Municipality of Tirana                      AlbaniaProfile of the Tirana ’s River Basin and Hydro                   Power ...
Capital of AlbaniaTirana cityTirana is the capital of Albania. Included surrounding villages, Tirana counts intotal about...
Tirana River   Tirana City
Watershed Area of Tirana     Tirana river tributaries           Ishem           Ishem                      T ii r         ...
The BasinRiver Tirana Tirana river constitutes the principal branch of Ishmi river . It has an ovearlllength of 35 km , a...
Restoration and Rehabilitation of the TiranasRiver’Banks one of the largest project of Tirana |                         Mu...
Rivers crossing the Capital TiranaTwo relevant rivers cross the city; the Lana River and the Tirana river. Those two      ...
Lana RiverLana River is a tributary of River Tirana, which crosses from East to West theurban area of the Capital.
POPULATION AND AGRICULTURE IN WATERSHEDS AREAThe historic and actual archive of HI is usedData to be collected Land use a...
                                     Tirana’s Watershed Chart                                                 Untitled   ...
Tirana River Cascade Hydropower Potential• Tirana’s river watershed energy project, will include the  constructions of two...
Card• Name of the work: HP watershed on Tirana’s river• Installed Power 18,20 MW (Average Annual Energy 68,20  MWh) suppli...
HPP-s technical Data•   Zall-Dajt-HPP•   Q average=0,70m3/sec•   Derivation pipeline Nr1 (Pipe/C/R) 1Ø1m and L=1250 m leng...
HP Turbines• ZALL-DAJT – HPPPELTON type turbine, two sets capacity 1500 kW.• BRAR – HPPPELTON type turbine, two sets capac...
Project’s time Lines and            Financial terms• The anticipated expected investment amounts at  42.60 millions of eur...
Tirana of the near future
A profile of the Tirana's river planned Hydro Power Plant
Upcoming SlideShare
Loading in …5
×

A profile of the Tirana's river planned Hydro Power Plant

908 views
770 views

Published on

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
908
On SlideShare
0
From Embeds
0
Number of Embeds
30
Actions
Shares
0
Downloads
11
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

A profile of the Tirana's river planned Hydro Power Plant

  1. 1. Municipality of Tirana AlbaniaProfile of the Tirana ’s River Basin and Hydro Power Plant Prof.Dr. Edmond Panariti Deputy/Mayor Tirana-Albania
  2. 2. Capital of AlbaniaTirana cityTirana is the capital of Albania. Included surrounding villages, Tirana counts intotal about 800.000 inhabitants among which about 500 000 are located in TiranaMunicipality. The surface extension of the city is 1238 km2
  3. 3. Tirana River Tirana City
  4. 4. Watershed Area of Tirana Tirana river tributaries Ishem Ishem T ii r Tr ana ana La La na na
  5. 5. The BasinRiver Tirana Tirana river constitutes the principal branch of Ishmi river . It has an ovearlllength of 35 km , and collects the water of Lana river and Limuthi branch. Themain river Ishem is formed downstream Tirana city. The hydrographic catchment of Ishmi river has a total area of 673 km2. Ithas a total length of about 75 km and an average elevation of 357 m. The Ishmiriver is formed by three main rivers Tirana river, Tercuza river and Zeza riverTirana river January 2012
  6. 6. Restoration and Rehabilitation of the TiranasRiver’Banks one of the largest project of Tirana | Municipality Tirana River is the most polluted river in Albania
  7. 7. Rivers crossing the Capital TiranaTwo relevant rivers cross the city; the Lana River and the Tirana river. Those two water bodies meet the main Ishem River downstream of Tirana city. Point where Tirana river join’s Lana river
  8. 8. Lana RiverLana River is a tributary of River Tirana, which crosses from East to West theurban area of the Capital.
  9. 9. POPULATION AND AGRICULTURE IN WATERSHEDS AREAThe historic and actual archive of HI is usedData to be collected Land use and urban density (Population) of connected watersheds Density of Rural land Arable Arboriculture Forest Pasture population (%) land (%) (%) (%) Sq/km (%) Tirana 385.5 36.3 29.1 7.2 33.9 4.3 River Tirana 460.4 25.4 19.1 6.3 39.7 6.1 Detailed maps of the river area 1:25.000
  10. 10.  Tirana’s Watershed Chart Untitled 4610000 4608000 4606000 4604000 4602000 4600000 4598000 4596000 4594000 4592000 4590000 1.1 4588000 75 3 22112 0 -5 4586000 EM 4584000 ISH 4582000 4580000 62.6 4578000 0-228 Lana 4576000 4370000 4375000 4380000 4385000 4390000 4395000 4400000 4405000
  11. 11. Tirana River Cascade Hydropower Potential• Tirana’s river watershed energy project, will include the constructions of two hydropower plants situated in two sites along the Tirana river flow Zall-Dajt and Brar.• Average perennial flow rate is 2,7 cubic m/s. The output energy shall enter the 20 kV substation situated 1000 m far from the HP plant. The plant will be placed at approximately 8 km from the capital.• A concession contract is expected to be concluded with the Ministry of Economy and Energy, once an investor shall be identified and will take it over.• Construction permit will be granted by the Government following the presentation of a detailed design of the work.
  12. 12. Card• Name of the work: HP watershed on Tirana’s river• Installed Power 18,20 MW (Average Annual Energy 68,20 MWh) supplied by two hydropower plants
  13. 13. HPP-s technical Data• Zall-Dajt-HPP• Q average=0,70m3/sec• Derivation pipeline Nr1 (Pipe/C/R) 1Ø1m and L=1250 m length• Derivation pipeline Nr 2 (Pipe/C/R) 1Ø 0,8 m and L=1550 m length• Pipeline of turbines (Steel) 2Ø0.90 m and L=130 m length.• Installed Power N=2,60 MW• Average Annual Energy E=11,35 million kWh.• Brar-HPP• Dam from gravel H Dam=55m• Total Volume of Reservoir, V reservoir=41.50 million m3• Regulator volume of Reservoir, V regulator=31.50 million m3• Dead Volume of Reservoir, V dead=10 million m3• Average perennial inflow rate Q average=2,70m3/sec• Derivation: Pipeline C/R Di= 1Ø2.2 m, L=3100 length an tunnel Di=Ø2.2m, L=3100m length• Balance Tower with DT=8m and Height H T=20m• Pipeline of Turbines (Steel) 2Ø1,60 m and L=1100 m length• Installed Power N=15.60 MW• Average annual energy output=68.20 million kWh
  14. 14. HP Turbines• ZALL-DAJT – HPPPELTON type turbine, two sets capacity 1500 kW.• BRAR – HPPPELTON type turbine, two sets capacity 8000 kW.• Energy produced by two HPP-s to be dispatched through a 10.300 m long line of 350 kv in Brari/Tirana substation.• Current Status of Work – Pending a concessionary biding process.• List o Conducted studies include: Hydrology, geology- engineering report, hydrotechnical and hydroenergetic report. Information by the Regional Water Basin Council on details of the concessionary operations, advantages and amounts of water to be used,
  15. 15. Project’s time Lines and Financial terms• The anticipated expected investment amounts at 42.60 millions of euro.• Operational Costs (running and maintenance)at 0.015 euro/kW• Electricity selling price: 0.09-0.12 euro/kWh• Deadline for self-settlement: 9.0-7.3 years• Construction period 3.5 years• Land to be used for the works: To be purchased by the investor in accordance with the price set by the state.
  16. 16. Tirana of the near future

×