Pointe du Bois Case Study

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    Favorites, Groups & Events

    Pointe du Bois Case Study - Presentation Transcript

    1. EnCurrent Pointe du Bois (Manitoba) CEATI has funded a project to move one step closer to the use of river kinetic turbines to generate power. This emerging technology holds great promise to provide affordable equipment for distributed generation. Kinetic river applications provide continuous power and require flow velocities that should exceed 2 m/s. The project is located on the Winnipeg River at Pointe du Bois in Manitoba Canada and involves New Energy Corporation Inc., the University of Manitoba and Manitoba Hydro. New Energy received support from Natural Resources Canada’s CANMET and TEAM programs in the development of the company’s products and for the deployment at Pointe du Bois. The Pointe du Bois site is managed by the University of Manitoba and is located just upstream of a Manitoba Hydro generating facility. Dr. Eric Bibeau, the NSERC/Manitoba Hydro Alternative Energy Industrial Chair, developed the site and installed two anchor points up-stream of the existing dam in 2006 to support the installation of hydrokinetic turbines. In late October of 2007 New Energy was given a 6 week window of opportunity to install a system at the site. In order to meet the timeline it was decided to install a 5 kW system that was already assembled using a pontoon boat that had been developed for testing. The pontoon boat, which was equipped with a 225 HP outboard motor, was moored in Sicamous BC, approximately 2000 km west of Pointe du Bois. It was not possible to ship the boat through the mountains in one piece so it was decided to disassemble it for shipping purposes. After cutting the pontoon in half with a plasma cutter it was shipped to Calgary where it was re-assembled and reconfigured so that it would eventually support a 25 kW system and transported to Pointe du Bois. Installation of 5 kW EnCurrent Power Generation System The site installation of the 5 kW System began on December 12, 2007. Installation presented difficulties primarily due to the-35 temperatures. On several instances it was thought that the installation would have to be cancelled due to factors such as the pontoon
    2. boat freezing to the shore or becoming stuck in the ice. Perseverance paid off, however, and the system was moved into location downstream of the onsite pedestrian bridge and secured to the existing anchors. The 5 kW System operated through the winter and was removed in March of 2008 in preparation for spring break-up. Initial operation identified that the power produced by the turbine was lower than anticipated. Possible causes included turbulence, drive train losses due to the cold weather, and lower than expected performance of the turbine rotor itself. The cause was eventually isolated to excessive losses from the rotor support arms which were simply square edged steel plates, which were used to minimize manufacturing costs. Performance was dramatically improved by using the same material and profile as used for the aluminum hydrofoils. Operation over the winter season presented significant challenges due to buildup of ice on the aluminum pontoons, requiring regular ice removal using ice picks and hammers. This prompted New Energy to move to plastic pontoons for subsequent installations. The 5 kW System was re-deployed in June 2008 and connected to the Manitoba Hydro grid on June 6th. This represents only the second grid interconnect of a hydrokinetic system in Canada, and the only currently operating installation. Installation of 25 kW EnCurrent Power Generation System Following the grid connect of the 5 kW System, a 25 kW System was deployed in the pontoon boat on June 16th and connected to the Manitoba Hydro grid two days later. The 25 kW System was mounted in the pontoon boat using a cradle and pivot arms to assist in deployment and anchoring of the system. The cradle allows for the turbine to be pivoted out of the water so that the system can be deployed with the turbine installed in the pontoon boat. Additionally, the anchor cables are attached to the pivot arms which in effect anchor the turbine rather than anchoring the pontoon boat. Anchoring of the turbine reduces the floatation required as there is no torque exerted at the front of the pontoon boat. It also ensures that the turbine remains relatively stable on the water flow regardless of the effects on the boat due to surface conditions. The 5 kW System was redeployed in a smaller floating structure using plastic pontoons and the same cradle assembly as utilized in the 25 kW System. This structure is now available as a standard product from New Energy for the 5, 10 and 25 kW models.
    SlideShare Zeitgeist 2009

    + nedakonedako Nominate

    custom

    162 views, 0 favs, 0 embeds more stats

    A mini case-study of the installation of an EnCurre more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 162
      • 162 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 1
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories