Review Change Out Program Objectives (ERGU) and Drivers (Migration) ...

Review Change Out Program Objectives (ERGU) and Drivers (Migration)
Site Qualifications, Scopes of Work, Phases, Clusters
Current Cut Schedule
Prep, Cut Night, Follow-up
Known lagging sites - potential island sites

Statistics

Views

Total Views
596
Views on SlideShare
596
Embed Views
0

Actions

Likes
0
Downloads
0
Comments
0

0 Embeds 0

No embeds

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

Cw Ergu Project Cw Ergu Project Presentation Transcript

  • Ericsson Replace, Grow, UMTS (ERGU) “Kick Off” Orlando Moreno 408.656.2498 [email_address]
  • Topics
    • Introductions
    • Review Change Out Program Objectives (ERGU) and Drivers (Migration)
    • Site Qualifications, Scopes of Work, Phases, Clusters
    • Current Cut Schedule
    • Prep, Cut Night, Follow-up
    • Known lagging sites - potential island sites
    • Open Discussion
  • Goals
    • Swap BTS, Nokia for Ericsson (9/1/05)
    • Grow site to April 06 forecast (12/31/05)
      • De-grow TDMA
    • Leave site ready for UMTS cabinet (12/31/05)
        • Antennas, Coax, and TMAs already installed
      • Set the Goal High
        • Per Sector; 4 DBDP Antennas, 8 runs of coax
        • Per Site; space for 6 GSM Cabinets + UMTS
    • No negative impact on customer experience
    • Maintain current maintenance window (12-5)
    • Accelerate VCF for Santa Barbara and Kern Counties
  • Site Qualification Philosophy
    • Desire to touch site once
    • Required to go to zoning and lease to try and get standard
    • Constrained to complete all by end of year
    • Results: Multiple Scopes of Work
    • Scope One
      • Minimum 1-1 swap
      • As much as can be done with no lease or zoning impacts
    • Scope Two & Three
      • As needed to complete April 06 Capacity and UMTS Prep
      • If cannot be completed by end of year will be modified to what can be done
      • Exceptions will be approved by Upper management
  • Phases
    • Phase 0 – Site to cut with sub-like for like configuration
      • Generally microcells where existing power will only support one Ericsson microcell, thus site will be single band, two radios
    • Phase 1 – Like for like
      • Same number of radios, dual band (if appropriate). Radios could be distributed across bands differently due to space constrictions.
    • Phase 2 – VCF
      • Radios, antennas, MCPAs, Diplexers, etc. to support April 06 VCF
    • Phase 3 – UMTS Ready
      • All hardware except BTS for UMTS installed
      • 4 ant & 8 Coax / sector OR business decision for lesser antenna system.
    • Phase will change on some sites during process
      • Zoning could come in early, lease negotiations may fail, etc.
    • Goal is to build most advanced Phase for cut, if needed return to complete Phase III before EOY.
  • Quick Stats
    • Tracking 365 on air sites and 84 new build sites for ’05
    • Cut Phase for on air sites, 58% @ VCF, 32% Like for Like, 9% Impacted
      • Phase 0 – 34
      • Phase I – 117
      • Phase II – 91
      • Phase III – 119
    • 29 of 34 Phase 0 sites are JPA Microcells
      • Exceptions: CL07, V005, OV35, OV45, OV68
    • 23 require zoning for cut
    • 51 sites are targeted for HcHc
  • Clusters
    • Defined by BTS Engineering, with input from District RF
    • Goal was to start as far outside of LA core as possible and work in
    • Generally 10 sites, existing and planned new build
    • Plan is to cut 2 clusters 5 nights a week throughout LA
    • District 1 to start with first BSCs for area
    • Initially 1 cluster/night, 2 nights/week
      • 12-5 Monday, 12-5 Wednesday
      • Open to doing 10 sites instead of 1 cluster, reviewing
    • Once Districts 3&4 wrap up their crews will be allocated to remaining districts – picking up our pace
  • Clusters
  • SLO Clusters
  • North County Clusters
  • Santa Barbara Clusters
  • Oxnard Clusters
  • 1000 Oaks Clusters
  • Mono and Kern Clusters
  • Kern Clusters
  • Bakersfield Clusters
  • San Fernando Valley Clusters
  • Palmdale / Lancaster Clusters
  • Rough Schedule
    • Bakersfield Soak Sites 5/16
      • CL07, CL85
      • C303, CL02, CL82 (two of three)
    • Oxnard Soak Sites 5/21
      • SB04, SB35
      • SB40, SB46
      • OV15, OV37
    • Cluster Cuts
      • Cluster 6 5/23
      • Cluster 7 5/25
      • Cluster 8 5/30
      • Cluster 9 6/1
      • Cluster 10 6/6
      • Cluster 12 6/8
      • Cluster 13 6/13
      • Cluster 14 6/15
    • Evaluating accelerating Kern County and Santa Maria in Schedule
  • Pre-Cut Requirements
    • Development of Data Transcripts (DT)
    • RBS Pre-Tests Ericsson Logistics Center
    • Site Preparation per FEED package
    • Ready For Equipment (RFE) Notification - 5 days before planned cutover
    • Equipment Delivery (when possible, before cutover)
    • Permits received and LL approval confirmed
    • TDMA Degrowth (ReStack) – Ian Robb/Mike Lavery
    • E911 –
      • PSAP/Andrew/Intrado Notification and Data Submittal
  • Pre-Cut Requirements
    • Facilities prepared at Switch location (Landline, Internet, etc.)
    • MOP (Planned Works) submitted/approved
    • RBS Pre-Install (when possible)
    • Request for Maintenance window extension (based on site configuration)
    • Establish daily meetings (conference calls) to identify issues in order to confirm that sites are ready for cluster cut.
    • Verify T1 (transport) availability and testing is complete
    • Antenna work 5-10 days before cut
  • Cut Night
    • Pre-check for Site Cutover Go/No Go decision. (includes verifying power, RF jumpers, T1 availability, grounding, etc.)
    • Conference bridge established for Coordinators/PMs in order to be updated during cutover
    • Separate bridge for ASP to communicate with site teams.
    • E911 Re-Cabling and verification
    • Escalation Process In Place
    • Cingular Support Field and Switch Required
    • RF Drive Testing – verify Hand Over and other parameters
    • Trouble Ticket Creation (if required)
  • Post Cut
    • Daily Reports submitted to Cingular by 8AM, (morning of the cluster cut).
    • Asset management Recorded
    • Hand-Over Process to Cingular
    • Nokia Equipment Packed, Pick Up and Ship back to Ericsson Logistics
    • As Built Documentation
    • Performance Reports from RF
  • Communication Plan
    • Weekly update of cut schedule (Bechtel)
      • Sorted by Cluster
      • Email to highlight next 8 clusters to cut
    • Nightly updates of cut results (Ericsson)
    • Antenna Sweeps on eRoom
    • Current Schedule will always be posted in eRoom.
  • Open Discussion
    • QUESTIONS