
 
Ure corporate presentation 20150206(final)
Ure corporate presentation 20150206(final)Ure corporate presentation 20150206(final)
Ure corporate presentation 20150206(final)
 
Ure corporate presentation 20150112(final)
Ure corporate presentation 20150112(final)Ure corporate presentation 20150112(final)
Ure corporate presentation 20150112(final)
 
Ur-Energy June 2016 Corporate Presentation
Ur-Energy June 2016 Corporate PresentationUr-Energy June 2016 Corporate Presentation
Ur-Energy June 2016 Corporate Presentation
 
Ure corporate presentation 20141203 (final)
Ure corporate presentation 20141203 (final)Ure corporate presentation 20141203 (final)
Ure corporate presentation 20141203 (final)
 
Ur-Energy January 2016 Corporate Presentation
Ur-Energy January 2016 Corporate PresentationUr-Energy January 2016 Corporate Presentation
Ur-Energy January 2016 Corporate Presentation
 
Ur-Energy 2015 Third Quarter Webcast and Teleconference
Ur-Energy 2015 Third Quarter Webcast and TeleconferenceUr-Energy 2015 Third Quarter Webcast and Teleconference
Ur-Energy 2015 Third Quarter Webcast and Teleconference
 
Ur-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and TeleconferenceUr-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and Teleconference
 
Ur-Energy Q2 Webcast Presentation
Ur-Energy Q2 Webcast PresentationUr-Energy Q2 Webcast Presentation
Ur-Energy Q2 Webcast Presentation
 
UR-Energy Q1 2016 Teleconference and Webcast
UR-Energy Q1 2016 Teleconference and WebcastUR-Energy Q1 2016 Teleconference and Webcast
UR-Energy Q1 2016 Teleconference and Webcast
 
Ur-Energy March 2016 Corporate Presentation
Ur-Energy March 2016 Corporate PresentationUr-Energy March 2016 Corporate Presentation
Ur-Energy March 2016 Corporate Presentation
 
Ur-Energy's June 2017 Corporate Presentation
Ur-Energy's June 2017 Corporate PresentationUr-Energy's June 2017 Corporate Presentation
Ur-Energy's June 2017 Corporate Presentation
 
Ur-Energy Q3 Webcast & Teleconference Power Point
Ur-Energy Q3 Webcast & Teleconference Power PointUr-Energy Q3 Webcast & Teleconference Power Point
Ur-Energy Q3 Webcast & Teleconference Power Point
 
Ure corporate presentation 20140901
Ure corporate presentation 20140901Ure corporate presentation 20140901
Ure corporate presentation 20140901
 
Ure corporate presentation 20140903 (final)
Ure corporate presentation 20140903 (final)Ure corporate presentation 20140903 (final)
Ure corporate presentation 20140903 (final)
 
Ure corporate presentation 20141003 (final)
Ure corporate presentation 20141003 (final)Ure corporate presentation 20141003 (final)
Ure corporate presentation 20141003 (final)
 
Corporate presentation-jan-31-2017
Corporate presentation-jan-31-2017Corporate presentation-jan-31-2017
Corporate presentation-jan-31-2017
 
Corporate presentation jan 16, 2016
Corporate presentation   jan 16, 2016Corporate presentation   jan 16, 2016
Corporate presentation jan 16, 2016
 

Viewers also liked

פורום סמנכלי משא מצגת נילי כאוס
פורום סמנכלי משא  מצגת נילי כאוספורום סמנכלי משא  מצגת נילי כאוס
פורום סמנכלי משא מצגת נילי כאוסVPHR
 
Linkedin for Business & Personal Branding
Linkedin for Business & Personal BrandingLinkedin for Business & Personal Branding
Linkedin for Business & Personal BrandingBWEST Interactive
 
WordCampEDU Scriblio 2009-02-02
WordCampEDU Scriblio 2009-02-02WordCampEDU Scriblio 2009-02-02
WordCampEDU Scriblio 2009-02-02Casey Bisson
 
Abbay\'s Enviro Graphics and Design
Abbay\'s Enviro Graphics and DesignAbbay\'s Enviro Graphics and Design
Abbay\'s Enviro Graphics and Designcnorth
 
Tofino - Social Media Workshop - August 12
Tofino - Social Media Workshop - August 12Tofino - Social Media Workshop - August 12
Tofino - Social Media Workshop - August 12BWEST Interactive
 
2012-02 iStrategy Sydney, AU Community Development and Management
2012-02 iStrategy Sydney, AU Community Development and Management2012-02 iStrategy Sydney, AU Community Development and Management
2012-02 iStrategy Sydney, AU Community Development and ManagementGillian Muessig
 
Interconcept Solutions Business Presentation
Interconcept Solutions Business PresentationInterconcept Solutions Business Presentation
Interconcept Solutions Business PresentationEddie OOI
 
