SlideShare a Scribd company logo
1 of 63
HYDRO POWER PLANT 
BASIC TERMS, TYPES and 
COMPONENTS 
By 
Prasad Vejendla 
Faculty in Mechanical Engineering 
KHIT, Guntur 
03.09.2012
TYPES OF POWER HOUSE 
• Surface. 
• Semi Under Ground 
• Under Ground.
SURFACE POWER HOUSE 
• All components of the Hydro power projects are 
on the natural/excavated ground surface. 
Surface power house has the advantage of pre-determined 
topography ,design and is easy to 
construct. However, these have the 
disadvantage of limitation of head available as 
per the topography. 
• In such projects the water inlet to the machines 
could be from a penstock or from a tunnel 
terminating into a penstock. The water outlet 
goes into a tail race. 
• If the power house is located just adjacent to the 
Dam then it is sometimes called a Dam-toe 
power house.
Surface Power House
Surface power house 
GENERATOR 
TURBINE 
EOT CRANE
Semi Underground powerhouse 
Some components of the power house are 
underground, while others are on surface. 
The advantages of both surface & 
underground are clubbed together in a 
semi-underground powerhouse, provided 
topography & geology so permit.
UNDER GROUND POWER HOUSE 
• Depending on the topography, a power house may 
have to be located inside a mountain. Such a 
power house is called an under ground power 
house. 
• In such power houses the complete power house 
equipment are located inside Cavern. In such 
power houses various tunnels such as Head race 
tunnel for the water inflow to the turbine, Tail race 
tunnel for water out flow of the turbine and various 
access tunnel have to be provided inside the 
hill/mountain. 
• Such power houses take greater amount of time 
and capital cost to construct.
Contd--- 
• This is very advantages as it overcomes 
the limitations of head available as per 
topography and provide compact and 
economical layout. 
• This requires less land and consequently 
reduce rehabilitation and resettlement 
problems(R&R). However, this has the 
disadvantages of geological uncertainties 
resulting into indeterminate design and 
construction problems leading to time and 
cost over runs
Under ground power house with tunnels
Salient Features of Uri Project 
(underground power house) 
Under ground power house of – 4 X 120MW. 
HRT - 10.6 km X 9.5m dia. Horse shoe Concrete lined 
TRT - 2.2 km X 9.5m dia Horse shoe Concrete lined 
Surge Shaft - 22m circular X 90m depth 
Adits- 4Nos Total1.7km X 6m modified shoe 
Adits- 6-TRT .471km X 6.5 X 7m modified shoe 
Main Access -- .630km tunnel 
Total Tunneling- 19.34km 
Machine Hall- 127mLx22mBx28mH
All the equipment are placed inside a Cavern 
Underground Chamera HEP
CH PH
CH PH
TYPE OF HYDRO POWER 
PROJECT 
• Multi-purpose Project 
• Purely Hydro-electric Project 
• Run of river project 
• Storage Project 
• Pump Storage project
Multi-purpose Project 
Power generation may be one of the 
benefits along with Flood Control, 
Irrigation, Navigation, Drinking Water 
Supply etc. 
Purely Hydro-electric Project 
Project is conceived exclusively for 
power generation.
Run of River Project 
• As the name implies, the project is planned as run of 
the river. 
• Water is diverted from the river, routed through the 
water conductor system and finally water after 
generation of power is thrown back to the river at a 
lower level on down stream. 
• It takes advantage of the drop in elevation that 
occurs over a distance in the river and does not 
involve water storage. 
• Power generation fluctuates with the river flow and 
the firm power is considerably low, as it depends on 
the minimum mean discharge. 
• Canal power projects are also run-of-river projects.
Storage Project 
• Storage projects provide storage or 
pondage and thereby, evens out stream 
flow fluctuations and enhances the water 
head. 
• It increases firm power and total power 
generation by regulating the flow. 
• Providing storage is complicated and 
costly as it involves construction of dam.
Pump Storage project 
• Pump storage projects involve reversible turbines, 
which can generate power from water of upper 
reservoir during peak hours and pump back water from 
lower reservoir to the upper reservoir during off peak 
hours. 
• These projects are advantageous in power system of 
mix type, which have thermal and nuclear power 
houses in addition to hydro power projects. 
• Pump storage project utilizes the off peak surplus 
power of the grid in lifting the water from lower 
reservoir to higher reservoir and generates power 
during peak hours thus flattening the load curve.
HYDRO DEVELOPMENT- IMPORTANT 
TERMS 
• FRL (FULL RESERVOIR LEVEL) 
FRL is the Upper level of the reservoir (selected based 
on techno-economic& submergence considerations) 
• MDDL (MINIMUM DRAWDOWN LEVEL) 
Lowest level up to which the reservoir level could be 
drawn down to withdraw waters for energy generation 
(selected from considerations of silt & turbine 
