Transportation Model
Aim of Transportation Model
To find out optimum transportation
schedule keeping in mind cost of
transportation to be minimized.
What is a Transportation Problem?
ā€¢ The transportation problem is a special type of
LPP where the objective is to minimize the cost
of distributing a product from a number of
sources or origins to a number of destinations.
ā€¢ Because of its special structure the usual simplex
method is not suitable for solving transportation
problems. These problems require special
method of solution.
The Transportation Problem
ā€¢ The problem of finding the minimum-cost
distribution of a given commodity
from a group of supply centers (sources) i=1,ā€¦,m
to a group of receiving centers (destinations)
j=1,ā€¦,n
ā€¢ Each source has a certain supply (si)
ā€¢ Each destination has a certain demand (dj)
ā€¢ The cost of shipping from a source to a
destination is directly proportional to the
number of units shipped
Simple Network Representation
Transpor
tation-5
1
2
m
1
2
n
Sources Destinations
ā€¦
ā€¦
Supply s1
Supply s2
Supply sm
Demand d1
Demand d2
Demand dn
cij
Costs cij
The Transportation Model
Characteristic
ā€¢ A product is to be transported from a number of sources
to a number of destinations at the minimum possible
cost.
ā€¢ Each source is able to supply a fixed number of units of
the product, and each destination has a fixed demand for
the product.
ā€¢ The linear programming model has constraints for supply
at each source and demand at each destination.
ā€¢ All constraints are equalities in a balanced transportation
model where supply equals demand.
ā€¢ Constraints contain inequalities in unbalanced models
where supply is not equal to demand.
Application of Transportation Model
ļ±Minimize shipping costs
ļ±Determine low cost location
ļ±Find minimum cost production schedule
ļ±Military distribution system
Two Types of Transportation
Problem
ā€¢ Balanced Transportation Problem
where the total supply equals total demand
ā€¢ Unbalanced Transportation Problem
where the total supply is not equal to the
total demand
Phases of Solution of
Transportation Problem
ā€¢ Phase I- obtains the initial basic feasible
solution
ā€¢ Phase II-obtains the optimal basic solution
Initial Basic Feasible Solution
ļ±North West Corner Rule (NWCR)
ļ±Row Minima Method
ļ±Column Minima Method
ļ±Least Cost Method
ļ±Vogle Approximation Method (VAM)
Northwest corner rule
ā€¢ The northwest-corner rule requires that we start in
the upper left-hand cell (or northwest corner) of the
table and allocate units to shipping routes as follows:
ā€¢ 1. Exhaust the supply (factory capacity) of each row
before moving down to the next row.
ā€¢ 2. Exhaust the (warehouse) requirements of each
column before moving to the next column on the
right.
ā€¢ 3. Check to ensure that all supplies and demands are
met.
Least cost method
ā€¢ The intuitive method makes initial allocations based on
lowest cost. This straightforward approach uses the
following steps:
ā€¢ 1. Identify the cell with the lowest cost. Break any ties for
the lowest cost arbitrarily.
ā€¢ 2. Allocate as many units as possible to that cell without
exceeding the supply or demand. Then cross out that row
or column (or both) that is exhausted by this assignment.
ā€¢ 3. Find the cell with the lowest cost from the remaining
(not crossed out) cells.
ā€¢ 4. Repeat steps 2 and 3 until all units have been allocated.
Vogelā€™s approximation method
ā€¢ This method also takes costs into account in allocation. Five
steps are involved in applying this heuristic:
ā€¢ Step 1: Determine the difference between the lowest two cells
in all rows and columns, including dummies.
ā€¢ Step 2: Identify the row or column with the largest difference.
Ties may be broken arbitrarily.
ā€¢ Step 3: Allocate as much as possible to the lowest-cost cell in
the row or column with the highest difference. If two or more
differences are equal, allocate as much as possible to the
lowest-cost cell in these rows or columns.
Step 4: Stop the process if all row and column requirements
are met. If not, go to the next step.
Step 5: Recalculate the differences between the two lowest
cells remaining in all rows and columns. Any row and
column with zero supply or demand should not be used in
calculating further differences. Then go to Step 2.
The Vogel's approximation method (VAM) usually produces
an optimal or near- optimal starting solution. One study
found that VAM yields an optimum solution in 80 percent of
the sample problems tested.
Optimum Basic Solution
ļ±Stepping Stone Method
ļ±Modified Distribution Method a.k.a. MODI Method
Optimum Basic Solution:
Stepping-Stone Method
1. Select any unused square to evaluate
2. Beginning at this square, trace a closed
path back to the original square via
squares that are currently being used
3. Beginning with a plus (+) sign at the
unused corner, place alternate minus and
plus signs at each corner of the path just
traced
Stepping-Stone Method
4. Calculate an improvement index by first
adding the unit-cost figures found in each
square containing a plus sign and subtracting
the unit costs in each square containing a
minus sign
5. Repeat steps 1 though 4 until you have
calculated an improvement index for all
unused squares. If all indices are ā‰„ 0, you
have reached an optimal solution.
Problem Illustration
FROM
TO A.
ALBUQUERQU
E
B.
BOSTON
C.
CLEVELAND
FACTORY
CAPACITY
D. DES
MOINES 5 4 3 100
E. EVANSVILLE
8 4 3 300
F. FORT
LAUDERDALE 9 7 5 300
WAREHOUSE
DEMAND 300 200 200 700
Initial Feasible Solution using
Northwest Corner Rule
FROM
TO A.
ALBUQUERQU
E
B.
BOSTON
C.
CLEVELAND
FACTORY
CAPACITY
D. DES
MOINES 5 4
3
100
E. EVANSVILLE
8 4
3
300
F. FORT
LAUDERDALE 9 7
5
300
WAREHOUSE
DEMAND 300 200 200 700
100
200 100
100 200
IFS= DA + EA +EB + FB + FC = 100(5) + 200(8) + 100(4) + 100(7) + 200(5)
= 500 + 1600 + 400 + 700 + 1000 = 4200
Rs5
Rs8 Rs4
Rs4
+ -
+-
Optimizing Solution using
Stepping-Stone Method
To (A)
Albuquerque
(B)
Boston
(C)
Cleveland
(D) Des Moines
(E) Evansville
(F) Fort Lauderdale
Warehouse
requirement 300 200 200
Factory
capacity
300
300
100
700
Rs5
Rs5
Rs4
Rs4
Rs3
Rs3
$9
Rs8
$7
From
100
100
100
200
200
+-
-+
1
100
201 99
99
100200Figure C.5
Des Moines-
Boston index
= Rs4 ā€“ Rs5 + Rs8 - Rs4
= Rs3
Stepping-Stone Method
To (A)
Albuquerque
(B)
Boston
(C)
Cleveland
(D) Des Moines
(E) Evansville
(F) Fort Lauderdale
Warehouse
requirement 300 200 200
Factory
capacity
300
300
100
700
Rs5
Rs5
Rs4
Rs4
Rs3
Rs3
Rs9
Rs8
Rs7
From
100
100
100
200
200
Figure C.6
Start
+-
+
-+
-
Des Moines-Cleveland index
= Rs3 - Rs5 + Rs8 - Rs4 + Rs7 - Rs5 = Rs4
Stepping-Stone Method
To (A)
Albuquerque
(B)
Boston
(C)
Cleveland
(D) Des Moines
(E) Evansville
(F) Fort Lauderdale
Warehouse
requirement 300 200 200
Factory
capacity
300
300
100
700
Rs5
Rs5
Rs4
Rs4
Rs3
Rs3
Rs9
Rs8
Rs7
From
100
100
100
200
200
Evansville-Cleveland index
= Rs3 - Rs4 + Rs7 - Rs5 = Rs1
(Closed path = EC - EB + FB - FC)
Fort Lauderdale-Albuquerque index
= Rs9- Rs7 + Rs4 - Rs8 = -Rs1
(Closed path = FA - FB + EB - EA)
Stepping-Stone Method
1. If an improvement is possible, choose the
route (unused square) with the largest
negative improvement index
2. On the closed path for that route, select the
smallest number found in the squares
containing minus signs
3. Add this number to all squares on the closed
path with plus signs and subtract it from all
squares with a minus sign
Stepping-Stone Method
To (A)
Albuquerque
(B)
Boston
(C)
Cleveland
(D) Des Moines
(E) Evansville
(F) Fort Lauderdale
Warehouse
requirement 300 200 200
Factory
capacity
300
300
100
700
Rs5
Rs5
Rs4
Rs4
Rs3
Rs3
Rs9
Rs8
Rs7
From
100
100
100
200
200
Figure C.7
+
+-
-
1. Add 100 units on route FA
2. Subtract 100 from routes FB
3. Add 100 to route EB
4. Subtract 100 from route EA
Stepping-Stone Method
To (A)
Albuquerque
(B)
Boston
(C)
Cleveland
(D) Des Moines
(E) Evansville
(F) Fort Lauderdale
Warehouse
requirement 300 200 200
Factory
capacity
300
300
100
700
Rs5
Rs5
Rs4
Rs4
Rs3
Rs3
Rs9
Rs8
Rs7
From
100
200
100
100
200
Figure C.8
Total Cost = Rs5(100) + Rs8(100) + Rs4(200) + Rs9(100) + Rs5(200)
= Rs4,000
Special Issues in Modeling
ļƒ¾ Demand not equal to supply
ļƒ¾ Called an unbalanced problem
ļƒ¾ Common situation in the real world
ļƒ¾ Resolved by introducing dummy
sources or dummy destinations as
necessary with cost coefficients of zero
Special Issues in Modeling
Figure C.9
New
Des Moines
capacity
To (A)
Albuquerque
(B)
Boston
(C)
Cleveland
(D) Des Moines
(E) Evansville
(F) Fort Lauderdale
Warehouse
requirement 300 200 200
Factory
capacity
300
300
250
850
Rs5
Rs5
Rs4
Rs4
Rs3
Rs3
Rs9
Rs8
Rs7
From
50200
250
50
150
Dummy
150
0
0
0
150
Total Cost = 250(Rs5) + 50(Rs8) + 200(Rs4) + 50(Rs3) + 150(Rs5) + 150(0)
= Rs3,350
Special Issues in Modeling
ļƒ¾ Degeneracy
ļƒ¾ To use the stepping-stone methodology,
the number of occupied squares in any
solution must be equal to the number of
rows in the table plus the number of
columns minus 1
ļƒ¾ If a solution does not satisfy this rule it is
called degenerate
To Customer
1
Customer
2
Customer
3
Warehouse 1
Warehouse 2
Warehouse 3
Customer
demand 100 100 100
Warehouse
supply
120
80
100
300
Rs8
Rs7
Rs2
Rs9
Rs6
Rs9
Rs7
Rs10
Rs10
From
Special Issues in Modeling
0 100
100
80
20
Figure C.10
Initial solution is degenerate
Place a zero quantity in an unused square and
proceed computing improvement indices
Thank you

