SlideShare a Scribd company logo
1 of 3
Download to read offline
WSARA: Baselining Programs Early
                    Compounds the Problems
                                                                 Peter Modigliani




      C
                ongress unanimously approved the Weapon System Acquisition Reform Act in 2009
                because if there’s one issue that everyone in Washington can agree on, it’s that defense
                acquisition needs additional reform. While enhanced discipline and rigor is required, the
                section of the law that attempted to control cost growth with additional organizations,
                processes, and requirements early in the acquisition life cycle will actually increase the
      costs and risks of many large programs. 


      Modigliani is an assistant vice president for program management at Alion supporting Air Force acquisition. He is a Project Management Profes-
      sional and Level III certified in program management.




Defense AT&L: July-August 2010
                                                                            12
The biggest pitfall of WSARA is baselining major defense
acquisition programs at Milestone A and driving Nunn-
McCurdy breaches if programs exceed the initial cost and
schedule estimates by 25 percent. At Milestone A, the effort                 We all want to develop major
is still in the early concept stages. The users have developed
an initial capabilities document to define the capability gap
and have conducted an analysis of alternatives of proposed
                                                                             programs faster and cheaper,
materiel solutions. The acquisition community developed
a technology development strategy to reduce technology                                yet the bureaucracy
risk and determine the appropriate set of technologies to
integrate. The Milestone A estimates are developed years                     encumbers speed and agility.
prior to having mature technologies demonstrated on repre-
sentative prototypes, a preliminary design, or requirements
solidified in a capability development document. While esti-
mates are valuable at this stage, WSARA requires cost and
schedule baselines prior to finalizing the scope.                        based on inflated cost estimates, the scope and costs will
                                                                         naturally grow to take advantage of the increased reserves
In the past, if cost estimates increased by 25 percent, the              to reduce risks or add capabilities. 
program manager was required to notify the milestone deci-                
sion authority, typically the Office of the Under Secretary of           An Example
Defense for Acquisition, Technology and Logistics, who then              Let’s examine a program that, by all accounts, is a well-
consulted with the Joint Requirements Oversight Council                  performing, high-demand program in the early stages of
on requirements and determined if the program warranted                  the life cycle. It baselined costs and schedule at Milestone
the resources required. In WSARA, Congress added new                     A and is maturing technologies via competitive prototypes
schedule criteria, and now, exceeding cost or schedule es-               and other early systems engineering efforts. The program
timates by 25 percent drives a Nunn-McCurdy breach, in                   manager comes to the realization that some of the critical
which the default plan would be to terminate the program.                technologies will cost more or take longer to develop than
If DoD wanted to continue with such a program, it would                  was originally planned two years ago based on initial as-
need to re-accomplish the Milestone A and face additional                sessments. There is full support from all key stakeholders
oversight, reporting, and scrutiny.                                      (combatant commanders, the Pentagon, and Capitol Hill)
                                                                         to proceed with this program, but it must now take a bu-
The Fallout of WSARA                                                     reaucratic time out.
Now, I will be the first to admit that DoD needs to get a
tighter grip on scope and cost growth, and 25 percent cost               The Joint Requirements Oversight Council will call for a se-
growth on a major defense acquisition program is a signifi-              ries of review boards to revalidate requirements. The Office
cant amount, but let’s take a step back and look at what                 of the Secretary of Defense’s director of cost assessment
WSARA truly does here. In the early stages of the acqui-                 and program evaluation will need to conduct an in-depth
sition life cycle, you are still defining the scope based on             cost estimate, which typically takes six months. The new
initial requirements, technology maturity, funding, cost, and            director of performance assessment and root cause analy-
schedule estimates. WSARA requires baselining based on                   sis will need to conduct a root cause analysis, and it could
the initial analysis, with severe consequences on breaching.             take months to audit the program. This is all in addition to
The fidelity of the cost and schedule estimates is low due to            the analysis and reviews conducted by the users, program
the significant amount of unknowns with the effort.                      office, program executive office staff, and Service headquar-
                                                                         ters staffs. Finally, the milestone decision authority will need
To reduce the risk of a Nunn-McCurdy breach, program                     to conduct additional reviews and the staffs will compile a
managers will now be motivated to inflate their cost and                 report to submit to Congress. While WSARA dictates that
schedule estimates to account for all the unknowns and                   a report be sent to Congress within 30 days upon the pro-
allow for more of a buffer. Yet presenting a higher cost es-             gram manager notifying the milestone decision authority,
timate likely exceeds the current program budget, thereby                no one finds that to be a realistic timeframe. It is difficult to
raising a full funding issue. If the cost estimates are too high,        staff a simple one-page memo through the Pentagon within
leadership may decide not to continue with an otherwise                  30 days, let alone a major analysis determining the fate of
valuable program. If the program does get approval, it will              a major defense acquisition program. The program can
likely require funds from other sources to ensure funding is             either fail to meet the 30-day suspense to Congress and/
at an acceptable cost confidence level. While independent                or the program manager delays formal milestone decision
cost estimates may help keep the program manager honest,                 authority notification. Congressional staffers and members
they will also be based on an undefined scope and ample un-              will also likely call for meetings or hearings to discuss the
knowns. Once a program manager has an approved program                   program further.