operational limits) 
• GROSS STORAGE 
Total storage capacity of the reservoir
Hydro Development- IMPORTANT TERMS-Cont 
• DEAD STORAGE 
Reservoir storage which cannot be used for generation 
and is left for silt deposition( below MDDL) 
• LIVE STORAGE 
The storage in the reservoir which is available for power 
generation (between FRL & MDDL) 
• FIRM POWER 
Continuous power output in the entire period of 
hydrological data at 90% dependability 
• FIRM ENERGY 
Energy generated corresponding to firm power
Hydro Development- IMPORTANT 
TERMS- Cont 
• Peak Energy 
Electric energy supplied during periods of relatively high 
system demands. 
• Off-peak Energy 
Electric energy supplied during periods of relatively low 
system demands. 
• Load Factor 
Ratio of the average load over a designated period to the 
peak-load occurring in that period 
• DIURNAL STORAGE 
Storage required to meet daily variations in load demand. It 
depends upon the minimum flows and peak discharges.
Hydro Development- IMPORTANT TERMS 
Cont 
• CRITICAL PERIOD 
Most critical period with respect to system load 
requirements, begins when reservoir begins 
delivering water for generation from full i.e the 
available storage is fully drafted at one point 
during the period; and the critical period ends 
when the storage has completely refilled. 
• CRITICAL DRAW DOWN PERIOD 
That portion of the critical period in which 
reservoir live storage is completely drafted while 
meeting firm energy requirements
IMPORTANT TERMS HEAD – Cont. 
• Design Head 
The head at which the turbine will operate 
to give the best overall efficiency 
under various operating conditions. 
• Gross Head 
The difference of elevations between 
water surfaces of the forebay/ dam and 
tailrace under specified conditions. 
• 
• Net Head 
The gross head chargeable to the turbine 
less all hydraulic losses in water 
conductor system.
Major components of Hydro 
Power Stations 
• Dam/Barrage 
• Water Conductor System 
• Power House
Dam/Barrage 
• Located on rivers, where rock is 
available at larger depth. 
• The dam/ Barrage is used for 
delivering/diverting the water to 
the water conductor system. 
• The barrage is used to regulate the 
water for power generation.
DAM KURICHU
BARRAGE AT URI
Water Conductor System 
• Water conductor system consists of 
head race tunnel of suitable size. 
• Water conductor system may consist 
of tunnel, channel, cut and cover as 
per the topography involved. 
• At end of tunnel there is surge shaft. 
• The water conductor system conveys 
water to penstock.
Components of Water 
Conductor System 
• Water intake structure 
• Head Race Tunnel 
• Surge shaft ,Pressure shaft ,gates, 
gates and hoisting mechanism 
• Penstock Protection Valve 
• Penstock 
• Main inlet Valve 
• Tail Race Tunnel
Water Intake Structure 
• It consists of gated structure at the 
dam/Barrage to control the flow of 
water and provided with gates along 
with hoisting arrangement. 
• Normally these gates remain open and 
allows water to flow to the tunnel 
/channel as the case may be until and 
unless water conductor system is 
taken under shut down for repair and 
maintenance.
Surge Shaft 
• Surge shaft is located at the end of 
tunnel . 
• It is a well type structure of suitable 
height and diameter to absorb the 
upcoming and lowering surges in case 
of tripping and starting of the machine 
in the power house. 
• The surge shaft is provided with gates 
to stop flow of water to the penstock if 
repairs are to be carried out in the 
penstock or inlet valves.
Penstock Protection Valve 
The Penstock protection valves are 
provided after the surge shaft to facilitate 
maintenance of the penstocks. The valves 
are of butterfly type. The BF valve are 
operated hydraulically with provision of 
pressure accumulators in case of power 
failure.
Pressure Shaft 
• When the water conduits in the Surge 
shaft and Main Inlet valve are not exposed 
to the atmosphere and buried in the 
ground/concrete due to its high pressure, 
these are called Pressure shaft.
Penstock 
• Penstocks are the water conductor conduit of 
suitable size connecting the surge shaft to main 
inlet valve 
• It allows water to the turbine through main inlet 
valve. 
• At the end of the penstock a drainage valve is 
provided which drains water from penstock to 
the draft tube. 
• In case of long penstock and high head, 
butterfly valve is provided just before the 
penstock. 
• It takes off from the surge shaft in addition to 
spherical valve at the end of the penstock acting 
as the main inlet valve.
Main Inlet Valve 
• Main inlet valve works as the gate 
valve/isolating valve in the water 
conductor system. 
• It is located before turbine and allows 
water flow from penstock to turbine. 
• MIV acts as closing valve and cuts the 
flow of water during an emergency trip. 
• They are of following type. 
• Butterfly valve (upto 200 m head) 
