Plan4all: WP7 Time table

Plan4all: WP7 Time table

Statistics

Views

Total Views
125
Views on SlideShare
122
Embed Views
3

Actions

Likes
0
Downloads
0
Comments
0

1 Embed 3

http://geoportal.ccss.cz 3

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Wp7 concept v3 Wp7 concept v3 Presentation Transcript

  • Co-funded by the Community programme e Content plus WP7 Conception Petr Horak
    • WP7 introduction
    • Task 7.2 Data deployment timetable
    • Partners responsibility (identification of responsible person)
    • Proposed portal solution for each partner
    • Data list for publication
    • Task 7.1
  • WP7 Start month – 1 0 => February 2010 (T7.1) - 17 => September 2010 (T7.2) - real start when the inputs from WP is available End month – 30 => October 20 11
    • The aim of the WP is to publish:
      • existing metadata
      • existing data
    • related to spatial planning, which are in the ownership of single data providers.
    • The publishing of data will respect IPRs, which will be agreed between data holder and project team  every partner will be able to decide which data will be publicly available.
    • All metadata will be publicly available.
  • WP7 Interactions
  • WP7 Deliverables HF LGV Hamburg
  • T7.2 Data Deployment
    • Goals:
    • Existing local, regional or national data will be transformed into data following new common conceptual models using transformers implemented in WP6.
    • Data will be published using services from WP6.
    • The transforming and publishing of data will start already from Month 16 (or M17?) in parallel with deploying the platforms, to test their functionality
    Task leader – Help forest
  • T7.2 Data Deployment Task leader – Help forest Responsible Participants
  • D7.2 Data Deployment Stage 1 - M24 (April 2011)
    • Steps
      • Indentification of Data sets for D7.2 – November 2010
      • The structure of D7.2 document – December 2010
      • Implementation of models from WP6 (first version) – February 2011
      • The first draft of the D7.2 report February 2011 – description of the each Content provider ’s deployment solution
      • Testing – March/ April 2011
      • Final D7.2 report – April 2011
    • Questions
      • When and which models will be available for this period???
      • When and which services (transformations, others) will be available for this period??? (January 2011)? Or when?
    • Style of work
      • Each content provider is responsible for deployment on his own portal (or on the Plan4all portal)
      • Technology provider supported content providers - table
      • WP7.2 meeting February/March 2011 – WHERE? 2-3 days??
  • D7.4 Data Deployment Stage 2 M30 (October 2011)
    • Steps
      • Indentification of Final Data sets for D7. 4 – May 2011
      • The structure of D7. 4 document – the same as D7.2 + minor changes – May 2011
      • Implementation of models from WP6 (the second version) – June 2011
      • The first draft of the D7. 4 report August 2011 – description of the each Content provider ’s deployment solution
      • Implementation of all models from WP6 – September 2011
      • Testing – May-September 2011
      • Final D7.4 report – October 2011
    • Questions
      • No new models or services are expected for implementation in this period. Is it right?
    • Style of work
      • Each content provider is responsible for deployment on his own portal (or on the Plan4all portal)
      • Technology provider supported content providers - table
      • WP7.2 meeting September 2011 – WHERE? 2-3 days??
  • T7.2 Data Deployment Task leader – Help forest
    • To do (each partner):
    • To nominate a responsible person for the task 7.2
    • To specify used portal solution
    • To describe current status of portal functionality implementation
    • To confirm data sets for publication
    • To describe current status of the data and metadata publication
    • To specify supporting technology partners (if you plan to directly collaborate with some technology partner)
  • Thanks for your attention Petr Horak