                                                                    13                                      Defense AT&L: July-August 2010
Avoiding termination, the program is now required to spend
the next six months re-accomplishing its Milestone A be-
fore it can resume technology development and prototyping.            A Six-Pack of Tips for
Both the Nunn-McCurdy process and re-accomplishing the
previous milestone can easily delay the program a year or             Defense AT&L Authors
two, which increases costs and compounds risk. The Of-
fice of the Secretary of Defense and the Service will need to
rebalance funding profiles while government and industry
will reallocate resources during the delays. This scenario was



                                                                      1
all because the estimates done prior to fully understanding
the program did not properly account for all the unknowns.                    Look at back issues of the magazine.
                                                                              If we printed an article on a particu-
Focusing on Milestone B                                                       lar topic a couple of issues ago, we're
The DoD Acquisition Framework traditionally focused on                unlikely to print another for a while—unless
the acquisition program starting at Milestone B, following            it offers brand new information or a different
ample planning and analysis of requirements, technologies,            point of view.



                                                                      2
and costs as well as a sound acquisition strategy. The in-
creased emphasis on early systems engineering, analysis                      We look on articles much more favor-
of alternatives, and cost estimates helps leadership make a                  ably if they follow our author guide-
sound decision at Milestone B on whether to grant approval                   lines on format, length, and presen-
to begin development. At Milestone B, the milestone deci-             tation. You'll find them at <http://www.
sion authority approves the acquisition program baseline,             dau.mil/pubs/pdf/DAT&L%20author%20
and the program manager must manage cost, schedule, and               guidelines_080528.pdf>   .



                                                                      3
performance within those limitations. Baselining programs
at Milestone A effectively forces planning and analysis to                    Number the pages in your manuscript
be performed years sooner. It’s almost getting to the point                   and put your name on every page. It
where once someone comes up with the need for a mate-                         makes our life so much easier if we
riel solution, he had better have all the details known the           happen to drop a stack of papers and your
next day. If Congress reversed those aspects of WSARA, it             article's among them.



                                                                      4
would put the focus back on Milestone B, allowing for proper
planning and still permitting the Office of the Secretary of                  Do avoid acronyms as far as pos-
Defense and Joint Staff to conduct checks and balances if                     sible, but if you must use them,
costs or schedules grow 25 percent higher than originally                     define them—every single one,
estimated. It would allow for more realistic Milestone A cost         however obvious you think it is. We get
and schedule estimates and reduce overall program cost                testy if we have to keep going to acronym
and schedule risks.                                                   finder.com, especially when we discover 10
                                                                      equally applicable possibilities for one ac-
A Major Concern                                                       ronym.