• Spherical valve (more than200m head)
BUTTERFLY VALVE
BUTTERFLY VALVE
SPHERICAL VALVE
Components of MIV 
• Spherical valve/Butterfly valve 
• Bypass valve 
• Oil pumping unit 
Spherical valve consist of plate which is in line with 
the flow of water when in open condition and in 
totally vertical direction when in closed position. 
Bypass valve acts as a means to charge the 
spherical valve and balance the pressure on either 
side of valve I,e penstock and turbine 
Oil pumping unit is used to pump the oil to operate 
the valve.
Draft Tube 
• Draft tube is located between lower ring of 
turbine and tail race . It conveys water after 
discharge from runner to tail race tunnel. 
• Draft tube (DT) gates are provided for 
isolating the Power house and tail pool 
before taking maintenance of the turbine. 
• The DT gates are provided with hoisting 
mechanism. 
• The DT gate may be a single piece or a 
combination of more than one piece
TTUURRBBIINNEE 
• TTuurrbbiinnee ccoonnvveerrttss ppootteennttiiaall eenneerrggyy ooff wwaatteerr ttoo 
mmeecchhaanniiccaall eenneerrggyy aanndd ttrraannssmmiittss iitt ttoo tthhee ggeenneerraattoorr.. 
• TTuurrbbiinneess ccaann bbee ooff:: 
• KKaappllaann ttyyppee 
• FFrraanncciiss ttyyppee 
• PPeellttoonn ttyyppee 
• BBuullbb ttyyppee 
• MMaaiinn ccoommppoonneennttss ooff tthhee ttuurrbbiinnee iinncclluuddee:: 
• Runner 
• Labyrinths 
• Shaft Seal 
• Guide Bearing 
• Top Cover 
• Lower Ring 
• Guide Vanes
Turbines 
• The hydro project are site specific as such 
the use of standard or off the shelf unit may 
not be possible. The selection of type of 
turbine is made on the basis of “Head”. The 
broad classification is given below. 
• Low head(upto60 m)– Kaplan Turbine 
• Medium head(30to600m)—Francis Turbine 
• High head (more than300m) Pelton
X-SECTION THROUGH 
KAPLAN TURBINE
PELTON TURBINE 
Nore Doppel - 
NORWAY
KAPLAN
SPIRAL CASING
CUT SECTION SPIRAL CASING
FRANCIS RUNNER 
AGUS-PHILIPINES
FRANCIS RUNNER LIFTING
FRANCIS RUNNER BEING 
HANDLED BY EOT CRANE
GGEENNEERRAATTOORR 
• HHyyddrroo ggeenneerraattoorr iiss ccoouupplleedd ttoo tthhee ttuurrbbiinnee aanndd ccoonnvveerrttss tthhee 
mmeecchhaanniiccaall eenneerrggyy ttrraannssmmiitttteedd bbyy tthhee ttuurrbbiinnee ttoo eelleeccttrriiccaall eenneerrggyy 
• GGeenneerraattoorrss ccaann bbee ooff:: 
• SSuussppeennddeedd ttyyppee 
• UUmmbbrreellllaa ttyyppee 
• MMaaiinn GGeenneerraattoorr ccoommppoonneennttss iinncclluuddee:: 
• SSttaattoorr 
• RRoottoorr 
• UUppppeerr BBrraacckkeett 
• LLoowweerr BBrraacckkeett 
• TThhrruusstt BBeeaarriinngg && GGuuiiddee BBeeaarriinnggss 
• SSlliipp RRiinngg && BBrruusshh AAsssseemmbbllyy 
• AAiirr CCoooolleerrss 
• BBrraakkeess && JJaacckkss 
• SSttaattoorr HHeeaatteerrss
UMBRELLA TYPE GENERATOR 
• COMBINED 
LOWER 
THRUST & 
GUIDE 
BEARING
SUSPENDED TYPE GENERATOR 
• UPPER 
THRUST 
BEARING -1 
• UPPER GUIDE 
BEARING -1 
• LOWER GUIDE 
BEARING -1
GEN SEC
STATOR SEGMENT
ROTOR
GGOOVVEERRNNOORR 
• UUsseedd ffoorr ccoonnttrroolllliinngg tthhee gguuiiddee vvaanneess bbyy 
ddeetteeccttiinngg ttuurrbbiinnee ssppeeeedd && iittss gguuiiddee vvaannee 
ooppeenniinngg iinn oorrddeerr ttoo kkeeeepp ttuurrbbiinnee ssppeeeedd 
ssttaabbllee oorr ttoo rreegguullaattee iittss oouuttppuutt.. 
• TThhee ppeerrffoorrmmaannccee ooff tthhee ggoovveerrnnoorr 
ddoommiinnaatteess tthhee ccoonnttrroollllaabbiilliittyy ooff tthhee ppoowweerr 
ppllaanntt aanndd qquuaalliittyy ooff eelleeccttrriiccaall ppoowweerr 
pprroodduucceedd ..
GOVERNOR 
• The hydraulic turbine governor 
is equipment for controlling the 
guide vanes by detecting turbine 
speed and its guide vane 
opening in order to keep the 
turbine speed stable or to 
regulate it's output 
• Governors are provided with the 
following features; 
 Quick Response and Stable 
Control 
 Guide Vane Opening Detection 
with High Accuracy 
 Speed Detection with High 
Accuracy 
 High Reliability 
 Easy Maintenance
Thank You
1.What are the component of water 
conductor system 
Ans:Intake structure, Head race tunnel, 
Surge shaft,Penestock, MIV,Draft tube 
and Tail RaceTunnel 
2.True/falls 
MDDL-Minimum draw down level(yes/no) 
3.FRL- Full reservoir level (yes/no) 
4.RUN OF RIVER have pondage (yes/no) 
5. Pumped storage scheme are generally 
used for peaking power (yes/no)
6.Dewatering system is used to dewater the 
draft tube and other turbine component 
(yes/no) 
7. Surge Shaft is used control upsurge/lower 
Surge in the hydro power station (yes/no) 
8.Under ground power station is installed w 
here there is scarcity of land(yes/no) 
9.GIS stands for Gas insulated Switchgear 
(yes/no) 
10.What are advantages of GIS over 
Conventional switchgear.
• What are the main component on turbine? 
• Why single phase transformers are 
preferred in hydro power plant? 
• Sulfer Hexafluoride gas(SF6) is used in GIS. 
(yes/no) 
• Rotor is the heaviest part of hydro 
generating machine.(yes/no)