Folleto Moratto Mar 2010
Folleto Moratto Mar 2010Folleto Moratto Mar 2010
Folleto Moratto Mar 2010marianotortora
 
Open Source@etailing v1.2 (video)
Open Source@etailing v1.2 (video)Open Source@etailing v1.2 (video)
Open Source@etailing v1.2 (video)Iksula
 
Kinect框架2.0
Kinect框架2.0Kinect框架2.0
Kinect框架2.0dasiyjun
 
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)Rich Boberg, SHRM-SCP, SPHR, PHRca
 
Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012Edo van Dijk
 
פורום סמנכלי משא מצגת פתיחה
פורום סמנכלי משא מצגת פתיחהפורום סמנכלי משא מצגת פתיחה
פורום סמנכלי משא מצגת פתיחהVPHR
 
Where do we go from here? Linking community organizing, people living with HI...
Where do we go from here? Linking community organizing, people living with HI...Where do we go from here? Linking community organizing, people living with HI...
Where do we go from here? Linking community organizing, people living with HI...Alex McClelland
 
The Amsterdam Style: the next step
The Amsterdam Style: the next stepThe Amsterdam Style: the next step
The Amsterdam Style: the next stepEdo van Dijk
 

Viewers also liked (20)

פורום סמנכלי משא מצגת נילי כאוס
פורום סמנכלי משא  מצגת נילי כאוספורום סמנכלי משא  מצגת נילי כאוס
פורום סמנכלי משא מצגת נילי כאוס
 
Linkedin for Business & Personal Branding
Linkedin for Business & Personal BrandingLinkedin for Business & Personal Branding
Linkedin for Business & Personal Branding
 
Ur-Energy April 2012 Corporate Presentation
Ur-Energy April 2012 Corporate PresentationUr-Energy April 2012 Corporate Presentation
Ur-Energy April 2012 Corporate Presentation
 
September 2011 Ur-Energy Corporate Presentation
September 2011 Ur-Energy Corporate PresentationSeptember 2011 Ur-Energy Corporate Presentation
September 2011 Ur-Energy Corporate Presentation
 
E mail-tiu-ru
E mail-tiu-ruE mail-tiu-ru
E mail-tiu-ru
 
WordCampEDU Scriblio 2009-02-02
WordCampEDU Scriblio 2009-02-02WordCampEDU Scriblio 2009-02-02
WordCampEDU Scriblio 2009-02-02
 
Abbay\'s Enviro Graphics and Design
Abbay\'s Enviro Graphics and DesignAbbay\'s Enviro Graphics and Design
Abbay\'s Enviro Graphics and Design
 
Tofino - Social Media Workshop - August 12
Tofino - Social Media Workshop - August 12Tofino - Social Media Workshop - August 12
Tofino - Social Media Workshop - August 12
 
2012-02 iStrategy Sydney, AU Community Development and Management
2012-02 iStrategy Sydney, AU Community Development and Management2012-02 iStrategy Sydney, AU Community Development and Management
2012-02 iStrategy Sydney, AU Community Development and Management
 
Interconcept Solutions Business Presentation
Interconcept Solutions Business PresentationInterconcept Solutions Business Presentation
Interconcept Solutions Business Presentation
 
Folleto Moratto Mar 2010
Folleto Moratto Mar 2010Folleto Moratto Mar 2010
Folleto Moratto Mar 2010
 
Open Source@etailing v1.2 (video)
Open Source@etailing v1.2 (video)Open Source@etailing v1.2 (video)
Open Source@etailing v1.2 (video)
 
20120808 ure corporate presentation (august 2012 final)
20120808 ure corporate presentation  (august 2012 final)20120808 ure corporate presentation  (august 2012 final)
20120808 ure corporate presentation (august 2012 final)
 
Kinect框架2.0
Kinect框架2.0Kinect框架2.0
Kinect框架2.0
 
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
 
Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012Edenspiekermann agency presentation 2012
Edenspiekermann agency presentation 2012
 
פורום סמנכלי משא מצגת פתיחה
פורום סמנכלי משא מצגת פתיחהפורום סמנכלי משא מצגת פתיחה
פורום סמנכלי משא מצגת פתיחה
 
Where do we go from here? Linking community organizing, people living with HI...
Where do we go from here? Linking community organizing, people living with HI...Where do we go from here? Linking community organizing, people living with HI...
Where do we go from here? Linking community organizing, people living with HI...
 
