How to teco the production orders - Murali Krishna Nookella

4,317 views

Published on

How to teco the production orders ppt presentation Murali Krishna Nookella

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
4,317
On SlideShare
0
From Embeds
0
Number of Embeds
43
Actions
Shares
0
Downloads
54
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

How to teco the production orders - Murali Krishna Nookella

  1. 1. How to TECO the production orders Use transaction :COHV Mass processing production orders Note: This is the best and easiest way to TECO the production orders in one go.
  2. 2. Enter the transaction code: COHV and press enter
  3. 3. You will come to this screen
  4. 4. Enter the data mentioned here and scroll down
  5. 5. Actual start date is the date of actual confirmation Actual finish date is the date of actual final confirmation done or production received.
  6. 6. Click on execute icon
  7. 7. System will display all the production orders in the mentioned dates. And it displays the orders that do not have status of TECO and PCNF. Note: We need to TECO the orders that are confirmed and delivered. Status: REL,CNF,DLV
  8. 8. Click here to select all the orders.
  9. 9. Choose the above path
  10. 10. System will pop up the above window.
  11. 11. Choose Technically complete from the above list
  12. 12. Click on execute icon
  13. 13. Click on refresh icon
  14. 14. Check the status now. All the orders have status have TECO,CNF and DLV status. Now these orders can be settled and period end closing can be done.

×