The Management Plan
Management PlanThis consists of the following steps adopted by us:A.   Pre-construction phase:1.   Management of LOCAL PRO...
Pre-construction phase: Management of LocalProblems• LOCAL PROBLEMS need to be taken  care of with respect of land lords, ...
Persual of Drawings and Fixing of Levels•   Complete perusal of drawings•   Co-relation to existing ground•   Working out ...
Grouping of ResourcesA.   Men•    Carpenters (Sutar)•    Masons & Helpers (Kadya)•    Bar Benders (Fitters)•    Labor gang...
Grouping of Resources cond’tB. Machines•   Piling rigs•   Safety equipment: Belts, Caps, Hangover, gloves, boots, etc•   D...
Grouping of Resources cond’t C. Materials •   Cement •   Steel •   Sand •   Aggregates •   Shuttering Material •   Cover B...
Construction Phase Allocation of Resources•   Making available plans to workmen•   Active discussions and coordination wit...
Time Control•   Setting fixed targets•   Tracking targets before they become due•   Monitoring progress of work•   Remidie...
Reporting & Billing• Weekly progress reports• Material Testing Reports• Monthly progress tracks• Monthly Bills• Quarterly ...
Post-Construction phase:Demobilizing•   Removal of concrete plants•   Removal of Labor Colonies•   Removal of Debris      ...
Upcoming SlideShare
Loading in …5
×

The Management Plan

411 views
366 views

Published on

The way we operate

Published in: Business, Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
411
On SlideShare
0
From Embeds
0
Number of Embeds
60
Actions
Shares
0
Downloads
2
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

The Management Plan

  1. 1. The Management Plan
  2. 2. Management PlanThis consists of the following steps adopted by us:A. Pre-construction phase:1. Management of LOCAL PROBLEMS2. Persual of Drawings and Fixing of Levels3. Grouping of ResourcesB. Construction Phase1. Allocation of Resources2. Time Control3. Time Control study4. Reporting & BillingC. Post-Construction phase:1. De-mobilizing2. Clearance of debris and other materials Rachcon InfraProjects Pvt. Ltd. 2011
  3. 3. Pre-construction phase: Management of LocalProblems• LOCAL PROBLEMS need to be taken care of with respect of land lords, farmers, etc.• Most projects fail to start off on time on account of negation of this aspect Rachcon InfraProjects Pvt. Ltd. 2011
  4. 4. Persual of Drawings and Fixing of Levels• Complete perusal of drawings• Co-relation to existing ground• Working out levels and matching them to required as per plan• Fixing of Levels Rachcon InfraProjects Pvt. Ltd. 2011
  5. 5. Grouping of ResourcesA. Men• Carpenters (Sutar)• Masons & Helpers (Kadya)• Bar Benders (Fitters)• Labor gangs (Begaris)• Block work (Bandhkam)• Plaster• Flooring• Finishing• Electricians• Mechanics Rachcon InfraProjects Pvt. Ltd. 2011
  6. 6. Grouping of Resources cond’tB. Machines• Piling rigs• Safety equipment: Belts, Caps, Hangover, gloves, boots, etc• DG Sets• Backhoe’s & JCB’s• RMC Plant• Cranes• Lifts for equipmetns• Concrete Mixers (manual)• Levelling equipments• Cutting Bending Machines• Tough Riders• Transit Mixers• Needle Vibrators• Office cabins, furniture, computers & printers• Bore wells Rachcon InfraProjects Pvt. Ltd. 2011
  7. 7. Grouping of Resources cond’t C. Materials • Cement • Steel • Sand • Aggregates • Shuttering Material • Cover Blocks • Murrum • Cube Moulds • Testing Laboratory • Concrete blocks or Bricks • Tiles • Electrical equipments: Wires, CFL’s, etc • Water pumps • Construction of Labor colonies Rachcon InfraProjects Pvt. Ltd. 2011
  8. 8. Construction Phase Allocation of Resources• Making available plans to workmen• Active discussions and coordination with Engineer in charge• Coordinating with suppliers for on time delivery of construction materials• Conducting tests of materials on site in the inhouse labs• Tracking changes in plans and updating the same• Coordination between workmen – Engineers• Quality Control• Measurements of work done Rachcon InfraProjects Pvt. Ltd. 2011
  9. 9. Time Control• Setting fixed targets• Tracking targets before they become due• Monitoring progress of work• Remidies for time lost• Bi-weekly meetings Rachcon InfraProjects Pvt. Ltd. 2011
  10. 10. Reporting & Billing• Weekly progress reports• Material Testing Reports• Monthly progress tracks• Monthly Bills• Quarterly financial progress Rachcon InfraProjects Pvt. Ltd. 2011
  11. 11. Post-Construction phase:Demobilizing• Removal of concrete plants• Removal of Labor Colonies• Removal of Debris Rachcon InfraProjects Pvt. Ltd. 2011

×