The Amsterdam Style: the next step
The Amsterdam Style: the next stepThe Amsterdam Style: the next step
The Amsterdam Style: the next step
 
ACH 216 Lecture 03 (Whos Who)
ACH 216 Lecture 03 (Whos Who)ACH 216 Lecture 03 (Whos Who)
ACH 216 Lecture 03 (Whos Who)
 

Similar to Ur-Energy August 2015 Corporate Presentation

Ur-Energy May 2016 Corporate Presentation
Ur-Energy May 2016 Corporate PresentationUr-Energy May 2016 Corporate Presentation
Ur-Energy May 2016 Corporate PresentationBrooke Rock
 
Ur-Energy July 2016 Corporate Presentation
Ur-Energy July 2016 Corporate PresentationUr-Energy July 2016 Corporate Presentation
Ur-Energy July 2016 Corporate PresentationBrooke Rock
 
Ur-Energy April 2016 Corporate Presentation
Ur-Energy April 2016 Corporate PresentationUr-Energy April 2016 Corporate Presentation
Ur-Energy April 2016 Corporate PresentationUr-Energy
 
Ur-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate PresentationUr-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate PresentationBrooke Rock
 
Ur-Energy November 2016 Corporate Presentation
Ur-Energy November 2016 Corporate PresentationUr-Energy November 2016 Corporate Presentation
Ur-Energy November 2016 Corporate PresentationBrooke Rock
 
Ur energy's january 2017 corporate presentation
Ur energy's january 2017 corporate presentationUr energy's january 2017 corporate presentation
Ur energy's january 2017 corporate presentationUr-Energy
 
Ur-Energy September 2016 Corporate Presentation
Ur-Energy September 2016 Corporate PresentationUr-Energy September 2016 Corporate Presentation
Ur-Energy September 2016 Corporate PresentationBrooke Rock
 
Ur-Energy August 2016 Corporate Presentation
Ur-Energy August 2016 Corporate Presentation Ur-Energy August 2016 Corporate Presentation
Ur-Energy August 2016 Corporate Presentation Brooke Rock
 
Ur Energy's February 2017 Corporate Presentation
Ur Energy's February 2017 Corporate PresentationUr Energy's February 2017 Corporate Presentation
Ur Energy's February 2017 Corporate PresentationUr-Energy
 
Ur-Energy October 2016 Corporate Presentation
Ur-Energy October 2016 Corporate Presentation Ur-Energy October 2016 Corporate Presentation
Ur-Energy October 2016 Corporate Presentation Brooke Rock
 
Ur-Energy's March 2017 Corporate Presentation
Ur-Energy's March 2017 Corporate PresentationUr-Energy's March 2017 Corporate Presentation
Ur-Energy's March 2017 Corporate PresentationUr-Energy
 
Ure corporate presentation 20140709 (final)
Ure corporate presentation 20140709 (final)Ure corporate presentation 20140709 (final)
Ure corporate presentation 20140709 (final)Urenergy
 
Ure corporate presentation 20141106
Ure corporate presentation 20141106Ure corporate presentation 20141106
Ure corporate presentation 20141106Urenergy
 
Ure corporate presentation 20141015 (final)
Ure corporate presentation 20141015 (final)Ure corporate presentation 20141015 (final)
Ure corporate presentation 20141015 (final)Urenergy
 
Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)Urenergy
 
Ure corporate presentation 20141103 (final)
Ure corporate presentation 20141103 (final)Ure corporate presentation 20141103 (final)
Ure corporate presentation 20141103 (final)Urenergy
 

Similar to Ur-Energy August 2015 Corporate Presentation (17)

Ur-Energy May 2016 Corporate Presentation
Ur-Energy May 2016 Corporate PresentationUr-Energy May 2016 Corporate Presentation
Ur-Energy May 2016 Corporate Presentation
 
Ur-Energy February 2016 Corporate Presentation
Ur-Energy February 2016 Corporate PresentationUr-Energy February 2016 Corporate Presentation
Ur-Energy February 2016 Corporate Presentation
 
Ur-Energy July 2016 Corporate Presentation
Ur-Energy July 2016 Corporate PresentationUr-Energy July 2016 Corporate Presentation
Ur-Energy July 2016 Corporate Presentation
 
Ur-Energy April 2016 Corporate Presentation
Ur-Energy April 2016 Corporate PresentationUr-Energy April 2016 Corporate Presentation
Ur-Energy April 2016 Corporate Presentation
 
Ur-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate PresentationUr-Energy December 2016 Corporate Presentation
Ur-Energy December 2016 Corporate Presentation
 
Ur-Energy November 2016 Corporate Presentation
Ur-Energy November 2016 Corporate PresentationUr-Energy November 2016 Corporate Presentation
Ur-Energy November 2016 Corporate Presentation
 
Ur energy's january 2017 corporate presentation
Ur energy's january 2017 corporate presentationUr energy's january 2017 corporate presentation
Ur energy's january 2017 corporate presentation
 
Ur-Energy September 2016 Corporate Presentation
Ur-Energy September 2016 Corporate PresentationUr-Energy September 2016 Corporate Presentation
Ur-Energy September 2016 Corporate Presentation
 