                                                                      5
At a recent conference, I raised this issue to a panel of cur-
rent and former senior DoD acquisition executives, and                       Fax the Certification as a Work of
they all agreed this was a major concern that will plague                    the U.S. Government form when
the department for years. As the expanded defense acqui-                     you e-mail your article because we
sition bureaucracy spends the next few years defining and             can’t review your manuscript until we have
implementing the new roles, policies, and processes, I hope           the release. Download it at <http://www.
they provide feedback to Congress on these unintended con-            dau.mil/pubs/pdf/DAT&L%20author%20
sequences. The draft IMPROVE Act of 2010 on Capitol Hill              guidelines_080528.pdf> Please don't make
                                                                                             .
these days does not address this early baselining issue, but          us chase you down for it. And please fill it
rather adds performance metrics. We all want to develop               out completely, even if you've written for
major programs faster and cheaper, yet the bureaucracy                us before.



                                                                      6
encumbers speed and agility. If we truly want to address
cost growth, we need to develop innovative approaches to                     We'll acknowledge receipt of your
streamline the bureaucracy, not expand it.                                   submission within three or four days
                                                                             and e-mail you a publication decision
                                                                      in four to five weeks. No need to remind us.
                                                                      We really will. Scout’s honor.
The author welcomes comments and questions and can be
contacted at peter.modigliani@yahoo.com.

Defense AT&L: July-August 2010                                   14

More Related Content

What's hot

Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbierNASAPMC
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Department of Energy and Climate Change
 
Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...
Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...
Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...Covance
 
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Department of Energy and Climate Change
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project ReportRISHABHSIINGH
 
Risk management plan loren schwappach
Risk management plan   loren schwappachRisk management plan   loren schwappach
Risk management plan loren schwappachLoren Schwappach
 
Global Program Management
Global Program ManagementGlobal Program Management
Global Program ManagementRex Baldwin
 
Fme project-risk
Fme project-riskFme project-risk
Fme project-risksahil mehta
 
Software Project Management by CMMi Level 5
Software Project Management by CMMi Level 5Software Project Management by CMMi Level 5
Software Project Management by CMMi Level 5mekongsolution
 
Bilbro james
Bilbro jamesBilbro james
Bilbro jamesNASAPMC
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
planonapage 14_15 2014-05-19
planonapage 14_15 2014-05-19planonapage 14_15 2014-05-19
planonapage 14_15 2014-05-19David McBride
 
Svarcas.rita
Svarcas.ritaSvarcas.rita
Svarcas.ritaNASAPMC
 
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualKemppe
 
Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...p6academy
 

What's hot (20)

Scope creep - cylfe campain
Scope creep - cylfe campainScope creep - cylfe campain
Scope creep - cylfe campain
 
Zimmerman barbier
Zimmerman barbierZimmerman barbier
Zimmerman barbier
 
Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...Decc discussion slides investor simulation workshop breakout_biomass conversi...
Decc discussion slides investor simulation workshop breakout_biomass conversi...
 
Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...
Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...
Creating Value - Compressing Time - Refining Burn Rate Forecasts: The Molecul...
 
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...Decc discussion slides investor simulation workshop breakout_onshore large-sc...
Decc discussion slides investor simulation workshop breakout_onshore large-sc...
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
 
D081073[1]
D081073[1]D081073[1]
D081073[1]
 
Risk management plan loren schwappach
Risk management plan   loren schwappachRisk management plan   loren schwappach
Risk management plan loren schwappach
 
Global Program Management
Global Program ManagementGlobal Program Management
Global Program Management
 
Fme project-risk
Fme project-riskFme project-risk
Fme project-risk
 
Software Project Management by CMMi Level 5
Software Project Management by CMMi Level 5Software Project Management by CMMi Level 5
Software Project Management by CMMi Level 5
 
Bilbro james
Bilbro jamesBilbro james
Bilbro james
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
planonapage 14_15 2014-05-19
planonapage 14_15 2014-05-19planonapage 14_15 2014-05-19
planonapage 14_15 2014-05-19
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Svarcas.rita
Svarcas.ritaSvarcas.rita
Svarcas.rita
 
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
 
Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...Portfolio management and the ppbe process at the department of energy white p...
Portfolio management and the ppbe process at the department of energy white p...
 
