Free PMP® Exam Sample
Question
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Mana...
2
The following PMP® Exam Sample Question is
taken from the Free PMP Exam Simulator:
3
PMP® Exam Sample Question
You are managing a water supply network deployment
project. During project planning you are co...
4
Estimates are never definitive.
All our questions are updated to the latest PMBOK® Guide
standard. Stop by at http://fre...
5
The correct answer is C.
Explanation:
Please note that the question doesn't
ask for the approach that is more
financiall...
Upcoming SlideShare
Loading in...5
×

Free PMP Exam Sample Question 192

214

Published on

The following PMP® Exam Sample Question is taken from the Free PMP Exam Simulator
http://free.pm-exam-simulator.com

Published in: Education
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
214
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
14
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Free PMP Exam Sample Question 192

  1. 1. Free PMP® Exam Sample Question PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  2. 2. 2 The following PMP® Exam Sample Question is taken from the Free PMP Exam Simulator:
  3. 3. 3 PMP® Exam Sample Question You are managing a water supply network deployment project. During project planning you are considering two approaches to lay the pipe network. Approach A will most likely cost $50,000 (±5%). Approach B will most likely cost $25,000 (±40%). Which approach will you select if your project stakeholders' risk tolerances are low and if you want to select the less risky approach? A) Neither approach since they are not definitive estimates. B) Approach B since it ranges from $15,000 to $35,000. C) Approach A since it ranges from $47,500 to $52,500. D) A combination of approach A and B.
  4. 4. 4 Estimates are never definitive. All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam- questions.com. We are a PMI® Registered Education Provider. Hint:
  5. 5. 5 The correct answer is C. Explanation: Please note that the question doesn't ask for the approach that is more financially feasible. Instead, the question asks you to identify the approach that has the lower risk. The larger the range of an estimate, the larger the risk. Since approach B is a wide range estimate, it is more risky. Approach C has a narrow estimate, which makes this approach less risky. Answer and Explanation:
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×