Ur-Energy August 2016 Corporate Presentation
Ur-Energy August 2016 Corporate Presentation Ur-Energy August 2016 Corporate Presentation
Ur-Energy August 2016 Corporate Presentation
 
Ur Energy's February 2017 Corporate Presentation
Ur Energy's February 2017 Corporate PresentationUr Energy's February 2017 Corporate Presentation
Ur Energy's February 2017 Corporate Presentation
 
Ur-Energy October 2016 Corporate Presentation
Ur-Energy October 2016 Corporate Presentation Ur-Energy October 2016 Corporate Presentation
Ur-Energy October 2016 Corporate Presentation
 
Ur-Energy's March 2017 Corporate Presentation
Ur-Energy's March 2017 Corporate PresentationUr-Energy's March 2017 Corporate Presentation
Ur-Energy's March 2017 Corporate Presentation
 
Ure corporate presentation 20140709 (final)
Ure corporate presentation 20140709 (final)Ure corporate presentation 20140709 (final)
Ure corporate presentation 20140709 (final)
 
Ure corporate presentation 20141106
Ure corporate presentation 20141106Ure corporate presentation 20141106
Ure corporate presentation 20141106
 
Ure corporate presentation 20141015 (final)
Ure corporate presentation 20141015 (final)Ure corporate presentation 20141015 (final)
Ure corporate presentation 20141015 (final)
 
Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)Ure corporate presentation 20140815 (final)
Ure corporate presentation 20140815 (final)
 
Ure corporate presentation 20141103 (final)
Ure corporate presentation 20141103 (final)Ure corporate presentation 20141103 (final)
Ure corporate presentation 20141103 (final)
 

More from Rich Boberg, SHRM-SCP, SPHR, PHRca

More from Rich Boberg, SHRM-SCP, SPHR, PHRca (20)

Ur-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and TeleconferenceUr-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and Teleconference
 
Ur-Energy 2015 2Q Webcast and Teleconference Presentation
Ur-Energy 2015 2Q Webcast and Teleconference PresentationUr-Energy 2015 2Q Webcast and Teleconference Presentation
Ur-Energy 2015 2Q Webcast and Teleconference Presentation
 
Ur-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate PresentationUr-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate Presentation
 
Ur-Energy Second Quarter 2015 Teleconference and Webcast
Ur-Energy Second Quarter 2015 Teleconference and WebcastUr-Energy Second Quarter 2015 Teleconference and Webcast
Ur-Energy Second Quarter 2015 Teleconference and Webcast
 
Ur-Energy October 2013 Corporate Presentation
Ur-Energy October 2013 Corporate PresentationUr-Energy October 2013 Corporate Presentation
Ur-Energy October 2013 Corporate Presentation
 
Ur-Energy September 2013 Corporate Presentation
Ur-Energy September 2013 Corporate PresentationUr-Energy September 2013 Corporate Presentation
Ur-Energy September 2013 Corporate Presentation
 
Ur-Energy July 2013 Corporate Presentation
Ur-Energy July 2013 Corporate PresentationUr-Energy July 2013 Corporate Presentation
Ur-Energy July 2013 Corporate Presentation
 
Ur-Energy June 2013 Corporate Presentation
Ur-Energy June 2013 Corporate PresentationUr-Energy June 2013 Corporate Presentation
Ur-Energy June 2013 Corporate Presentation
 
Ur-Energy May 2013 Corporate Presentation
Ur-Energy May 2013 Corporate PresentationUr-Energy May 2013 Corporate Presentation
Ur-Energy May 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate PresentationUr-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate Presentation
 
Ur-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate PresentationUr-Energy March 2013 Corporate Presentation
Ur-Energy March 2013 Corporate Presentation
 
Ur-Energy February 2013 Corporate Presentation
Ur-Energy February 2013 Corporate PresentationUr-Energy February 2013 Corporate Presentation
Ur-Energy February 2013 Corporate Presentation
 
Ur-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate PresentationUr-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate Presentation
 
Ur-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate PresentationUr-Energy January 2013 Corporate Presentation
Ur-Energy January 2013 Corporate Presentation
 
Ur-Energy December 2012 Presentation
Ur-Energy December 2012 PresentationUr-Energy December 2012 Presentation
Ur-Energy December 2012 Presentation
 
November 2012 Ur-Energy Corporate Presentation
November 2012 Ur-Energy Corporate PresentationNovember 2012 Ur-Energy Corporate Presentation
November 2012 Ur-Energy Corporate Presentation
 

Recently uploaded

Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 

Recently uploaded (20)

Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 

Ur-Energy August 2015 Corporate Presentation

  • 1. NYSE MKT: URG • TSX: URE August 2015
  • 2. NYSE MKT: URG • TSX: URE This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur in the future. Such statements include without limitation the Company’s timeframe for the completion of ramp up of production at Lost Creek to steady-state operations and nameplate capacity; timing of making product deliveries; the technical and economic viability of Lost Creek (including the production and cost projections contained in the preliminary economic analysis of the Lost Creek Property); whether higher- than-expected headgrades will continue to be realized throughout Lost Creek; the ability to complete additional favorable uranium sales agreements and ability to reduce exposure to volatile market; the potential of exploration targets throughout the Lost Creek Property (including the continuing ability to expand resources); the further exploration, development and permitting of Company projects including at PMC Shirley Basin project); the technical and economic viability of Shirley Basin (including the production and cost projections contained in the preliminary economic analysis of the Shirley Basin project; completion of (and timing for) regulatory approvals and other development at Shirley Basin; and the long term effects on the uranium market of events in Japan in 2011 including supply and demand projections; and whether a re-rating of the Company will occur with establishment of production credentials. These statements are based on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Numerous factors could cause actual events to differ materially from those in the forward-looking statements. Factors that could cause such differences, without limiting the generality of the following, include: risks inherent in exploration activities; volatility and sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of exploration competition; the ability to raise funds through private or public equity financings; imprecision in resource and reserve estimates; environmental and safety risks including increased regulatory burdens; unexpected geological or hydrological conditions; a possible deterioration in political support for nuclear energy; changes in government regulations and policies, including trade laws and policies; demand for nuclear power; weather and other natural phenomena; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; and other exploration, development, operating, financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this presentation. Ur-Energy Inc. disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise. Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and, accordingly, the estimates and assumptions underlying the projections are inherently highly uncertain, based on events that have not taken place, and are subject to significant economic, financial, regulatory, competitive and other uncertainties and contingencies beyond the control of Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors, there can be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially, from those projected. The attention of investors is drawn to the Risk Factors set out in the Company's Annual Report on Form 10-K, filed March 2, 2015, which is filed with the U.S. Securities and Exchange Commission on EDGAR (http://www.sec.gov/edgar.shtml) and the regulatory authorities in Canada on SEDAR (www.sedar.com). Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the terms "measured", "indicated" and "inferred" mineral resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize these terms. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally minable. John Cooper, Ur-Energy Project Geologist, P.Geo., SME Registered Member and Qualified Person as defined by National Instrument 43-101, reviewed and approved the technical information contained in this presentation. 2
  • 3. NYSE MKT: URG • TSX: URE 3 See Disclaimer re Forward-looking Statements and Projections (slide 2)  Lost Creek ISR – our 100% Owned Uranium Production Facility – Initiated Production 3Q2013 • Produced 1,000,000th pound of U308 2Q2015 • State of the art flagship project • Results demonstrate that Lost Creek is a reliable, low cost production center  Pathfinder - Shirley Basin, our Next Development • PEA completed in January 2015 • Applications for permits anticipated 3Q2015  Realizing better sales prices through long term sales agreements  1H2015 sales revenue of US$25.6 million 2014 sales revenue of US$26.5 million  Resource Growth – First 2015 Update • MU1 gross increase of 2.31 million lbs measured resource • Resources from exploration drilling: 100,000lbs Measured &Indicated; 300,000lbs Inferred