Pm Student Ho
Pm Student HoPm Student Ho
Pm Student Ho
 
Getting it Right
Getting it Right Getting it Right
Getting it Right
 

Viewers also liked

Come step back
Come step backCome step back
Come step backRenny
 
History of Tower Butte
History of Tower ButteHistory of Tower Butte
History of Tower ButtePapillon
 
Payton_P3_Horses
Payton_P3_HorsesPayton_P3_Horses
Payton_P3_HorsesMs Wilson
 
Winter Worries
Winter WorriesWinter Worries
Winter WorriesRenny
 
Comparing the 401k to the 403b
Comparing the 401k to the 403bComparing the 401k to the 403b
Comparing the 401k to the 403bWayne Demeester
 
Winter idyll
Winter idyllWinter idyll
Winter idyllRenny
 
Important trees
Important treesImportant trees
Important treesRenny
 
Fee-Only Investment Advisors
Fee-Only Investment AdvisorsFee-Only Investment Advisors
Fee-Only Investment AdvisorsWayne Demeester
 
Stairs
StairsStairs
StairsRenny
 
Is there a business in rural markets
Is there a business in rural marketsIs there a business in rural markets
Is there a business in rural marketsSurinder Kumar
 
Faces 090402143234-phpapp02
Faces 090402143234-phpapp02Faces 090402143234-phpapp02
Faces 090402143234-phpapp02Jaing Lai
 
BannerAd Bomb.pdf
BannerAd Bomb.pdfBannerAd Bomb.pdf
BannerAd Bomb.pdfclare2373
 
anheuser-busch 2005AR_DomesticBeerOperations
anheuser-busch 2005AR_DomesticBeerOperationsanheuser-busch 2005AR_DomesticBeerOperations
anheuser-busch 2005AR_DomesticBeerOperationsfinance15
 
世界美景任遨遊113幅
世界美景任遨遊113幅世界美景任遨遊113幅
世界美景任遨遊113幅Jaing Lai
 
South Africa, Selected Images
South Africa, Selected ImagesSouth Africa, Selected Images
South Africa, Selected Imagesmelcioiu flori
 

Viewers also liked (20)

Come step back
Come step backCome step back
Come step back
 
History of Tower Butte
History of Tower ButteHistory of Tower Butte
History of Tower Butte
 
Digital Pentagon
Digital PentagonDigital Pentagon
Digital Pentagon
 
Payton_P3_Horses
Payton_P3_HorsesPayton_P3_Horses
Payton_P3_Horses
 
Lake And Mountain
Lake And MountainLake And Mountain
Lake And Mountain
 
Winter Worries
Winter WorriesWinter Worries
Winter Worries
 
Comparing the 401k to the 403b
Comparing the 401k to the 403bComparing the 401k to the 403b
Comparing the 401k to the 403b
 
Old style of life
Old style of lifeOld style of life
Old style of life
 
Winter idyll
Winter idyllWinter idyll
Winter idyll
 
Important trees
Important treesImportant trees
Important trees
 
Fee-Only Investment Advisors
Fee-Only Investment AdvisorsFee-Only Investment Advisors
Fee-Only Investment Advisors
 
Stairs
StairsStairs
Stairs
 
Monasteries
MonasteriesMonasteries
Monasteries
 
Is there a business in rural markets
Is there a business in rural marketsIs there a business in rural markets
Is there a business in rural markets
 
Faces 090402143234-phpapp02
Faces 090402143234-phpapp02Faces 090402143234-phpapp02
Faces 090402143234-phpapp02
 
BannerAd Bomb.pdf
BannerAd Bomb.pdfBannerAd Bomb.pdf
BannerAd Bomb.pdf
 
anheuser-busch 2005AR_DomesticBeerOperations
anheuser-busch 2005AR_DomesticBeerOperationsanheuser-busch 2005AR_DomesticBeerOperations
anheuser-busch 2005AR_DomesticBeerOperations
 
