PMP Exam Sample Questions Set 1

1,146 views
1,056 views

Published on

0 Comments
5 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
1,146
On SlideShare
0
From Embeds
0
Number of Embeds
1
Actions
Shares
0
Downloads
102
Comments
0
Likes
5
Embeds 0
No embeds

No notes for slide

PMP Exam Sample Questions Set 1

  1. 1. PMP® Sample QuestionsPMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate inthe development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy orcontent. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for thePMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as areplacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No suchguarantees or warranties are implied or expressed by OSP International LLC.
  2. 2. This presentation will showcase free sample PMP® questions that will help and guide you in studying for your PMP® examFind more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  3. 3. Sample PMP® Exam Question In a project, several risk response strategies are used to effectively manage project risks. The strategy or mix of strategies should be used when planning for risk responses. Which of the following statements best describes an accept strategy for negative risks or threats? a. Adopting less complex processes is an accept strategy. b. Use of insurance is part of an accept strategy. c. Using contingency reserve is part of accept strategy. d. Extending schedule is part of an accept strategy.HINT: A risk acceptance strategy is adopted because it isseldom possible to eliminate all threats from a project. One ofthe risk acceptance strategies is performed in the early stages ofplanning. Find the option which is performed during planning.
  4. 4. Answer and Explanation The correct answer is C The most common risk acceptance strategy in a project is to establish contingency reserves.
  5. 5. Sample PMP® Exam Question You developed alternative schedules based on the best-case and worst-case scenarios in your project. You want to keep these alternative schedules stored in your project, in case of changes in project resources. Where would you store alternative schedules? a. Schedule Baseline b. Schedule Data c. Project documents d. Project scope statementHINT: Alternative schedules are output of developschedule process. Look for the outputs of developschedule process to see where these schedules arestored.
  6. 6. Answer and Explanation The correct answer is B Schedule data contains alternative schedules such as best-case or worst-case scenario. This is an output of develop schedule process.
  7. 7. Sample PMP® Exam Question Tim is working on an electronic manufacturing project. In his project he wants to establish a warranty for some of the precision parts he is buying. What risk response strategy is he using? a. Mitigate b. Avoid c. Accept d. Transfer HINT: Tim is shifting the negative impact of the risk.
  8. 8. Answer and Explanation The correct answer is D Risk transfer requires shifting some or all of the negative impact of a threat, along with the ownership of the response. Taking out insurance or a warranty transfers the risk from the owner to the other party.
  9. 9. Sample PMP® Exam Question What is risk tolerance? a. Risks created by tolerating customer behavior. b. Willingness to accept varying degrees of risk. c. Risks created by zero tolerance. d. Being tolerant if stakeholders are willing to accept risks. HINT: Look for the “least strange” answer.
  10. 10. Answer and Explanation The correct answer is B Do you feel that A, C and D are odd? Correct, they are and they were included intentionally. Sometimes you can expect to find some “funny” answer choices. Risk tolerance is the stakeholders willingness to accept varying degrees of risk. Choice B is the only correct answer to this question.
  11. 11. Sample PMP® Exam Question You are managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring, and controlling the project work. Which process performs this activity? a. Create WBS b. Define Scope c. Define Activities d. Create Project Management PlanHINT: Estimating is performed when the activitiesare defined and the schedule is prepared.
  12. 12. Answer and Explanation The correct answer is C Activities form a basis for estimating, scheduling, executing, and monitoring and controlling the project work. This is performed in the Define Activities process.
  13. 13. Sample PMP® Exam Question You are considering using WBS templates to create your projects WBS. Where would you most likely find these templates? a. PMIs Practice Standard for WBS b. Microsoft Project Web Site c. Organizational Process Assets d. All of the aboveHINT: Get your mind out of the PMBOK Guide andthink freely for this question.
  14. 14. Answer and Explanation The correct answer is D This question isnt asking about "inputs" to the Create WBS process. The question is simply asking: Where could you find templates to help you build a WBS? All of the answer choices are possible sources for WBS templates.

×