More Related Content

What's hot

Assignment Problem
Assignment ProblemAssignment Problem
Assignment ProblemNakul Bhardwaj
Ā 
Transportation and Assignment
Transportation and AssignmentTransportation and Assignment
Transportation and AssignmentLokesh Payasi
Ā 
Introduction to Operations Research
Introduction to Operations ResearchIntroduction to Operations Research
Introduction to Operations ResearchVictor Seelan
Ā 
Transportation Problem In Linear Programming
Transportation Problem In Linear ProgrammingTransportation Problem In Linear Programming
Transportation Problem In Linear ProgrammingMirza Tanzida
Ā 
Operations research - an overview
Operations research -  an overviewOperations research -  an overview
Operations research - an overviewJoseph Konnully
Ā 
Location model smm
Location model smmLocation model smm
Location model smmJoseph Konnully
Ā 
Transportation model and assignment model
Transportation model and assignment modelTransportation model and assignment model
Transportation model and assignment modelpriyanka yadav
Ā 
Operation research ppt chapter one
Operation research ppt   chapter oneOperation research ppt   chapter one
Operation research ppt chapter onemitku assefa
Ā 
Transportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete MathsTransportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete MathsKrupesh Shah
Ā 
Modified distribution method (modi method)
Modified distribution method (modi method)Modified distribution method (modi method)
Modified distribution method (modi method)Dinesh Suthar
Ā 
Centre of gravity method of location planning
Centre of gravity method of location planningCentre of gravity method of location planning
Centre of gravity method of location planningGaganjot Kaur
Ā 
History of Operations Research
History of Operations ResearchHistory of Operations Research
History of Operations ResearchKarishma Chaudhary
Ā 
Assignment problem
Assignment problemAssignment problem
Assignment problemAbu Bashar
Ā 
Stepping Stone Method
Stepping Stone MethodStepping Stone Method
Stepping Stone MethodHimanshi Gupta
Ā 
Transportation problem
Transportation problemTransportation problem
Transportation problemA B
Ā 
Assignment model
Assignment modelAssignment model
Assignment modelPalash Badal
Ā 
Transportation model powerpoint
Transportation model powerpointTransportation model powerpoint
Transportation model powerpointGiselle Gaas
Ā 
Simulation in Operation Research
Simulation in Operation ResearchSimulation in Operation Research
Simulation in Operation ResearchYamini Kahaliya
Ā 
Operation research and its application
Operation research and its applicationOperation research and its application
Operation research and its applicationpriya sinha
Ā 

What's hot (20)

Assignment Problem
Assignment ProblemAssignment Problem
Assignment Problem
Ā 
Transportation and Assignment
Transportation and AssignmentTransportation and Assignment
Transportation and Assignment
Ā 
Introduction to Operations Research
Introduction to Operations ResearchIntroduction to Operations Research
Introduction to Operations Research
Ā 
Transportation Problem In Linear Programming
Transportation Problem In Linear ProgrammingTransportation Problem In Linear Programming
Transportation Problem In Linear Programming
Ā 
Operations research - an overview
Operations research -  an overviewOperations research -  an overview
Operations research - an overview
Ā 
Location model smm
Location model smmLocation model smm
Location model smm
Ā 
Transportation model and assignment model
Transportation model and assignment modelTransportation model and assignment model
Transportation model and assignment model
Ā 
Modi method
Modi methodModi method
Modi method
Ā 
Operation research ppt chapter one
Operation research ppt   chapter oneOperation research ppt   chapter one
Operation research ppt chapter one
Ā 
Transportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete MathsTransportation Modelling - Quantitative Analysis and Discrete Maths
Transportation Modelling - Quantitative Analysis and Discrete Maths
Ā 
Modified distribution method (modi method)
Modified distribution method (modi method)Modified distribution method (modi method)
Modified distribution method (modi method)
Ā 
Centre of gravity method of location planning
Centre of gravity method of location planningCentre of gravity method of location planning
Centre of gravity method of location planning
Ā 
History of Operations Research
History of Operations ResearchHistory of Operations Research
History of Operations Research
Ā 
Assignment problem
Assignment problemAssignment problem
Assignment problem
Ā 
Stepping Stone Method
Stepping Stone MethodStepping Stone Method
Stepping Stone Method
Ā 
Transportation problem
Transportation problemTransportation problem
Transportation problem
Ā 
Assignment model
Assignment modelAssignment model
Assignment model
Ā 
Transportation model powerpoint
Transportation model powerpointTransportation model powerpoint
Transportation model powerpoint
Ā 
Simulation in Operation Research
Simulation in Operation ResearchSimulation in Operation Research
Simulation in Operation Research
Ā 
Operation research and its application
Operation research and its applicationOperation research and its application
Operation research and its application
Ā 

Viewers also liked

9. transportation model
9. transportation model9. transportation model
9. transportation modelSudipta Saha
Ā 
Vogel's Approximation Method & Modified Distribution Method
Vogel's Approximation Method & Modified Distribution MethodVogel's Approximation Method & Modified Distribution Method
Vogel's Approximation Method & Modified Distribution MethodKaushik Maitra
Ā 
Solving Transportation Problem in Operations Research
Solving Transportation Problem in Operations ResearchSolving Transportation Problem in Operations Research
Solving Transportation Problem in Operations ResearchChandan Pahelwani
Ā 
Transportation Assignment
Transportation AssignmentTransportation Assignment
Transportation AssignmentNilam Kabra
Ā 
Transportation Model
Transportation ModelTransportation Model
Transportation ModelKarthik Shakthi
Ā 
Transportation model
Transportation modelTransportation model
Transportation modelSwapnil Chavan
Ā 
MASS CONCRETE
MASS CONCRETEMASS CONCRETE
MASS CONCRETESATISH
Ā 
Simplex method
Simplex methodSimplex method
Simplex methodtatteya
Ā 
transporation problem - stepping stone method
transporation problem - stepping stone methodtransporation problem - stepping stone method
transporation problem - stepping stone methodoragon291764
Ā 
Distribution network desing
Distribution network desingDistribution network desing
Distribution network desingSohag Hasan
Ā 
Bba 3274 qm week 9 transportation and assignment models
Bba 3274 qm week 9 transportation and assignment modelsBba 3274 qm week 9 transportation and assignment models
Bba 3274 qm week 9 transportation and assignment modelsStephen Ong
Ā 
Simplex Method
Simplex MethodSimplex Method
Simplex MethodSachin MK
Ā 
Decision making management chapter 6
Decision making   management chapter 6Decision making   management chapter 6
Decision making management chapter 6Fawad Hussain
Ā 
Quantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pagesQuantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pagestaniyakhurana
Ā 
Transportation in a supply chain management
Transportation in a supply chain managementTransportation in a supply chain management
Transportation in a supply chain managementsai krishna
Ā 
Decision making
Decision makingDecision making
Decision makingAmit Chauhan
Ā 

Viewers also liked (20)

9. transportation model
9. transportation model9. transportation model
9. transportation model
Ā 
Vogel's Approximation Method & Modified Distribution Method
Vogel's Approximation Method & Modified Distribution MethodVogel's Approximation Method & Modified Distribution Method
Vogel's Approximation Method & Modified Distribution Method
Ā 
Solving Transportation Problem in Operations Research
Solving Transportation Problem in Operations ResearchSolving Transportation Problem in Operations Research
Solving Transportation Problem in Operations Research
Ā 
Transportation Assignment
Transportation AssignmentTransportation Assignment
Transportation Assignment
Ā 
Transportation Model
Transportation ModelTransportation Model
Transportation Model
Ā 
Transportation model
Transportation modelTransportation model
Transportation model
Ā 
T P
T PT P
T P
Ā 
MASS CONCRETE
MASS CONCRETEMASS CONCRETE
MASS CONCRETE
Ā 
Simplex method
Simplex methodSimplex method
Simplex method
Ā 
Recruitment
RecruitmentRecruitment
Recruitment
Ā 
transporation problem - stepping stone method
transporation problem - stepping stone methodtransporation problem - stepping stone method
transporation problem - stepping stone method
Ā 
Distribution network desing
Distribution network desingDistribution network desing
Distribution network desing
Ā 
unbalanced transportation problem
unbalanced transportation problemunbalanced transportation problem
unbalanced transportation problem
Ā 
Bba 3274 qm week 9 transportation and assignment models
Bba 3274 qm week 9 transportation and assignment modelsBba 3274 qm week 9 transportation and assignment models
Bba 3274 qm week 9 transportation and assignment models
Ā 
Simplex Method
Simplex MethodSimplex Method
Simplex Method
Ā 
Decision making management chapter 6
Decision making   management chapter 6Decision making   management chapter 6
Decision making management chapter 6
Ā 
Quantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pagesQuantitative techniques introduction 19 pages
Quantitative techniques introduction 19 pages
Ā 
Transportation in a supply chain management
Transportation in a supply chain managementTransportation in a supply chain management
Transportation in a supply chain management
Ā 
Decision making
Decision makingDecision making
Decision making
Ā 
Quantitative Techniques
Quantitative TechniquesQuantitative Techniques
Quantitative Techniques
Ā 

Similar to Transportation model

Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation pptDeepika Bansal
Ā 
transportation-model.ppt
transportation-model.ppttransportation-model.ppt
transportation-model.pptanubhuti18
Ā 
Transportation.pptx
Transportation.pptxTransportation.pptx
Transportation.pptxSauravDash10
Ā 
chapter 3.pptx
chapter 3.pptxchapter 3.pptx
chapter 3.pptxDejeneDay
Ā 
QA CHAPTER III and IV(1)(1).pdf
QA CHAPTER III and IV(1)(1).pdfQA CHAPTER III and IV(1)(1).pdf
QA CHAPTER III and IV(1)(1).pdfTeshome48
Ā 
QABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptxQABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptxhonakjannu789
Ā 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.pptulvikeremov
Ā 
transportation_model (4).ppt
transportation_model (4).ppttransportation_model (4).ppt
transportation_model (4).pptArepuriDeepthi
Ā 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.pptNanoSana
Ā 
5. transportation problems
5. transportation problems5. transportation problems
5. transportation problemsHakeem-Ur- Rehman
Ā 
Transportation problem
Transportation problemTransportation problem
Transportation problemAbhimanyu Verma
Ā 
Productions & Operations Management Chapter 08
Productions & Operations Management Chapter 08Productions & Operations Management Chapter 08
Productions & Operations Management Chapter 08jncgw5t6xq
Ā 
07. Transportation Problem.pptx
07. Transportation Problem.pptx07. Transportation Problem.pptx
07. Transportation Problem.pptxSupplierSepitengTerm
Ā 
Transportatopn problm
Transportatopn problmTransportatopn problm
Transportatopn problmAnshul Singh
Ā 
Chap 10
Chap 10Chap 10
Chap 10geet232
Ā 
03-Unit Three -OR.pptx
03-Unit Three -OR.pptx03-Unit Three -OR.pptx
03-Unit Three -OR.pptxAbdiMuceeTube
Ā 
04-Unit Four - OR.pptx
04-Unit Four - OR.pptx04-Unit Four - OR.pptx
04-Unit Four - OR.pptxAbdiMuceeTube
Ā 

Similar to Transportation model (20)

Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation ppt
Ā 
transportation-model.ppt
transportation-model.ppttransportation-model.ppt
transportation-model.ppt
Ā 
O.R UNIT 3.pdf
O.R UNIT 3.pdfO.R UNIT 3.pdf
O.R UNIT 3.pdf
Ā 
Transportation.pptx
Transportation.pptxTransportation.pptx
Transportation.pptx
Ā 
chapter 3.pptx
chapter 3.pptxchapter 3.pptx
chapter 3.pptx
Ā 
QA CHAPTER III and IV(1)(1).pdf
QA CHAPTER III and IV(1)(1).pdfQA CHAPTER III and IV(1)(1).pdf
QA CHAPTER III and IV(1)(1).pdf
Ā 
OR 14 15-unit_2
OR 14 15-unit_2OR 14 15-unit_2
OR 14 15-unit_2
Ā 
QABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptxQABD Transportation problems-UNIT-3.pptx
QABD Transportation problems-UNIT-3.pptx
Ā 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.ppt
Ā 
transportation_model (4).ppt
transportation_model (4).ppttransportation_model (4).ppt
transportation_model (4).ppt
Ā 
transportation_model.ppt
transportation_model.ppttransportation_model.ppt
transportation_model.ppt
Ā 
5. transportation problems
5. transportation problems5. transportation problems
5. transportation problems
Ā 
Transportation problem
Transportation problemTransportation problem
Transportation problem
Ā 
Productions & Operations Management Chapter 08
Productions & Operations Management Chapter 08Productions & Operations Management Chapter 08
Productions & Operations Management Chapter 08
Ā 
Transportation technique
Transportation techniqueTransportation technique
Transportation technique
Ā 
07. Transportation Problem.pptx
07. Transportation Problem.pptx07. Transportation Problem.pptx
07. Transportation Problem.pptx
Ā 
Transportatopn problm
Transportatopn problmTransportatopn problm
Transportatopn problm
Ā 
Chap 10
Chap 10Chap 10
Chap 10
Ā 
03-Unit Three -OR.pptx
03-Unit Three -OR.pptx03-Unit Three -OR.pptx
03-Unit Three -OR.pptx
Ā 
04-Unit Four - OR.pptx
04-Unit Four - OR.pptx04-Unit Four - OR.pptx
04-Unit Four - OR.pptx
Ā 

Recently uploaded

Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
Ā 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
Ā 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
Ā 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
Ā 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
Ā 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
Ā 
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort serviceGurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort servicejennyeacort
Ā 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
Ā 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
Ā 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
Ā 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
Ā 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
Ā 
Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)
Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)
Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
Ā 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
Ā 

Recently uploaded (20)

Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
Ā 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
Ā 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
Ā 
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
šŸ”9953056974šŸ”!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
Ā 
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Serviceyoung call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
young call girls in Green ParkšŸ” 9953056974 šŸ” escort Service
Ā 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
Ā 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
Ā 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Ā 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
Ā 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
Ā 
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort serviceGurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Gurgaon āœ”ļø9711147426āœØCall In girls Gurgaon Sector 51 escort service
Ā 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
Ā 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
Ā 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
Ā 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
Ā 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
Ā 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
Ā 
Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)
Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)
Call Us ā‰½ 8377877756 ā‰¼ Call Girls In Shastri Nagar (Delhi)
Ā 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
Ā 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Ā 