More Related Content

What's hot

Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Ryan Triadhitama
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important componentsIEI GSC
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Aniket Raj
 
Elements of Water Conductor System
Elements of Water Conductor SystemElements of Water Conductor System
Elements of Water Conductor SystemSatish Taji
 
Spillway and its types
Spillway and its typesSpillway and its types
Spillway and its typesBilal Mirani
 
hydro power energy water conveyance system
hydro power energy water conveyance system   hydro power energy water conveyance system
hydro power energy water conveyance system khabat shekhany
 
Hydro Electric Power plant
Hydro Electric Power plantHydro Electric Power plant
Hydro Electric Power plantRatan Debnath
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plantCraZzy Shubh
 
Mass and Flow duration curves
Mass and Flow duration curvesMass and Flow duration curves
Mass and Flow duration curvesVignesh Sekar
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantSiraskarCom
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe pptzafaralam7868
 
Dam - Classification based on structure
Dam - Classification based on structureDam - Classification based on structure
Dam - Classification based on structureAbhijit Pal
 
HYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTHYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTKiranmoy Samanta
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -HydraulicsCivil Zone
 

What's hot (20)

Spillways
SpillwaysSpillways
Spillways
 
Spillway
Spillway Spillway
Spillway
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
 
Various types of gates, their important components
Various types of gates, their important componentsVarious types of gates, their important components
Various types of gates, their important components
 
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
Hydroelectric power plant, hydro power plant ppt hydro powerplant pdf, dam wo...
 
Elements of Water Conductor System
Elements of Water Conductor SystemElements of Water Conductor System
Elements of Water Conductor System
 
Spillway and its types
Spillway and its typesSpillway and its types
Spillway and its types
 
hydro power energy water conveyance system
hydro power energy water conveyance system   hydro power energy water conveyance system
hydro power energy water conveyance system
 
Hydro Electric Power plant
Hydro Electric Power plantHydro Electric Power plant
Hydro Electric Power plant
 
Pumped storage hydro power plant
Pumped storage hydro power plantPumped storage hydro power plant
Pumped storage hydro power plant
 
Mass and Flow duration curves
Mass and Flow duration curvesMass and Flow duration curves
Mass and Flow duration curves
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Desin of penstock pipe ppt
Desin of penstock pipe pptDesin of penstock pipe ppt
Desin of penstock pipe ppt
 
Dam - Classification based on structure
Dam - Classification based on structureDam - Classification based on structure
Dam - Classification based on structure
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Spillways
SpillwaysSpillways
Spillways
 
hydro power plant
hydro power planthydro power plant
hydro power plant
 
HYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANTHYDRO-ELECTRIC POWER PLANT
HYDRO-ELECTRIC POWER PLANT
 
Hydro-Electric Power
Hydro-Electric PowerHydro-Electric Power
Hydro-Electric Power
 
Hydropower engineering -Hydraulics
Hydropower engineering -HydraulicsHydropower engineering -Hydraulics
Hydropower engineering -Hydraulics
 

Viewers also liked

Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantGirish Gupta
 
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Er. Abhushan Neupane
 
Small hydropower development in nepal iit roorkee
Small hydropower development in  nepal iit roorkeeSmall hydropower development in  nepal iit roorkee
Small hydropower development in nepal iit roorkeeSanjeev Pokhrel
 
HYDROPOWER DEVELOPMENT IN NEPAL
HYDROPOWER DEVELOPMENT IN NEPALHYDROPOWER DEVELOPMENT IN NEPAL
HYDROPOWER DEVELOPMENT IN NEPALSaroj Upadhyay
 
solar energy--the ultimate renewable resource
  solar energy--the ultimate  renewable resource  solar energy--the ultimate  renewable resource
solar energy--the ultimate renewable resourceGhassan Hadi
 
Renewable energy sources
Renewable energy sourcesRenewable energy sources
Renewable energy sourcesGhassan Hadi
 
fourier representation of signal and systems
fourier representation of signal and systemsfourier representation of signal and systems
fourier representation of signal and systemsSugeng Widodo
 
Binary Pass-Band Modulation Techniques
Binary Pass-Band Modulation TechniquesBinary Pass-Band Modulation Techniques
Binary Pass-Band Modulation TechniquesSugeng Widodo
 
introdution to analog and digital communication
introdution to analog and digital communicationintrodution to analog and digital communication
introdution to analog and digital communicationSugeng Widodo
 
Hydropower in iran. by Dr Siamak Goudarzi, Open Iran
Hydropower in iran. by Dr Siamak Goudarzi, Open IranHydropower in iran. by Dr Siamak Goudarzi, Open Iran
Hydropower in iran. by Dr Siamak Goudarzi, Open IranSiamak Goudarzi, PhD
 
introduction to hydroelectric power
 introduction  to hydroelectric power introduction  to hydroelectric power
introduction to hydroelectric powerGhassan Hadi
 
Pendahuluan dan sistem panas bumi
Pendahuluan dan sistem panas bumiPendahuluan dan sistem panas bumi
Pendahuluan dan sistem panas bumiAnis KD
 
Environmental laws
Environmental laws  Environmental laws
Environmental laws Ghassan Hadi
 
control of AC machines
control of AC machines control of AC machines
control of AC machines Sugeng Widodo
 

Viewers also liked (20)

Performance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power PlantPerformance Evaluation of Small Hydro Power Plant
Performance Evaluation of Small Hydro Power Plant
 
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
Status of Hydropower in Nepal- Presented in CIA Training Session at Luang Pra...
 
