1. RPMES 1st Quarter Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of March 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
SOCIAL SECTOR
1. Pantawid Pamilyang Pilipino DSWD 706.332 World Educ. &
Program (4Ps) Bank & Health:
ADB 97.17%
Family
Development
Session:
91.87%
2. National Household Targeting DSWD 35.427 GOP, On-going
System for Poverty Reduction Loan
Program
3. Red and Black School Building DepEd 146.54 GOP 88.44 %
Program (CY 2011)
4. Rehabilitation of School Building DepEd 29.340 GOP On-going
including Water Sanitation
Facilities
5. Philippine Response to Indigenous DepEd 3.978 AusAid On-going
People’s (IP) and Muslim
Education (PRIME)
6. Construction of Various Health DOH 117.866 GOP 37%
Facility
7. Water System DOH 184.500 GOP 3.61%
8. Cordillera-wide Strengthening of DOH & LGUs 43 JBIC The project is
Local Health System for Effective Abra Apayao on its early
and Efficient Delivery of Maternal Benguet stage since it
and Child Health Services was only
launched on
March 13,2012
1,266.983
ECONOMIC SECTOR
9. Second Cordillera Highland DA 3.081 IFAD, 18%
Agricultural Resource ADB.
Management (CHARM 2) Project OFID
10. Agrarian Reform Infrastructure DAR 903.863 Loan 33.37%
Support Project Phase III GOP
11. Farm-to-Market Roads DA 53 Grant On-going
1
2. RPMES 1st Quarter Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of March 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
12. Irrigation Projects NIA 1,184.838 GOP 8.04%
13. One Town One Product Program DTI 2.273 GOP 12.64%
(OTOP)
14. Rural Micro Enterprise Promotion DTI 1.8 IFAD with On-going
Programme (RuMEPP) GOP
Counter
part
15. Shared Service Facilities Project DTI 1.125 NEDAC Proposal
(SSF) Fund endorsed to
(National RODG, DTI for
Export approval and
Develop- downloading
ment and of funds.
Competi-
tiveness)
16. Small Enterprise Technology DOST 28.673 GOP 3.05%
Upgrading Program (SETUP) Core
and Non-Core Funded Projects
17. Packaging and Labeling DOST 0.688 GOP 11.43%
18. National Greening Program (NGP) DENR 100.527 GOP Seedling
Production:
18%
Maintenance
and
Protection:
14%
Sub-Total 2,279.868
INFRASTRUCTURE SECTOR
Abra
19. Abra-Ilocos Sur Road DPWH 106.195 GOP NTP issued
March 29,
2012
20. Abra-Kalinga Road, K0467+000 DPWH 147.691 GOP Failure of
K0474+305 bidding. Re-
advertised
2
3. RPMES 1st Quarter Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of March 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
21. Abra-Ilocos Norte, K0436+700- DPWH 62 GOP Short of
K0439+395 award.
Awaiting for
the SARO
indicating the
realigned
project.
22. Road Upgrading along Abra- DPWH 60 GOP Short of
Cervantes Road (Realigned from award.
Sto. Tomas-Manabo Bridge) Awaiting for
the SARO
indicating the
realigned
project.
23. Sto. Tomas-Manabo Bridge (P DPWH 160 GOP 49.44%
160.0 M)
24. Abra-Kalinga Road K0410+000- DPWH 50.45 GOP 95.63%
K0413+810
25. Abra-Kalinga Road K0437+490- DPWH 143.67 GOP 75.80%
K0455+890, K0432+000-
K0450+800
Apayao
26. Kabugao-Pudtol-Luna-Cagayan DPWH 58.827 GOP 5% Memo
Boundary Road K0661+000 - (Nov. 3, 2011)
K0661+321, K0643+646 - from Secretary
K0645+825 Gravel to Concrete Singson:
Approved for
upgrading
from
Secondary to
Arterial Road
27. Kabugao- Solsona (Apayao- Ilocos DPWH 100 GOP Not yet started
Norte Road) due to failure
to bidding.
There were no
takers due to
relatively low
estimated unit
3
4. RPMES 1st Quarter Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of March 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
cost. Project is
for rebidding.
Benguet
28. Rehab./Reconst’n/Upgrading of DPWH 54.433 GOP Advertised
Kennon Road March 23,
2012. Bids
opening April
16, 2012
29. Baguio-Bontoc Road (Pico- DPWH 98.674 GOP Advertised
Lamtang Rd., Baguio Itogon & March 23,2012
Baguio-Bontoc)
30. Baguio-Bontoc Road, K0269+000- DPWH 109.332 GOP Bids opening
K0275+000 (v.s.)& K0299+000- April 23, 2012
K0300+900 (v.s.) & K0305+000-
K0308+500 (v.s.) & K0309+000-
K0311+000 (v.s.), K0317+415-
K0318+500 (v.s.), & K0323+000 –
K0328+000 (v.s.)
31. Gurel-Bokod-Kabayan-Buguias- DPWH 98.5 GOP 46.81%
Abatan Road
32. Gurel-Bokod-Kabayan-Buguias- DPWH 116.5 GOP 69.30%
Abatan Road K0303+600-
K03012+000
33. Rehab./Impv’t. of Gurel-Bokod- DPWH 148 GOP Bids opened:
Kabayan-Buguias Road including March 28,
RROW 2012
34. Gurel-Bokod-Kabayan-Buguias- DPWH 68.921 GOP Plans & POW
Abatan Road, K0345+513- submitted to
K0359+300 (vs.) Central office
Feb. 29, 2012.
Advertised:
March 23-29,
2012. Opening
of Bids: April
16, 2012
4
5. RPMES 1st Quarter Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of March 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
Ifugao
35. Banaue-Mayoyao-A Lista-Isabela DPWH 58.064 GOP Failure of
Bdry. Road bidding. Re-
advertised.
36. Nueva Vizcaya-Ifugao-Mt. DPWH 54.163 GOP Bids opened:
Province Road March 28,
2012
Kalinga
37. Kalinga-Abra Road, K0470+000- DPWH 53.057 GOP Bids opened:
K0472+267 March 21,
2012.
Post
evaluation on-
going
38. Kalinga-Abra Road, K0476+000- DPWH 135.27 GOP Failure of
K0480+1000, K0480+1000- bidding. Re-
K0482+700 (with exceptions) advertised.
39. Balbalan-Pinukpuk Road DPWH 100 GOP 31.32%
40. Balbalan-Pinukpuk Road DPWH 245 GOP 10.60%
41. Mt. Province Bdry. –Calanan- DPWH 209 GOP 14.94%
Pinukpuk –Abbut Road (Pinukpuk)
(P209.0 M) K0499+674-
K0509+294 (I.S.)
42. Balbalan-Pinukpuk Road, Abut A DPWH 183.239 GOP Design
of Baay Bridge+(-18502) to Abut A Concept
of Baay Bridge+0 Approved. For
procurement
at CPO.
Mountain Province
43. Mt. Province –Ilocos Sur via Tue DPWH 81.815 GOP 4%
Road
44. Mt. Province-Ilocos Sur via Kayan DPWH 92 GOP 2%
Sub-Total 2,794.801
Total 6,341.652
Sources: Agencies' RPMES PMC Form I-1 and RPMES PMC Form I-2 as of March 2012
5
6. Priority Sectoral Programs/ Projects, CAR
As of March 2012
Cost
Name of Fund Imp Status/
Description Location (Php)
Project/Sector Source Entity Remarks
M
Second Cordillera The project has five Abra, 3.081 IFAD, DA 18%
Highland Agricultural components: Apayao, ADB.
Resource (1) Community mobilization, Benguet, OFID
Management participatory planning of Ifugao,
(CHARM 2) Project investments, and land titling; Kalinga, Mt.
(2) community watershed Province
conservation (including forest
management and agro
forestry development); (3)
agricultural and agribusiness
development, and promotion
of income-generating
activities; (4) rural
infrastructure development;
and (5) project management
and coordination.
Pantawid Pamilyang The program addresses the Regionwide 706.332 World DSWD *Educ. &
Pilipino Program (4Ps) Millennium Development Bank & Health:
Goals such as reducing of ADB 97.17%
extreme poverty and hunger,
achieving universal primary *Family
education, reducing child Development
mortality, improving maternal Session:
health, and promoting gender 91.87%
equality and empowerment of
women. The beneficiaries
must meet the conditions of
the program to avail cash
1
7. Priority Sectoral Programs/ Projects, CAR
As of March 2012
Cost
Name of Fund Imp Status/
Description Location (Php)
Project/Sector Source Entity Remarks
M
grants and each household
beneficiary will receive cash
grants for at most five years.