Transportation model

  • 2. Aim of Transportation Model To find out optimum transportation schedule keeping in mind cost of transportation to be minimized.
  • 3. What is a Transportation Problem? ā€¢ The transportation problem is a special type of LPP where the objective is to minimize the cost of distributing a product from a number of sources or origins to a number of destinations. ā€¢ Because of its special structure the usual simplex method is not suitable for solving transportation problems. These problems require special method of solution.
  • 4. The Transportation Problem ā€¢ The problem of finding the minimum-cost distribution of a given commodity from a group of supply centers (sources) i=1,ā€¦,m to a group of receiving centers (destinations) j=1,ā€¦,n ā€¢ Each source has a certain supply (si) ā€¢ Each destination has a certain demand (dj) ā€¢ The cost of shipping from a source to a destination is directly proportional to the number of units shipped
  • 5. Simple Network Representation Transpor tation-5 1 2 m 1 2 n Sources Destinations ā€¦ ā€¦ Supply s1 Supply s2 Supply sm Demand d1 Demand d2 Demand dn cij Costs cij
  • 6. The Transportation Model Characteristic ā€¢ A product is to be transported from a number of sources to a number of destinations at the minimum possible cost. ā€¢ Each source is able to supply a fixed number of units of the product, and each destination has a fixed demand for the product. ā€¢ The linear programming model has constraints for supply at each source and demand at each destination. ā€¢ All constraints are equalities in a balanced transportation model where supply equals demand. ā€¢ Constraints contain inequalities in unbalanced models where supply is not equal to demand.
  • 7. Application of Transportation Model ļ±Minimize shipping costs ļ±Determine low cost location ļ±Find minimum cost production schedule ļ±Military distribution system
  • 8. Two Types of Transportation Problem ā€¢ Balanced Transportation Problem where the total supply equals total demand ā€¢ Unbalanced Transportation Problem where the total supply is not equal to the total demand
  • 9. Phases of Solution of Transportation Problem ā€¢ Phase I- obtains the initial basic feasible solution ā€¢ Phase II-obtains the optimal basic solution
  • 10. Initial Basic Feasible Solution ļ±North West Corner Rule (NWCR) ļ±Row Minima Method ļ±Column Minima Method ļ±Least Cost Method ļ±Vogle Approximation Method (VAM)
  • 11. Northwest corner rule ā€¢ The northwest-corner rule requires that we start in the upper left-hand cell (or northwest corner) of the table and allocate units to shipping routes as follows: ā€¢ 1. Exhaust the supply (factory capacity) of each row before moving down to the next row. ā€¢ 2. Exhaust the (warehouse) requirements of each column before moving to the next column on the right. ā€¢ 3. Check to ensure that all supplies and demands are met.
  • 12. Least cost method ā€¢ The intuitive method makes initial allocations based on lowest cost. This straightforward approach uses the following steps: ā€¢ 1. Identify the cell with the lowest cost. Break any ties for the lowest cost arbitrarily. ā€¢ 2. Allocate as many units as possible to that cell without exceeding the supply or demand. Then cross out that row or column (or both) that is exhausted by this assignment. ā€¢ 3. Find the cell with the lowest cost from the remaining (not crossed out) cells. ā€¢ 4. Repeat steps 2 and 3 until all units have been allocated.
  • 13. Vogelā€™s approximation method ā€¢ This method also takes costs into account in allocation. Five steps are involved in applying this heuristic: ā€¢ Step 1: Determine the difference between the lowest two cells in all rows and columns, including dummies. ā€¢ Step 2: Identify the row or column with the largest difference. Ties may be broken arbitrarily. ā€¢ Step 3: Allocate as much as possible to the lowest-cost cell in the row or column with the highest difference. If two or more differences are equal, allocate as much as possible to the lowest-cost cell in these rows or columns.
  • 14. Step 4: Stop the process if all row and column requirements are met. If not, go to the next step. Step 5: Recalculate the differences between the two lowest cells remaining in all rows and columns. Any row and column with zero supply or demand should not be used in calculating further differences. Then go to Step 2. The Vogel's approximation method (VAM) usually produces an optimal or near- optimal starting solution. One study found that VAM yields an optimum solution in 80 percent of the sample problems tested.
  • 15. Optimum Basic Solution ļ±Stepping Stone Method ļ±Modified Distribution Method a.k.a. MODI Method