Small hydropower development in nepal iit roorkee
Small hydropower development in  nepal iit roorkeeSmall hydropower development in  nepal iit roorkee
Small hydropower development in nepal iit roorkee
 
HYDROPOWER DEVELOPMENT IN NEPAL
HYDROPOWER DEVELOPMENT IN NEPALHYDROPOWER DEVELOPMENT IN NEPAL
HYDROPOWER DEVELOPMENT IN NEPAL
 
solar energy--the ultimate renewable resource
  solar energy--the ultimate  renewable resource  solar energy--the ultimate  renewable resource
solar energy--the ultimate renewable resource
 
SISTIM PANAS BUMI-2
SISTIM PANAS BUMI-2SISTIM PANAS BUMI-2
SISTIM PANAS BUMI-2
 
DC motors
DC motorsDC motors
DC motors
 
가족의 기능
가족의 기능가족의 기능
가족의 기능
 
Renewable energy sources
Renewable energy sourcesRenewable energy sources
Renewable energy sources
 
fourier representation of signal and systems
fourier representation of signal and systemsfourier representation of signal and systems
fourier representation of signal and systems
 
Binary Pass-Band Modulation Techniques
Binary Pass-Band Modulation TechniquesBinary Pass-Band Modulation Techniques
Binary Pass-Band Modulation Techniques
 
introdution to analog and digital communication
introdution to analog and digital communicationintrodution to analog and digital communication
introdution to analog and digital communication
 
Paper
PaperPaper
Paper
 
Hydropower in iran. by Dr Siamak Goudarzi, Open Iran
Hydropower in iran. by Dr Siamak Goudarzi, Open IranHydropower in iran. by Dr Siamak Goudarzi, Open Iran
Hydropower in iran. by Dr Siamak Goudarzi, Open Iran
 
introduction to hydroelectric power
 introduction  to hydroelectric power introduction  to hydroelectric power
introduction to hydroelectric power
 
Pendahuluan dan sistem panas bumi
Pendahuluan dan sistem panas bumiPendahuluan dan sistem panas bumi
Pendahuluan dan sistem panas bumi
 
SISTIM PANAS BUMI-1
SISTIM PANAS BUMI-1SISTIM PANAS BUMI-1
SISTIM PANAS BUMI-1
 
Inverter
InverterInverter
Inverter
 
Environmental laws
Environmental laws  Environmental laws
Environmental laws
 
control of AC machines
control of AC machines control of AC machines
control of AC machines
 

Similar to Basics of Hydro power plant

Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plantSwapnil Gadgune
 
IES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.pptIES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.pptSubbuSuni
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptxWajidMalik27
 
hydroelectricpowerm3-120625045759-phpapp01.pptx
hydroelectricpowerm3-120625045759-phpapp01.pptxhydroelectricpowerm3-120625045759-phpapp01.pptx
hydroelectricpowerm3-120625045759-phpapp01.pptxRaviKumar6132
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plantprem_jovin
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecturec3b2a1
 
Small Hydro Power System_Tidal_Ocean Energy.pptx
Small Hydro Power System_Tidal_Ocean Energy.pptxSmall Hydro Power System_Tidal_Ocean Energy.pptx
Small Hydro Power System_Tidal_Ocean Energy.pptxAmanGanesh1
 
Hydropowerplantppt 161122123345
Hydropowerplantppt 161122123345Hydropowerplantppt 161122123345
Hydropowerplantppt 161122123345AzherAli13
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptxmagedahmed44
 
Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plantRahul Rathod
 
class 4.pptx power plant engineering gas
class 4.pptx power plant engineering gasclass 4.pptx power plant engineering gas
class 4.pptx power plant engineering gasssuser72b8e8
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt9888437802
 

Similar to Basics of Hydro power plant (20)

Hydel Generation and Types Of Turbines
Hydel Generation and Types Of TurbinesHydel Generation and Types Of Turbines
Hydel Generation and Types Of Turbines
 
Lecture 20 hydro electric power plant
Lecture 20 hydro electric power plantLecture 20 hydro electric power plant
Lecture 20 hydro electric power plant
 
IES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.pptIES Academy Fluid Machine by S K Mondal.ppt
IES Academy Fluid Machine by S K Mondal.ppt
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydropower plant
Hydropower plantHydropower plant
Hydropower plant
 