  • 4. NYSE MKT: URG • TSX: URE 4 Share Capital & Cash Position As of 6/30/15 Shares Outstanding 130.48M Stock Options & RSUs 8.52M Warrants 8.37M Fully Diluted 147.37M Market Cap (8/3/15) US$89.71M Cash (7/30/15) US$3.6M Share Price (8/3/15) US$0.69 52 Week Range US$.58 - $1.18 Avg. Daily Volume ~373,000 (3-mo URG & URE 8/3/15) Member of S&P/TSX SmallCap Index Geographical Distribution as of 6/30/15 United States ~65% Canada ~19% Other ~16% NYSE MKT: URG TSX: URE
  • 5. NYSE MKT: URG • TSX: URE Ur-Energy Inc. is followed by the analysts listed above. This list, including the firms and individual analysts at these firms, is subject to change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or recommendations regarding Ur-Energy Inc. performance made by these analysts are theirs alone and do not represent opinions, estimates, forecasts, conclusions, recommendations or predictions of Ur-Energy Inc. or its management. Ur-Energy Inc. does not by its reference above or in any other manner imply its endorsement of or concurrence with such information, conclusions or recommendations. 5 United States H.C. Wainwright Heiko Ihle (New York, NY) 1.212.356.0510 Roth Capital Partners Joseph Reagor (Newport Beach, CA) 1.949.720.7106 Canada Cantor Fitzgerald Rob Chang (Toronto, ON) 1.416.849.5008 Dundee Securities David Talbot (Toronto, ON) 1.416.350.3082 Haywood Securities Colin Healey (Vancouver, BC) 1.604.697.7400 L.B. Securities Chris Chang (Toronto, ON) 1.416.865.5798 Raymond James David Sadowski (Vancouver, BC) 1.604.659.8255
  • 6. NYSE MKT: URG • TSX: URE Board of Directors Executive Director  Jeffrey T. Klenda,* Board Chairman, Executive Director, Acting CEO (Mining Finance) Non-Executive Directors  W. William Boberg,* Former President & CEO (Professional Geologist)  James M. Franklin,* Chair-Technical Committee (Professional Geologist)  Paul Macdonell,* Chair-Compensation and Corp. Governance & Nominating Committees (Private Mediator)  Thomas H. Parker, Lead Director, Chair-Audit Committee (Professional Engineer)  Gary C. Huber, Director (Professional Geologist; Mining Executive) Officers  Roger L. Smith, Chief Financial Officer & Chief Administrative Officer (CPA & MBA)  Steven M. Hatten, VP Operations (Mining Engineer)  John W. Cash, VP Regulatory Affairs (Geologist & Geophysicist)  James A. Bonner, VP of Geology (Professional Geologist)  Penne A. Goplerud, Corporate Secretary & General Counsel (JD) * Founding Directors 6
  • 7. NYSE MKT: URG • TSX: URE  Highly experienced technical and management team  ~180 years of direct uranium production experience • ISR operations experience – Nebraska, Texas & Wyoming 7
  • 8. NYSE MKT: URG • TSX: URE  437 operable reactors world wide with 375 GWe capacity  66 New Nuclear Reactors under construction in 14 countries • 90 net new reactors by 2022 • 168 planned • 322 proposed 8 *Source: UxC Uranium Market Outlook  Renewed prospect of restarting Japan’s reactor fleet (timing unknown)  In 2014, world nuclear industry consumption was ~171 million lbs and production was only ~145 million lbs See Disclaimer re Forward-looking Statements and Projections (slide 2) *Sources: Nuclear Energy Institute; World Nuclear Association
  • 9. NYSE MKT: URG • TSX: URE  HEU secondary supply concluded in 2013 • Provided 24 Mlbs/yr equivalent for past 20 years  Large scale production uneconomical at current prices • Rossing – reduced production rates (6.0 Mlbs/yr) • Paladin – Kayelekera production halted (3.0 Mlbs/yr)  Key supply deferrals • BHP Billiton – Olympic Dam expansion • Cameco – Kintyre and Millennium • Areva – Trekkopje and Imouraren • Many more  Current uranium pricing cannot sustain high cost producers 9 See Disclaimer re Forward-looking Statements and Projections (slide 2)
  • 10. NYSE MKT: URG • TSX: URE 10
  • 11. NYSE MKT: URG • TSX: URE  US demand is not met by US production • US domestic production ~4.9M lbs of uranium/yr1 • US utilities consume ~53M lbs of uranium/yr1  Ur-Energy is well positioned to capitalize on this opportunity 11 See Disclaimer re Forward-looking Statements and Projections (slide 2) 1U.S. Energy Information Administration 2014 Uranium originating in Kazakhstan, Russia and Uzbekistan accounted for 39% of the 53 million pounds purchased by US utilities
  • 12. NYSE MKT: URG • TSX: URE  Eleven long term contracts spanning 2013-2021 timeframe, post Fukushima  De-risking by securing future revenue stream in an uncertain market • 2014: 517,760 lbs U3O8 at average realizable sales price of $51.22/lb - $26.5M gross revenues • 2015: 630,000 lbs U3O8 at average realizable sales price of $50.10/lb - $31.5M gross revenues 12  Exclusive representation by Jim Cornell of NuCore Energy, LLC in negotiations of off-take purchase agreements See Disclaimer re Forward-looking Statements and Projections (slide 2)
  • 13. NYSE MKT: URG • TSX: URE  Environmentally sound production method  Well understood by Wyoming state regulators  Cost effective, low capital costs  Governor signed bill to become an “Agreement State” 13 (Place cursor on photo and click to view video)