  • 16. Optimum Basic Solution: Stepping-Stone Method 1. Select any unused square to evaluate 2. Beginning at this square, trace a closed path back to the original square via squares that are currently being used 3. Beginning with a plus (+) sign at the unused corner, place alternate minus and plus signs at each corner of the path just traced
  • 17. Stepping-Stone Method 4. Calculate an improvement index by first adding the unit-cost figures found in each square containing a plus sign and subtracting the unit costs in each square containing a minus sign 5. Repeat steps 1 though 4 until you have calculated an improvement index for all unused squares. If all indices are ā‰„ 0, you have reached an optimal solution.
  • 18. Problem Illustration FROM TO A. ALBUQUERQU E B. BOSTON C. CLEVELAND FACTORY CAPACITY D. DES MOINES 5 4 3 100 E. EVANSVILLE 8 4 3 300 F. FORT LAUDERDALE 9 7 5 300 WAREHOUSE DEMAND 300 200 200 700
  • 19. Initial Feasible Solution using Northwest Corner Rule FROM TO A. ALBUQUERQU E B. BOSTON C. CLEVELAND FACTORY CAPACITY D. DES MOINES 5 4 3 100 E. EVANSVILLE 8 4 3 300 F. FORT LAUDERDALE 9 7 5 300 WAREHOUSE DEMAND 300 200 200 700 100 200 100 100 200 IFS= DA + EA +EB + FB + FC = 100(5) + 200(8) + 100(4) + 100(7) + 200(5) = 500 + 1600 + 400 + 700 + 1000 = 4200
  • 20. Rs5 Rs8 Rs4 Rs4 + - +- Optimizing Solution using Stepping-Stone Method To (A) Albuquerque (B) Boston (C) Cleveland (D) Des Moines (E) Evansville (F) Fort Lauderdale Warehouse requirement 300 200 200 Factory capacity 300 300 100 700 Rs5 Rs5 Rs4 Rs4 Rs3 Rs3 $9 Rs8 $7 From 100 100 100 200 200 +- -+ 1 100 201 99 99 100200Figure C.5 Des Moines- Boston index = Rs4 ā€“ Rs5 + Rs8 - Rs4 = Rs3
  • 21. Stepping-Stone Method To (A) Albuquerque (B) Boston (C) Cleveland (D) Des Moines (E) Evansville (F) Fort Lauderdale Warehouse requirement 300 200 200 Factory capacity 300 300 100 700 Rs5 Rs5 Rs4 Rs4 Rs3 Rs3 Rs9 Rs8 Rs7 From 100 100 100 200 200 Figure C.6 Start +- + -+ - Des Moines-Cleveland index = Rs3 - Rs5 + Rs8 - Rs4 + Rs7 - Rs5 = Rs4
  • 22. Stepping-Stone Method To (A) Albuquerque (B) Boston (C) Cleveland (D) Des Moines (E) Evansville (F) Fort Lauderdale Warehouse requirement 300 200 200 Factory capacity 300 300 100 700 Rs5 Rs5 Rs4 Rs4 Rs3 Rs3 Rs9 Rs8 Rs7 From 100 100 100 200 200 Evansville-Cleveland index = Rs3 - Rs4 + Rs7 - Rs5 = Rs1 (Closed path = EC - EB + FB - FC) Fort Lauderdale-Albuquerque index = Rs9- Rs7 + Rs4 - Rs8 = -Rs1 (Closed path = FA - FB + EB - EA)
  • 23. Stepping-Stone Method 1. If an improvement is possible, choose the route (unused square) with the largest negative improvement index 2. On the closed path for that route, select the smallest number found in the squares containing minus signs 3. Add this number to all squares on the closed path with plus signs and subtract it from all squares with a minus sign
  • 24. Stepping-Stone Method To (A) Albuquerque (B) Boston (C) Cleveland (D) Des Moines (E) Evansville (F) Fort Lauderdale Warehouse requirement 300 200 200 Factory capacity 300 300 100 700 Rs5 Rs5 Rs4 Rs4 Rs3 Rs3 Rs9 Rs8 Rs7 From 100 100 100 200 200 Figure C.7 + +- - 1. Add 100 units on route FA 2. Subtract 100 from routes FB 3. Add 100 to route EB 4. Subtract 100 from route EA
  • 25. Stepping-Stone Method To (A) Albuquerque (B) Boston (C) Cleveland (D) Des Moines (E) Evansville (F) Fort Lauderdale Warehouse requirement 300 200 200 Factory capacity 300 300 100 700 Rs5 Rs5 Rs4 Rs4 Rs3 Rs3 Rs9 Rs8 Rs7 From 100 200 100 100 200 Figure C.8 Total Cost = Rs5(100) + Rs8(100) + Rs4(200) + Rs9(100) + Rs5(200) = Rs4,000
  • 26. Special Issues in Modeling ļƒ¾ Demand not equal to supply ļƒ¾ Called an unbalanced problem ļƒ¾ Common situation in the real world ļƒ¾ Resolved by introducing dummy sources or dummy destinations as necessary with cost coefficients of zero
  • 27. Special Issues in Modeling Figure C.9 New Des Moines capacity To (A) Albuquerque (B) Boston (C) Cleveland (D) Des Moines (E) Evansville (F) Fort Lauderdale Warehouse requirement 300 200 200 Factory capacity 300 300 250 850 Rs5 Rs5 Rs4 Rs4 Rs3 Rs3 Rs9 Rs8 Rs7 From 50200 250 50 150 Dummy 150 0 0 0 150 Total Cost = 250(Rs5) + 50(Rs8) + 200(Rs4) + 50(Rs3) + 150(Rs5) + 150(0) = Rs3,350
  • 28. Special Issues in Modeling ļƒ¾ Degeneracy ļƒ¾ To use the stepping-stone methodology, the number of occupied squares in any solution must be equal to the number of rows in the table plus the number of columns minus 1 ļƒ¾ If a solution does not satisfy this rule it is called degenerate
  • 29. To Customer 1 Customer 2 Customer 3 Warehouse 1 Warehouse 2 Warehouse 3 Customer demand 100 100 100 Warehouse supply 120 80 100 300 Rs8 Rs7 Rs2 Rs9 Rs6 Rs9 Rs7 Rs10 Rs10 From Special Issues in Modeling 0 100 100 80 20 Figure C.10 Initial solution is degenerate Place a zero quantity in an unused square and proceed computing improvement indices