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
369353488-Hydropower-PPT-Water-Resources-Engineering.pptx
 
hydroelectricpowerm3-120625045759-phpapp01.pptx
hydroelectricpowerm3-120625045759-phpapp01.pptxhydroelectricpowerm3-120625045759-phpapp01.pptx
hydroelectricpowerm3-120625045759-phpapp01.pptx
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydro electric power plant lecture
Hydro electric power plant lectureHydro electric power plant lecture
Hydro electric power plant lecture
 
Small Hydro Power System_Tidal_Ocean Energy.pptx
Small Hydro Power System_Tidal_Ocean Energy.pptxSmall Hydro Power System_Tidal_Ocean Energy.pptx
Small Hydro Power System_Tidal_Ocean Energy.pptx
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Hydropowerplantppt 161122123345
Hydropowerplantppt 161122123345Hydropowerplantppt 161122123345
Hydropowerplantppt 161122123345
 
Hydroelectric power
Hydroelectric power Hydroelectric power
Hydroelectric power
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
Introduction to power plant
Introduction to power plantIntroduction to power plant
Introduction to power plant
 
class 4.pptx power plant engineering gas
class 4.pptx power plant engineering gasclass 4.pptx power plant engineering gas
class 4.pptx power plant engineering gas
 
Hydroelectric Power.pptx
Hydroelectric Power.pptxHydroelectric Power.pptx
Hydroelectric Power.pptx
 
Malay nces ppt
Malay nces pptMalay nces ppt
Malay nces ppt
 
Hydropower
HydropowerHydropower
Hydropower
 

Recently uploaded

Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 

Recently uploaded (20)

Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 

Basics of Hydro power plant

  • 1. HYDRO POWER PLANT BASIC TERMS, TYPES and COMPONENTS By Prasad Vejendla Faculty in Mechanical Engineering KHIT, Guntur 03.09.2012
  • 2.
  • 3. TYPES OF POWER HOUSE • Surface. • Semi Under Ground • Under Ground.
  • 4. SURFACE POWER HOUSE • All components of the Hydro power projects are on the natural/excavated ground surface. Surface power house has the advantage of pre-determined topography ,design and is easy to construct. However, these have the disadvantage of limitation of head available as per the topography. • In such projects the water inlet to the machines could be from a penstock or from a tunnel terminating into a penstock. The water outlet goes into a tail race. • If the power house is located just adjacent to the Dam then it is sometimes called a Dam-toe power house.
  • 6. Surface power house GENERATOR TURBINE EOT CRANE
  • 7. Semi Underground powerhouse Some components of the power house are underground, while others are on surface. The advantages of both surface & underground are clubbed together in a semi-underground powerhouse, provided topography & geology so permit.
  • 8. UNDER GROUND POWER HOUSE • Depending on the topography, a power house may have to be located inside a mountain. Such a power house is called an under ground power house. • In such power houses the complete power house equipment are located inside Cavern. In such power houses various tunnels such as Head race tunnel for the water inflow to the turbine, Tail race tunnel for water out flow of the turbine and various access tunnel have to be provided inside the hill/mountain. • Such power houses take greater amount of time and capital cost to construct.
  • 9. Contd--- • This is very advantages as it overcomes the limitations of head available as per topography and provide compact and economical layout. • This requires less land and consequently reduce rehabilitation and resettlement problems(R&R). However, this has the disadvantages of geological uncertainties resulting into indeterminate design and construction problems leading to time and cost over runs
  • 10. Under ground power house with tunnels
  • 11. Salient Features of Uri Project (underground power house) Under ground power house of – 4 X 120MW. HRT - 10.6 km X 9.5m dia. Horse shoe Concrete lined TRT - 2.2 km X 9.5m dia Horse shoe Concrete lined Surge Shaft - 22m circular X 90m depth Adits- 4Nos Total1.7km X 6m modified shoe Adits- 6-TRT .471km X 6.5 X 7m modified shoe Main Access -- .630km tunnel Total Tunneling- 19.34km Machine Hall- 127mLx22mBx28mH
  • 12. All the equipment are placed inside a Cavern Underground Chamera HEP
  • 13. CH PH
  • 14. CH PH
  • 15. TYPE OF HYDRO POWER PROJECT • Multi-purpose Project • Purely Hydro-electric Project • Run of river project • Storage Project • Pump Storage project
  • 16. Multi-purpose Project Power generation may be one of the benefits along with Flood Control, Irrigation, Navigation, Drinking Water Supply etc. Purely Hydro-electric Project Project is conceived exclusively for power generation.
  • 17. Run of River Project • As the name implies, the project is planned as run of the river. • Water is diverted from the river, routed through the water conductor system and finally water after generation of power is thrown back to the river at a lower level on down stream. • It takes advantage of the drop in elevation that occurs over a distance in the river and does not involve water storage. • Power generation fluctuates with the river flow and the firm power is considerably low, as it depends on the minimum mean discharge. • Canal power projects are also run-of-river projects.
  • 18. Storage Project • Storage projects provide storage or pondage and thereby, evens out stream flow fluctuations and enhances the water head. • It increases firm power and total power generation by regulating the flow. • Providing storage is complicated and costly as it involves construction of dam.
  • 19. Pump Storage project • Pump storage projects involve reversible turbines, which can generate power from water of upper reservoir during peak hours and pump back water from lower reservoir to the upper reservoir during off peak hours. • These projects are advantageous in power system of mix type, which have thermal and nuclear power houses in addition to hydro power projects. • Pump storage project utilizes the off peak surplus power of the grid in lifting the water from lower reservoir to higher reservoir and generates power during peak hours thus flattening the load curve.
  • 20. HYDRO DEVELOPMENT- IMPORTANT TERMS • FRL (FULL RESERVOIR LEVEL) FRL is the Upper level of the reservoir (selected based on techno-economic& submergence considerations) • MDDL (MINIMUM DRAWDOWN LEVEL) Lowest level up to which the reservoir level could be drawn down to withdraw waters for energy generation (selected from considerations of silt & turbine operational limits) • GROSS STORAGE Total storage capacity of the reservoir
  • 21. Hydro Development- IMPORTANT TERMS-Cont • DEAD STORAGE Reservoir storage which cannot be used for generation and is left for silt deposition( below MDDL) • LIVE STORAGE The storage in the reservoir which is available for power generation (between FRL & MDDL) • FIRM POWER Continuous power output in the entire period of hydrological data at 90% dependability • FIRM ENERGY Energy generated corresponding to firm power
  • 22. Hydro Development- IMPORTANT TERMS- Cont • Peak Energy Electric energy supplied during periods of relatively high system demands. • Off-peak Energy Electric energy supplied during periods of relatively low system demands. • Load Factor Ratio of the average load over a designated period to the peak-load occurring in that period • DIURNAL STORAGE Storage required to meet daily variations in load demand. It depends upon the minimum flows and peak discharges.
  • 23. Hydro Development- IMPORTANT TERMS Cont • CRITICAL PERIOD Most critical period with respect to system load requirements, begins when reservoir begins delivering water for generation from full i.e the available storage is fully drafted at one point during the period; and the critical period ends when the storage has completely refilled. • CRITICAL DRAW DOWN PERIOD That portion of the critical period in which reservoir live storage is completely drafted while meeting firm energy requirements
  • 24. IMPORTANT TERMS HEAD – Cont. • Design Head The head at which the turbine will operate to give the best overall efficiency under various operating conditions. • Gross Head The difference of elevations between water surfaces of the forebay/ dam and tailrace under specified conditions. • • Net Head The gross head chargeable to the turbine less all hydraulic losses in water conductor system.
  • 25. Major components of Hydro Power Stations • Dam/Barrage • Water Conductor System • Power House
  • 26. Dam/Barrage • Located on rivers, where rock is available at larger depth. • The dam/ Barrage is used for delivering/diverting the water to the water conductor system. • The barrage is used to regulate the water for power generation.