Agrarian Reform The project involves Abra, 903.863 Loan DAR 33.37%
Infrastructure Support collaboration among the Apayao, GOP
Project Phase III implementing agencies (DAR, Benguet,
DPWH, LGU, and NIA) and Ifugao,
Irrigators Associations. It Kalinga,
involves Mt. Province
construction/rehabilitation of
rural infrastructure such as
irrigation facilities, farm-to-
market roads, post-harvest
facilities, and rural water
supply systems, agrarian
reform information and
marketing center building,
development of coop
managed agri-business/rural
enterprise/ livelihood farmers’
organizations in the ARCs
through appropriate training
and capacity building
approaches.
Kabugao- Solsona The road is a major Kabugao, 100 GOP DPWH Not yet started
(Apayao- Ilocos Norte component of the Cordillera Apayao due to failure
Road) Roads Improvement Project to bidding.
(CRIP) as lateral road; it There were no
2
8. Priority Sectoral Programs/ Projects, CAR
As of March 2012
Cost
Name of Fund Imp Status/
Description Location (Php)
Project/Sector Source Entity Remarks
M
connects Ilocos Region and takers due to
the Northern Cordilleras. It relatively low
traverses the municipalities of estimated unit
Kabugao and Calanasan in cost. Project is
Apayao and turns west to for rebidding.
Solsona in Ilocos Norte.
Kabugao-Pudtol-Luna- The road is a major Apayao 58.827 GOP DPWH 5% Memo
Cagayan Boundary component of the Cordillera (Nov. 3, 2011)
Road Roads Improvement Project from Secretary
K0661+000 - (CRIP) as the northern tip of Singson:
K0661+321, the regional backbone. It Approved for
K0643+646 - traverses the municipalities of upgrading
K0645+825 Gravel to Kabugao, Pudtol and Luna in from
Concrete Apayao and turns east to Secondary to
Abulog in Cagayan. Arterial Road
Cordillera-wide The project aims to enhance Abra, 43 JBIC DOH & The project is
Strengthening of the citizen’s condition health Apayao, LGUs on its early
Local Health System condition particularly of Benguet Abra stage since it
for Effective and women and children through Apayao was only
Efficient Delivery of the delivery of effective and Benguet launched on
Maternal and Child efficient Maternal and Child March 13,2012
Health Services Health (MCH) services.
The project seeks to: (a)
strengthen the local health
systems in all the CAR
Provinces; and (b) improve
the quality of health services.
3
9. Priority Sectoral Programs/ Projects, CAR
As of March 2012
Cost
Name of Fund Imp Status/
Description Location (Php)
Project/Sector Source Entity Remarks
M
National Greening An administration priority Regionwide 100.527 GOP DENR Seedling
Program (NGP) program (Executive Order No. Production:
26) that seeks to attain a 18%
sustainable human
development, economic and Maintenance
ecological security through the and Protection
planting of 1.5 billion trees in : 14%
around 1.5 million hectares of
public land within six years
from year 2011 to 2016.
The NGP also aims to ensure
food security, biodiversity
conservation and address
climate change.
In the Cordillera, the target for
CY 2012 is 7.5 million trees
covering 15,000 hectares.
Red and Black School The Regular School Building Regionwide 146.54 GOP DepEd 88.44 %
Building Program Program specifically targets (CY 2011)
schools which are categorized
under the Red Zone or those
which have a ratio of 56 or
more students to one
classroom: and the Black
Zone, or schools which make
use of makeshift classrooms
and facilities.
The standard DepEd design is
4
10. Priority Sectoral Programs/ Projects, CAR
As of March 2012
Cost
Name of Fund Imp Status/
Description Location (Php)
Project/Sector Source Entity Remarks
M
7m x 9m classroom for rural
areas with a classroom-
student ratio of 1:45. This
standard also applies to all
public secondary schools,
regardless of location and
class size.
5