  • 14. NYSE MKT: URG • TSX: URE 14  Ur-Energy is a “Pipeline Producer” • Target larger and scalable projects • Not just “Pounds in the Ground” • Following the “Smith Ranch” model See Disclaimer re Forward-looking Statements and Projections (slide 2) Wyoming, USA
  • 15. NYSE MKT: URG • TSX: URE Resource Update NI 43-101 Technical Report* 15 See Disclaimer re Forward-looking Statements and Projections (slide 2) Measured: 7.18 Mlbs eU3O8 (in 7.301 Mt @ 0.049%)1 Indicated: 3.90 Mlbs eU3O8 (in 4.18 Mt @ 0.047%) Inferred: 5.04 Mlbs eU3O8 (in 5.15 Mt @ 0.049%) Based on grade cutoff of 0.02% eU3O8 and GT cutoffs of 0.2 and 0.3 1Measured resources not reduced by the 978,821 lbs. produced from MU1 Lost Creek Property ~42,000 acres On-property exploration targets provide potential for additional resource growth *Technical Report for the Lost Creek Property, Sweetwater County, Wyoming prepared by TREC Inc. – June 17, 2015 (posted on SEDAR). March 2011 February 2012 April 2012 December 2013 June 2015 5,230,000 5,765,300 8,348,200 8,655,000 11,084,000 780,000 2,017,800 2,869,100 4,740,000 5,040,000 Resources Lost Creek Resource Growth 2011-2015 Measured & Indicated Inferred
  • 16. NYSE MKT: URG • TSX: URE June 17, 2015 Technical Report* updates resources  Estimates 9.2 million pounds recoverable over life of mine  Project Economics (2013 PEA based on then-known resource) • Gross revenues of US$588M LOM • Net cash flow US$319M • Internal rate of return (IRR) at 74.5%  Lowest quartile Uranium Production Costs • Estimates direct operating costs at US$11.54/lb. • Cash operating cost including sustaining development US$21.61/lb. • LOM project cost including initial capital and reclamation US$29.13/lb. • Projected head grades at 42 ppm  Capital requirement of US$49M • US$46.5 initial capital completed prior to 2013 PEA 16 See Disclaimer re Forward-looking Statements and Projections (slide 2) Cautionary Statement: This Technical Report is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this Technical Report is based on both site- specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery at this level will be achieved. *Technical Report for the Lost Creek Property, Sweetwater County, Wyoming prepared by TREC Inc. – June 17, 2015 (posted on SEDAR). Lost Creek Processing Plant
  • 17. NYSE MKT: URG • TSX: URE 17 A Construction and Operational Success  Operations commenced and all production circuits commissioned in 2013  Surpassing production targets • Peak production grade 3X-4X 2013 PEA projections See Disclaimer re Forward-looking Statements and Projections (slide 2) Mine Unit 1 Finished Yellowcake Product Projected Head Grades 42 ppm 2014 Head Grades 150 ppm 2015 Q1 Head Grades 110 ppm 2015 Q2 Head Grades 108 ppm Ion Exchange Vessels for Uranium Recovery Interior of Header House
  • 18. NYSE MKT: URG • TSX: URE 18 2013 Q4 2014 2015 Q1 2015 Q2 141K lbs captured 596K lbs captured 192K lbs captured 207K lbs captured 131K lbs drummed 548K lbs drummed 177K lbs drummed 184k lbs drummed $21.98/lb cash cost* $19.73/lb cash cost* $18.86/lb cash cost* $16.15/lb cash cost* Uranium production December 2013 2014 2015 Q1 2015 Q2 $5.7 million $26.5 million $7.4 million $18.2 million 90K lbs at $62.92/lb sold 518K lbs at $51.22/lb sold 146K lbs at $50.55/lb sold 404k lbs at $45.08/lb sold Revenues from operations $19.73 – 2014 average cash cost/lb sold before severance and ad valorem taxes *Excludes severance and ad valorem cost per pound, which for 2014 averaged $2.48 per pound
  • 19. NYSE MKT: URG • TSX: URE  Purchase closed in December 2013  On patented mining claims – we own the ground  8.8 million pounds, shallow, high grade roll front deposit  ISR amenable mineralization Baseline data gathering nearing completion. Licensing and permitting being amended for in-situ. Expect applications for permits to be filed 3Q 2015. 19 See Disclaimer re Forward-looking Statements and Projections (slide 2) 1. Sum of Measured and Indicated tons and pounds may not add to the reported total due to rounding. 2. Based on grade cutoff of 0.02 percent eU3O8 and a grade x thickness cutoff of 0.25 GT. 3. Measured and Indicated Mineral Resources as defined in Section 1.2 of NI 43-101 (the CIM Definition Standards (CIM Council, 2014)). 4. All reported resources occur below the historic pre-mining static water table. RESOURCE AREA MEASURED INDICATED AVG GRADE % eU3O8 SHORT TONS (X 1000) POUNDS (X 1000) AVG GRADE % eU3O8 SHORT TONS (X 1000) POUNDS (X 1000) FAB TREND 0.280 1,172 6,574 0.119 456 1,081 AREA 5 0.243 195 947 0.115 93 214 TOTAL 0.275 1,367 7,521 0.118 549 1,295 MEASURED & INDICATED 0.230 1,915 8,816 Mineral Resource Estimate Summary July 2014 *Preliminary Economic Assessment Shirley Basin Uranium Project, Carbon County, Wyoming prepared by Western Water Consultants, Inc., d/b/a WWC Engineering – January 27, 2015 (posted on SEDAR).