世界美景任遨遊113幅
世界美景任遨遊113幅世界美景任遨遊113幅
世界美景任遨遊113幅
 
Pure and beautiful
Pure and beautifulPure and beautiful
Pure and beautiful
 
South Africa, Selected Images
South Africa, Selected ImagesSouth Africa, Selected Images
South Africa, Selected Images
 

Similar to WSARA: Baselining Programs Early Compounds the Problems

Dubois Resume 2014
Dubois Resume 2014Dubois Resume 2014
Dubois Resume 2014Rick Dubois
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Glen Alleman
 
ipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfssuser52d5d3
 
Student guide for unit 9
Student guide for unit 9Student guide for unit 9
Student guide for unit 9Peter R Breach
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
Doe Oai Audit Report On Sg Program Jan 2012
Doe   Oai   Audit Report On Sg Program   Jan 2012Doe   Oai   Audit Report On Sg Program   Jan 2012
Doe Oai Audit Report On Sg Program Jan 2012John Chowdhury
 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7Michael Cary
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfiFieldsmart Technologies
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process Bob Prieto
 
Section 1 describe the process (steps) you would use in any organiz
Section 1 describe the process (steps) you would use in any organizSection 1 describe the process (steps) you would use in any organiz
Section 1 describe the process (steps) you would use in any organizSHIVA101531
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityAcumen
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDavid Greig
 
Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...Association for Project Management
 
Depository Trust & Clearing Corporation Shared Assessments Case Study
Depository Trust & Clearing Corporation Shared Assessments Case StudyDepository Trust & Clearing Corporation Shared Assessments Case Study
Depository Trust & Clearing Corporation Shared Assessments Case StudyKen Peterson
 

Similar to WSARA: Baselining Programs Early Compounds the Problems (20)

Dubois Resume 2014
Dubois Resume 2014Dubois Resume 2014
Dubois Resume 2014
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule Growth
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)
 
ipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdfipa_routemap_asset_management_module.pdf
ipa_routemap_asset_management_module.pdf
 
Student guide for unit 9
Student guide for unit 9Student guide for unit 9
Student guide for unit 9
 
Pmwg.110603
Pmwg.110603Pmwg.110603
Pmwg.110603
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Doe Oai Audit Report On Sg Program Jan 2012
Doe   Oai   Audit Report On Sg Program   Jan 2012Doe   Oai   Audit Report On Sg Program   Jan 2012
Doe Oai Audit Report On Sg Program Jan 2012
 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7
 
Maximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdfMaximizing Project Value with Construction Management Platforms..pdf
Maximizing Project Value with Construction Management Platforms..pdf
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
Section 1 describe the process (steps) you would use in any organiz
Section 1 describe the process (steps) you would use in any organizSection 1 describe the process (steps) you would use in any organiz
Section 1 describe the process (steps) you would use in any organiz
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme Errors
 
Symons
SymonsSymons
Symons
 
Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...Measures for assurance - Introduction and user group experience webinar, 29 A...
Measures for assurance - Introduction and user group experience webinar, 29 A...
 
Concurrence.PM.v2
Concurrence.PM.v2Concurrence.PM.v2
Concurrence.PM.v2
 
Depository Trust & Clearing Corporation Shared Assessments Case Study
Depository Trust & Clearing Corporation Shared Assessments Case StudyDepository Trust & Clearing Corporation Shared Assessments Case Study
Depository Trust & Clearing Corporation Shared Assessments Case Study
 

Recently uploaded

Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 

Recently uploaded (20)

Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 

WSARA: Baselining Programs Early Compounds the Problems

  • 1. WSARA: Baselining Programs Early Compounds the Problems Peter Modigliani C ongress unanimously approved the Weapon System Acquisition Reform Act in 2009 because if there’s one issue that everyone in Washington can agree on, it’s that defense acquisition needs additional reform. While enhanced discipline and rigor is required, the section of the law that attempted to control cost growth with additional organizations, processes, and requirements early in the acquisition life cycle will actually increase the costs and risks of many large programs.  Modigliani is an assistant vice president for program management at Alion supporting Air Force acquisition. He is a Project Management Profes- sional and Level III certified in program management. Defense AT&L: July-August 2010 12
  • 2. The biggest pitfall of WSARA is baselining major defense acquisition programs at Milestone A and driving Nunn- McCurdy breaches if programs exceed the initial cost and schedule estimates by 25 percent. At Milestone A, the effort We all want to develop major is still in the early concept stages. The users have developed an initial capabilities document to define the capability gap and have conducted an analysis of alternatives of proposed programs faster and cheaper, materiel solutions. The acquisition community developed a technology development strategy to reduce technology yet the bureaucracy risk and determine the appropriate set of technologies to integrate. The Milestone A estimates are developed years encumbers speed and agility. prior to having mature technologies demonstrated on repre- sentative prototypes, a preliminary design, or requirements solidified in a capability development document. While esti- mates are valuable at this stage, WSARA requires cost and schedule baselines prior to finalizing the scope.  based on inflated cost estimates, the scope and costs will   naturally grow to take advantage of the increased reserves In the past, if cost estimates increased by 25 percent, the to reduce risks or add capabilities.  program manager was required to notify the milestone deci-   sion authority, typically the Office of the Under Secretary of An Example Defense for Acquisition, Technology and Logistics, who then Let’s examine a program that, by all accounts, is a well- consulted with the Joint Requirements Oversight Council performing, high-demand program in the early stages of on requirements and determined if the program warranted the life cycle. It baselined costs and schedule at Milestone the resources required. In WSARA, Congress added new A and is maturing technologies via competitive prototypes schedule criteria, and now, exceeding cost or schedule es- and other early systems engineering efforts. The program timates by 25 percent drives a Nunn-McCurdy breach, in manager comes to the realization that some of the critical which the default plan would be to terminate the program. technologies will cost more or take longer to develop than If DoD wanted to continue with such a program, it would was originally planned two years ago based on initial as- need to re-accomplish the Milestone A and face additional sessments. There is full support from all key stakeholders oversight, reporting, and scrutiny. (combatant commanders, the Pentagon, and Capitol Hill) to proceed with this program, but it must now take a bu- The Fallout of WSARA reaucratic time out. Now, I will be the first to admit that DoD needs to get a tighter grip on scope and cost growth, and 25 percent cost The Joint Requirements Oversight Council will call for a se- growth on a major defense acquisition program is a signifi- ries of review boards to revalidate requirements. The Office cant amount, but let’s take a step back and look at what of the Secretary of Defense’s director of cost assessment WSARA truly does here. In the early stages of the acqui- and program evaluation will need to conduct an in-depth sition life cycle, you are still defining the scope based on cost estimate, which typically takes six months. The new initial requirements, technology maturity, funding, cost, and director of performance assessment and root cause analy- schedule estimates. WSARA requires baselining based on sis will need to conduct a root cause analysis, and it could the initial analysis, with severe consequences on breaching. take months to audit the program. This is all in addition to The fidelity of the cost and schedule estimates is low due to the analysis and reviews conducted by the users, program the significant amount of unknowns with the effort.  