Your SlideShare is downloading. ×
RCREEE-enerMENA_présentation  algeria
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

RCREEE-enerMENA_présentation algeria

438
views

Published on

Renewable Energy for Project Planners and Managers:enerMENA Professional Training Course for CSP …

Renewable Energy for Project Planners and Managers:enerMENA Professional Training Course for CSP
19-23 August,2013
Cairo, Egypt.

Published in: Technology, Business

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
438
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. RENEWABLE ENERGY JORDANIE 2013
  • 2. Presentation Of The Company The Company of the Engineering of Electricity and Gas CEEG spa is a subsidiary company of SONELGAZ HOLDING, it has in charge of the control of work (studies, control, work, reception and brought into service) of the projects of realization of energy infrastructures (means of electricity production and gas, networks gas transport and high voltage),all of that in the best technical conditions, of cost, quality and schedule of realization. CEEG spa has the roles of : 1 To contribute to the development of general policies of the holding in the fields : • Investments • Technical • Mode of realization of work • Planning 2 To work out the programs of studies and work and to ensure their realization pursuant to the decisions of committee of investment of the holding. 3 To promote and develop national integration in the various phases of construction of the works. 4 To take care of the quality of the design and the studies carried out. 5 To take care of the strict application of the rules of management of the investments, the orders and the markets and contracts. 6 To ensure the permanent control of the building sites the various phases of realization (inspection vehicle, quantity, cost, tests and control before reception and startup of the equipment).
  • 3. Power Plants Electric stations Powerlines Telecommunications Renewables Energies Gas  Activities Activities
  • 4. Président Directeur Général Mr Arkab Mohamed Direction Engineering Réseau Haute Tension Direction Engineering Gaz Direction Engineering Télécommunications Direction Engineering Energies Renouvelables Direction Engineering Postes Direction Engineering Lignes Attachées Communication Assistante de La Direction Générale Direction Engineering Des Moyens de Production Direction Ressources Humaines Direction Finances et Comptabilité Direction Juridique et Réglementation des Marchés Division Commerciale Service Développement Informatique Service Affaires Générales Directeur SIE Our Organisation
  • 5. Map of transmission of electric-energy
  • 6. Fiber optic network
  • 7. gas transport network
  • 8. Renewable energy projects under construction photovoltaic panels plants of 1100 KWc in Ghardaia wind farm of 10,2 MW in KABERTENE - ADRAR Electrification by Photovoltaic power References Acquisition of ten (10) weather stations measure Realization of the factory of manufacture of photovoltaic modules in Rouïba of a capacity of production of 200 MWc/an.
  • 9. 5 1 Electrification by Photovoltaic power2 4 3 Photovoltaic plants of 1100 KWc in Ghardaia Wind farm of 10,2 MW in KABERTENE - ADRAR II. Project Under construction 5 . factory of manufacture of photovoltaic modules in Rouïba of 200 MWc/an Acquisition of ten (10) weather stations measure
  • 10.  Technology selected Silicium multi cristallin  Client: ROUIBA ECLAIRAGE. Spa  Contractors : CEEG / Primo contractor, SIDEM / civil plans, CTC / supervision of works , INERGA /civil Works, ETTERKIB / for Installation of équipements ,  Réalization deadline : 38 mois  The land area: 4,2 Hectares
  • 11.  Client: Sociétés de Distribution de l’Est SDE, l’Ouest SDO et Centre SDC.  Contractor :Le groupement Algérien Inter entreprise/ Aquatec  The land area for one solar Kit : 05 MW  Réalization deadline : 12 months
  • 12. Photovoltaic plants of 1100 KWc in Ghardaia
  • 13. Eolienne + kiosque
  • 14. ……….Suite  Maître d’Ouvrage: SPE Société Algérienne de Production de l’Electricité _ filiale sonelgaz,  Délai de réalisation du projet: 08 mois  Contrat attribué provisoirement à ATLAS AGRO (Suisse) pour l’Acquisition des équipements des stations avec supervision du montage et mise en service d’une station pilote.  Elaboration d’un cahier des charges pour l’étude, fourniture et installation de neufs mâts de mesure météorologiques avec la réalisation des travaux de génie civil en cours. Acquisition of ten (10) weather stations measure
  • 15. IV. Project Before Construction Projet centrale géothermique de 5 MWe à GUELMA Projet de réalisation d’une ferme éolienne de 20MW à KHENCHELA Projets centrales en panneaux photovoltaïques de 3 MW à DJANET,9 MW à TINDOUF et 13 MW à TAMANRASSET