  • 20. NYSE MKT: URG • TSX: URE January 27, 2015 PEA*  Satellite construction estimated to begin January 2017, with production commencing October 2017  Estimates 6.3 million pounds will be produced from the Project  Project Economics • Gross revenues of US$230.1M LOM • Net cash flow US$215.9M • Internal rate of return (IRR) at 117.0%  Uranium Production Costs • Estimates direct operating costs at US$14.54/lb. • Total cost of production including severance taxes and operational and capital spending is estimated at US$31.26/lb.  Capital requirement of US$30.6M 20 See Disclaimer re Forward-looking Statements and Projections (slide 2) *Preliminary Economic Assessment Shirley Basin Uranium Project, Carbon County, Wyoming prepared by Western Water Consultants, Inc., d/b/a WWC Engineering – January 27, 2015 (posted on SEDAR). Cautionary Statement: This Preliminary Economic Assessment is preliminary in nature and includes mineral resources. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimated mineral recovery used in this Preliminary Economic Assessment is based on site-specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery of mineral resources at this level will be achieved. There is no certainty that the preliminary economic assessment will be realized.
  • 21. NYSE MKT: URG • TSX: URE  2015 US$1.25M Budget (Estimated) • Complete four quarters of baseline data gathering • Submit application converting license from conventional to ISR • Ongoing permitting and licensing throughout 2015  2016 US$1.5M Budget (Estimated) • Complete all permitting and licensing activities • Initiation of financing for capital expenditures • Begin early stage work 21 See Disclaimer re Forward-looking Statements and Projections (slide 2)
  • 22. NYSE MKT: URG • TSX: URE  Lucky Mc – Gas Hills • Historic estimate of resources: 4.7 Mlbs U3O8* • Strategic opportunities with nearby developers  ISR by-product disposal facility • Revenue generating asset • Fully licensed for operation • Multiple disposal agreements in place • Scarce asset – 1 of 4 commercial facilities of this type in the US  Historical US uranium exploration database • Hundreds of project descriptions located in twenty-three states • More than 15,000 drill logs; technical and economic evaluations • Strong addition to Ur-Energy’s existing project database 22 See Disclaimer re Forward-looking Statements and Projections (slide 2) *Ur-Energy is not treating the historic reports as current mineral resources or mineral reserves, because a Qualified Person has not yet conducted sufficient work to classify the estimates as such. Lucky Mc resource estimate is based on an internal 1996 PMC polygonal method estimation.
  • 23. NYSE MKT: URG • TSX: URE  M&I resource average GT of 1.1 (17.2 ft @ 0.065% U3O8)  Shallow: 240 feet deep  Over 3,700 drill holes define deposit 23 See Disclaimer re Forward-looking Statements and Projections (slide 2) NI 43-101 Resource, July 2006 Measured & Indicated: 12.2 Mlbs eU3O8 (in 9.4 Mt @ 0.065%) Inferred: 1.8 Mlbs eU3O8 (in1.6 Mt @ 0.055%)  Can be licensed with NRC as amendment to Lost Creek license (Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR) Lost Soldier Property
  • 24. NYSE MKT: URG • TSX: URE  Growth oriented technical & management team  Proven track record of bringing projects to production • Low-cost uranium production center at Lost Creek • Top producing new project in the US  Development (not exploration) project pipeline  Shirley Basin  Lost Soldier  Multiple long-term uranium sales agreements • Reducing Company exposure to volatile marketplace  Cash flowing project to secure financial picture  Continued re-rating likely as Ur-Energy proves production credentials 24 See Disclaimer re Forward-looking Statements and Projections (slide 2)
  • 25. NYSE MKT: URG • TSX: URE 1. Advance Lost Creek to nameplate production • Maintain “steady state” production • Efficient cost management of mining operations 2. Pathfinder Mines – Shirley Basin • Transition to operating and regulatory activities • Resources NI 43-101 compliant • NI 43-101 PEA completed January 2015 3. Demonstrate growth in production profile • Expand Lost Creek Property resources – June 2015 Technical Report • Further update to Lost Creek resources – anticipated 4Q 2015 • New Initiatives 4. Corporate finance – positive cash position • Lost Creek production revenues • Leader in innovative finance activities 25 See Disclaimer re Forward-looking Statements and Projections (slide 2)
  • 26. NYSE MKT: URG • TSX: URE For more information, please contact: Jeff Klenda, Board Chairman & Executive Director, Acting CEO Rich Boberg, Senior Director of Investor and Public Relations By Mail: Ur-Energy Corporate Office 10758 W. Centennial Rd., Suite 200 Littleton, CO 80127 USA By Phone: Office 720.981.4588 Toll-Free 866.981.4588 Fax 720.981.5643 By E-mail: jeff.klenda@ur-energy.com rich.boberg@ur-energy.com 26