office, program executive office staff, and Service headquar-   ters staffs. Finally, the milestone decision authority will need To reduce the risk of a Nunn-McCurdy breach, program to conduct additional reviews and the staffs will compile a managers will now be motivated to inflate their cost and report to submit to Congress. While WSARA dictates that schedule estimates to account for all the unknowns and a report be sent to Congress within 30 days upon the pro- allow for more of a buffer. Yet presenting a higher cost es- gram manager notifying the milestone decision authority, timate likely exceeds the current program budget, thereby no one finds that to be a realistic timeframe. It is difficult to raising a full funding issue. If the cost estimates are too high, staff a simple one-page memo through the Pentagon within leadership may decide not to continue with an otherwise 30 days, let alone a major analysis determining the fate of valuable program. If the program does get approval, it will a major defense acquisition program. The program can likely require funds from other sources to ensure funding is either fail to meet the 30-day suspense to Congress and/ at an acceptable cost confidence level. While independent or the program manager delays formal milestone decision cost estimates may help keep the program manager honest, authority notification. Congressional staffers and members they will also be based on an undefined scope and ample un- will also likely call for meetings or hearings to discuss the knowns. Once a program manager has an approved program program further. 13 Defense AT&L: July-August 2010
  • 3. Avoiding termination, the program is now required to spend the next six months re-accomplishing its Milestone A be- fore it can resume technology development and prototyping. A Six-Pack of Tips for Both the Nunn-McCurdy process and re-accomplishing the previous milestone can easily delay the program a year or Defense AT&L Authors two, which increases costs and compounds risk. The Of- fice of the Secretary of Defense and the Service will need to rebalance funding profiles while government and industry will reallocate resources during the delays. This scenario was 1 all because the estimates done prior to fully understanding the program did not properly account for all the unknowns.  Look at back issues of the magazine. If we printed an article on a particu- Focusing on Milestone B lar topic a couple of issues ago, we're The DoD Acquisition Framework traditionally focused on unlikely to print another for a while—unless the acquisition program starting at Milestone B, following it offers brand new information or a different ample planning and analysis of requirements, technologies, point of view. 2 and costs as well as a sound acquisition strategy. The in- creased emphasis on early systems engineering, analysis We look on articles much more favor- of alternatives, and cost estimates helps leadership make a ably if they follow our author guide- sound decision at Milestone B on whether to grant approval lines on format, length, and presen- to begin development. At Milestone B, the milestone deci- tation. You'll find them at <http://www. sion authority approves the acquisition program baseline, dau.mil/pubs/pdf/DAT&L%20author%20 and the program manager must manage cost, schedule, and guidelines_080528.pdf> . 3 performance within those limitations. Baselining programs at Milestone A effectively forces planning and analysis to Number the pages in your manuscript be performed years sooner. It’s almost getting to the point and put your name on every page. It where once someone comes up with the need for a mate- makes our life so much easier if we riel solution, he had better have all the details known the happen to drop a stack of papers and your next day. If Congress reversed those aspects of WSARA, it article's among them. 4 would put the focus back on Milestone B, allowing for proper planning and still permitting the Office of the Secretary of Do avoid acronyms as far as pos- Defense and Joint Staff to conduct checks and balances if sible, but if you must use them, costs or schedules grow 25 percent higher than originally define them—every single one, estimated. It would allow for more realistic Milestone A cost however obvious you think it is. We get and schedule estimates and reduce overall program cost testy if we have to keep going to acronym and schedule risks. finder.com, especially when we discover 10   equally applicable possibilities for one ac- A Major Concern ronym. 5 At a recent conference, I raised this issue to a panel of cur- rent and former senior DoD acquisition executives, and Fax the Certification as a Work of they all agreed this was a major concern that will plague the U.S. Government form when the department for years. As the expanded defense acqui- you e-mail your article because we sition bureaucracy spends the next few years defining and can’t review your manuscript until we have implementing the new roles, policies, and processes, I hope the release. Download it at <http://www. they provide feedback to Congress on these unintended con- dau.mil/pubs/pdf/DAT&L%20author%20 sequences. The draft IMPROVE Act of 2010 on Capitol Hill guidelines_080528.pdf> Please don't make . these days does not address this early baselining issue, but us chase you down for it. And please fill it rather adds performance metrics. We all want to develop out completely, even if you've written for major programs faster and cheaper, yet the bureaucracy us before. 6 encumbers speed and agility. If we truly want to address cost growth, we need to develop innovative approaches to We'll acknowledge receipt of your streamline the bureaucracy, not expand it.  submission within three or four days and e-mail you a publication decision in four to five weeks. No need to remind us.   We really will. Scout’s honor. The author welcomes comments and questions and can be contacted at peter.modigliani@yahoo.com. Defense AT&L: July-August 2010 14