Arrow diagram

1,998 views

Published on

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
1,998
On SlideShare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
61
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Arrow diagram

  1. 1. Arrow Diagram
  2. 2. Activity Network diagram, CPM, CPS, PERTDescriptionThe arrow diagram is used to plan and show the required order oftasks in a project or process, the best schedule for the entireproject, and potential scheduling and resource problems and theirsolutions.The arrow diagram, lets you calculate the critical path of theproject. This is the flow of critical steps where delays will affect thetiming of the entire project, and where addition of resources canspeed up the project.
  3. 3. When to use• When planning a complex project or process with interrelated tasks and resources.• When analyzing the timing of a project; this analysis can happen before, during or after the project.• When allocating resources (such as people, money and time) to a project.• When monitoring the progress of a project.• When replanning a project in progress, due to changes in conditions or resources.• Only when you know the steps of the project or process, their sequence, and how long each steps takes.
  4. 4. Procedure Planning 1. List all the necessary tasks in the project or process. One convenient method is to write each task on the top half of a card or Post It note. Across the middle of the card, draw a horizontal arrow pointing right. 2. Determine the correct sequence of the tasks. Do this by asking three questions for each task.• Which tasks must happen before this one can begin?• Which tasks can be done at the same time as this one?• Which tasks should happen immediately after this one? It can be useful to create a table with four columns - prior tasks, this task, simultaneous tasks, following tasks.
  5. 5. Procedure...3. Diagram the network of tasks. If you are using notes or cards,arrange them in sequence on a large piece of paper. Time should flowfrom left to right and concurrent tasks should be vertically aligned.Leave space between the cards.4. Between each two tasks, draw circles for events. An event marks thebeginning or end of a task, a milestone for the project. Thus, events arenodes that separate tasks.
  6. 6. Procedure...5. Look for three common problem situations and redraw them usingdummies or extra events. A dummy is an arrow drawn with dotted lineto separate tasks that would otherwise start and stop with the sameevents, or to show logical sequence of tasks. Dummies are not realtasks.6. When the network is correct, label all events in sequence with eventnumbers in the circle. It can be useful to label all tasks in sequence,using letters.
  7. 7. Scheduling7. Determine the take times. The task time is the best estimate of thetime that each task should require. Use one consistent measuring unit(hours, days, weeks). Write the time on each task’s arrow.8. Determine the critical path. The critical path is the longest path fromthe beginning to the end of the project. Mark the critical path with aheavy line or color. Calculate the length of the critical path: the sum ofall the task times on the path.
  8. 8. Scheduling...9. Calculate the earliest times each task can start and finish, based onhow long preceding tasks take. Start with the first task, where theearliest start is zero, and work forward.Earliest start (ES) = the largest earliest finish of the tasks leading intothis one.Earliest finish (EF) = earliest start + task time
  9. 9. Scheduling...10. Calculate the latest times each task can start and finish withoutupsetting the project schedule, based on how long later tasks will take.Start from the last task, where the latest finish is the project deadlineand work backwards.Latest finish (LF) = the smallest latest start of all the tasks leading outthis one.Latest start (LS) = latest finish - task time
  10. 10. Scheduling...11. Write all four times - ES. EF, LS, LF - beside the task arrow.One common way to show them is in four boxes arranged asfollows:( Example of the arrow diagram on the next two slides ) Earliest Earliest start finish Latest Latest start finish
  11. 11. Earliest start Earliest finish Number of days 1 0 5 Latest finish 5 Develop broad plan 3 8 Latest start 2 5 7 2 Get approval 8 10 3 7 17 10 Identify team 10 20 4 17 19 2 Train team 20 2219 21 Develop detailed plan24 26 5 2 19 23 6 4 Conduct research 22 26 0 7 23 26 3 Identify key practices 28 31
  12. 12. 823 38 Identify partners27 42 15 23 33 10 Collect data 26 36 Critical path 2 0 Identify current Develop 11 state questions 26 28 26 37 10 40 42 31 42 9 Critical path 0 6 33 39 Analyze data39 45 36 42 Visit partners 6 1148 54 39 51 12 Develop new process 12 42 54 0 13 2 51 53 Finalize new process Critical path 54 56 14 53 57 4 Get approval for implementation 56 60 15

×