  • 29. Water Conductor System • Water conductor system consists of head race tunnel of suitable size. • Water conductor system may consist of tunnel, channel, cut and cover as per the topography involved. • At end of tunnel there is surge shaft. • The water conductor system conveys water to penstock.
  • 30. Components of Water Conductor System • Water intake structure • Head Race Tunnel • Surge shaft ,Pressure shaft ,gates, gates and hoisting mechanism • Penstock Protection Valve • Penstock • Main inlet Valve • Tail Race Tunnel
  • 31. Water Intake Structure • It consists of gated structure at the dam/Barrage to control the flow of water and provided with gates along with hoisting arrangement. • Normally these gates remain open and allows water to flow to the tunnel /channel as the case may be until and unless water conductor system is taken under shut down for repair and maintenance.
  • 32. Surge Shaft • Surge shaft is located at the end of tunnel . • It is a well type structure of suitable height and diameter to absorb the upcoming and lowering surges in case of tripping and starting of the machine in the power house. • The surge shaft is provided with gates to stop flow of water to the penstock if repairs are to be carried out in the penstock or inlet valves.
  • 33. Penstock Protection Valve The Penstock protection valves are provided after the surge shaft to facilitate maintenance of the penstocks. The valves are of butterfly type. The BF valve are operated hydraulically with provision of pressure accumulators in case of power failure.
  • 34. Pressure Shaft • When the water conduits in the Surge shaft and Main Inlet valve are not exposed to the atmosphere and buried in the ground/concrete due to its high pressure, these are called Pressure shaft.
  • 35. Penstock • Penstocks are the water conductor conduit of suitable size connecting the surge shaft to main inlet valve • It allows water to the turbine through main inlet valve. • At the end of the penstock a drainage valve is provided which drains water from penstock to the draft tube. • In case of long penstock and high head, butterfly valve is provided just before the penstock. • It takes off from the surge shaft in addition to spherical valve at the end of the penstock acting as the main inlet valve.
  • 36. Main Inlet Valve • Main inlet valve works as the gate valve/isolating valve in the water conductor system. • It is located before turbine and allows water flow from penstock to turbine. • MIV acts as closing valve and cuts the flow of water during an emergency trip. • They are of following type. • Butterfly valve (upto 200 m head) • Spherical valve (more than200m head)
  • 40. Components of MIV • Spherical valve/Butterfly valve • Bypass valve • Oil pumping unit Spherical valve consist of plate which is in line with the flow of water when in open condition and in totally vertical direction when in closed position. Bypass valve acts as a means to charge the spherical valve and balance the pressure on either side of valve I,e penstock and turbine Oil pumping unit is used to pump the oil to operate the valve.
  • 41. Draft Tube • Draft tube is located between lower ring of turbine and tail race . It conveys water after discharge from runner to tail race tunnel. • Draft tube (DT) gates are provided for isolating the Power house and tail pool before taking maintenance of the turbine. • The DT gates are provided with hoisting mechanism. • The DT gate may be a single piece or a combination of more than one piece
  • 42. TTUURRBBIINNEE • TTuurrbbiinnee ccoonnvveerrttss ppootteennttiiaall eenneerrggyy ooff wwaatteerr ttoo mmeecchhaanniiccaall eenneerrggyy aanndd ttrraannssmmiittss iitt ttoo tthhee ggeenneerraattoorr.. • TTuurrbbiinneess ccaann bbee ooff:: • KKaappllaann ttyyppee • FFrraanncciiss ttyyppee • PPeellttoonn ttyyppee • BBuullbb ttyyppee • MMaaiinn ccoommppoonneennttss ooff tthhee ttuurrbbiinnee iinncclluuddee:: • Runner • Labyrinths • Shaft Seal • Guide Bearing • Top Cover • Lower Ring • Guide Vanes
  • 43. Turbines • The hydro project are site specific as such the use of standard or off the shelf unit may not be possible. The selection of type of turbine is made on the basis of “Head”. The broad classification is given below. • Low head(upto60 m)– Kaplan Turbine • Medium head(30to600m)—Francis Turbine • High head (more than300m) Pelton
  • 45. PELTON TURBINE Nore Doppel - NORWAY
  • 51. FRANCIS RUNNER BEING HANDLED BY EOT CRANE
  • 52. GGEENNEERRAATTOORR • HHyyddrroo ggeenneerraattoorr iiss ccoouupplleedd ttoo tthhee ttuurrbbiinnee aanndd ccoonnvveerrttss tthhee mmeecchhaanniiccaall eenneerrggyy ttrraannssmmiitttteedd bbyy tthhee ttuurrbbiinnee ttoo eelleeccttrriiccaall eenneerrggyy • GGeenneerraattoorrss ccaann bbee ooff:: • SSuussppeennddeedd ttyyppee • UUmmbbrreellllaa ttyyppee • MMaaiinn GGeenneerraattoorr ccoommppoonneennttss iinncclluuddee:: • SSttaattoorr • RRoottoorr • UUppppeerr BBrraacckkeett • LLoowweerr BBrraacckkeett • TThhrruusstt BBeeaarriinngg && GGuuiiddee BBeeaarriinnggss • SSlliipp RRiinngg && BBrruusshh AAsssseemmbbllyy • AAiirr CCoooolleerrss • BBrraakkeess && JJaacckkss • SSttaattoorr HHeeaatteerrss
  • 53. UMBRELLA TYPE GENERATOR • COMBINED LOWER THRUST & GUIDE BEARING
  • 54. SUSPENDED TYPE GENERATOR • UPPER THRUST BEARING -1 • UPPER GUIDE BEARING -1 • LOWER GUIDE BEARING -1
  • 57. ROTOR
  • 58. GGOOVVEERRNNOORR • UUsseedd ffoorr ccoonnttrroolllliinngg tthhee gguuiiddee vvaanneess bbyy ddeetteeccttiinngg ttuurrbbiinnee ssppeeeedd && iittss gguuiiddee vvaannee ooppeenniinngg iinn oorrddeerr ttoo kkeeeepp ttuurrbbiinnee ssppeeeedd ssttaabbllee oorr ttoo rreegguullaattee iittss oouuttppuutt.. • TThhee ppeerrffoorrmmaannccee ooff tthhee ggoovveerrnnoorr ddoommiinnaatteess tthhee ccoonnttrroollllaabbiilliittyy ooff tthhee ppoowweerr ppllaanntt aanndd qquuaalliittyy ooff eelleeccttrriiccaall ppoowweerr pprroodduucceedd ..
  • 59. GOVERNOR • The hydraulic turbine governor is equipment for controlling the guide vanes by detecting turbine speed and its guide vane opening in order to keep the turbine speed stable or to regulate it's output • Governors are provided with the following features;  Quick Response and Stable Control  Guide Vane Opening Detection with High Accuracy  Speed Detection with High Accuracy  High Reliability  Easy Maintenance
  • 61. 1.What are the component of water conductor system Ans:Intake structure, Head race tunnel, Surge shaft,Penestock, MIV,Draft tube and Tail RaceTunnel 2.True/falls MDDL-Minimum draw down level(yes/no) 3.FRL- Full reservoir level (yes/no) 4.RUN OF RIVER have pondage (yes/no) 5. Pumped storage scheme are generally used for peaking power (yes/no)
  • 62. 6.Dewatering system is used to dewater the draft tube and other turbine component (yes/no) 7. Surge Shaft is used control upsurge/lower Surge in the hydro power station (yes/no) 8.Under ground power station is installed w here there is scarcity of land(yes/no) 9.GIS stands for Gas insulated Switchgear (yes/no) 10.What are advantages of GIS over Conventional switchgear.
  • 63. • What are the main component on turbine? • Why single phase transformers are preferred in hydro power plant? • Sulfer Hexafluoride gas(SF6) is used in GIS. (yes/no) • Rotor is the heaviest part of hydro generating machine.(yes/no)