Managing projects by data
 

Managing projects by data

on

  • 1,198 views

After the course, student will:...

After the course, student will:
Understand Fsoft metric system.
Know about Fsoft PCBs and norms.
Be able to use data for managing projects.
Effort (Project, work product, process, type of activity): Weekly
Schedule (Start-date, expected end-date, actual end-date, delivery): At milestones
Defect (Project, work product, stage detected, QC activities, stage injected, process origin, severity, classification type, priority): Weekly
Size (Total, work product, activity): At milestones
Requirement (Total, size, status): Weekly
Customer complaints, customer satisfaction survey point, NC
Tools: Fsoft management suite (Timesheet, DMS, NCMS, Dashboard, Fsoft Insight)

Statistics

Views

Total Views
1,198
Views on SlideShare
1,196
Embed Views
2

Actions

Likes
0
Downloads
36
Comments
0

1 Embed 2

http://www.slashdocs.com 2

Accessibility

Categories

Upload Details

Uploaded via as Microsoft PowerPoint

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    Managing projects by data Managing projects by data Presentation Transcript

    • Managing projects by data Version: 3.0 Author: Le The Hung Sep 05, 2005 Instructor: Thai Nguyen © 2001 FPT-SOFT 04e-BM/NS/HDCV/FSOFT
    • Introduction
      • Course duration: 1 hour 45’
      • Purpose: Practical use of data for managing projects
      • Targeted attendees: Team leaders, SEPG, SQA, project managers
      • Tests/quiz: Quiz in 15’ for new attendants
    • Objectives
      • After the course, student will:
      • Understand Fsoft metric system.
      • Know about Fsoft PCBs and norms.
      • Be able to use data for managing projects.
      • Fsoft metric system – 45’
      • Fsoft PCBs and Norms – 45’
      • Quiz – 15’
      Table of contents
      • Why it’s needed?
      • Metric set
      • Analysis tools
      • Fsoft SLC in quantitative management
      Fsoft metric system
    • Why: Fsoft quality objective
        • “ FPT-SOFT is committed to deliver products that fully meet customer’s requirements on schedule defined in the project plan”
    • Why: International standards
      • ISO 9001:2000
        • 8.2.3 Monitoring and measurement of the processes
        • 8.4 Analysis of data
      • CMM/SEI 1.1:
        • PA.G1: The quantitative process management activities are planned
        • PA.G2: The process performance of the project's defined software process is controlled quantitatively
        • PA.G3: The process capability of the organization's standard software process is known in quantitative terms
    • Why: International standards
      • CMMI/SEI 1.1:
        • Measurement and Analysis
        • Quantitative project management
        • Organizational Process Performance
    • Why: Production improvements
    • Metric set: Collected data
      • Effort (Project, work product, process, type of activity): Weekly
      • Schedule (Start-date, expected end-date, actual end-date, delivery): At milestones
      • Defect (Project, work product, stage detected, QC activities, stage injected, process origin, severity, classification type, priority): Weekly
      • Size (Total, work product, activity): At milestones
      • Requirement (Total, size, status): Weekly
      • Customer complaints, customer satisfaction survey point, NC
      • Tools : Fsoft management suite (Timesheet, DMS, NCMS, Dashboard, Fsoft Insight)
    • Metric set: Calculated indicators
      • Effort (Effectiveness, deviation): Weekly
      • Schedule (Timeliness, deviation): At milestones
      • Defect (Defect rate, leakage): Weekly
      • Size (Deviation): At milestones
      • Requirement (Requirement Completeness): Weekly
      • Productivity, customer satisfaction, process compliance, distribution (Effort, defects): At the end of project
      • Status (Effort, Schedule, Defect): Weekly
      • Tools : Fsoft management suite (Timesheet, DMS, NCMS, Dashboard, Fsoft Insight)
    • Metric set: Work Flow
    • Fsoft SLC models: Manage by data
    • Initiation stage: Norms for WO
      • Overview
        • The Initiation stage is the start of the SLC, in which:
        • Project's software scope and boundary conditions, including the operational vision and proposed products, are established.
        • Overall cost and schedule of the project are estimated.
        • Potential risks are defined.
      • Metrics
        • Estimated size, estimated effort and planned schedule for the project.
        • Target value of the quality goals for the project: Timeliness, Requirement Completeness, Leakage, Correct Cost, Customer Satisfaction, Process Compliance, Response Time.
        • Actual data of the stage: Actual effort and actual schedule for the stage.
      • Help
        • Use Fsoft norms for overall estimating and setting goals.
        • Record in the WO, Estimation sheets, Fsoft Insight
    • Definition stage: PCB for Planning
      • Overview
        • Studying and clarifying user requirements.
        • Preparing and releasing SRS.
        • Negotiating Acceptance Criteria with customer.
        • Updating and releasing complete project plan.
      • Metrics
        • Estimated size for the project, estimated effort and planned schedule for the stage.
        • Progress values of the quality goals: Timeliness, Requirement Completeness, Correct Cost.
        • Actual data of the stage: Actual effort and actual schedule for the stage, actual size and defects of the project plan, URD and SRS.
      • Help
        • Use Fsoft norms for detail estimating and planning.
        • Fill data in the Fsoft Insight
        • Analyse by viewing the Charts/Status and log issue in the Issue table
    • Solution stage: Review metrics
      • Overview
        • The main purpose of this stage is to define an effective solution to meet customer requirements.
        • Analyzing and creating a good design for the software package are the main activities.
      • Metrics
        • Estimated effort and planned schedule for the stage.
        • Progress values of the quality goals : Timeliness, Completeness, Correct Cost, Process Compliance.
        • Actual data of the stage: Actual effort and actual schedule for the stage, actual size and defects of the ADD and Test Plan.
      • Help
        • Use Fsoft norms for re-estimating and re-planning.
        • Fill data in the Fsoft Insight
        • Analyse by viewing the Charts/Status and log issue in the Issue table
    • Construction stage: Data analysis
      • Overview
        • The goal of the construction stage is to develop the system.
        • Coding and testing for the software package are the main activities.
      • Metrics
        • Estimated effort and planned schedule for the stage.
        • Progress values of the quality goals : Timeliness, Completeness, Correct Cost, Process Compliance.
        • Actual data of the stage: Actual effort and actual schedule for the stage, actual size and defects of the DDD, Test case and Test Data, modules and unit programs.
      • Help
        • Use Fsoft norms for re-estimating and re-planning.
        • Fill data in the Fsoft Insight
        • Analyse by viewing the Charts/Status and log issue in the Issue table
    • Transition stage: Leakage
      • Overview
        • The focus of the Transition stage is to ensure that software is available for its end users. Delivering software to customer, implementing software systems on customer site and conducting test activities for acceptance are main activities of this stage.
      • Metrics
        • Estimated effort and planned schedule for the stage.
        • Progress values of the quality goals: Timeliness, Completeness, Leakage, Correct Cost, Process Compliance.
        • Actual data of the stage: Actual effort and actual schedule for the stage, actual size and defects of the software package.
      • Help
        • Use Fsoft norms for re-estimating and re-planning.
        • Fill data in the Fsoft Insight
        • Analyse by viewing the Charts/Status and log issue in the Issue table
    • Termination stage: Fsoft Data
      • Overview
        • The project closes at this stage when customer accepts the whole project and signs off the contract. Project assets must be collected and transferred to Fsoft process asset library.
        • The goal of this stage is to summarize the results of the project and to provide the project knowledge and experiences for other projects.
      • Metrics
        • Estimated effort and planned schedule for the stage.
        • Final values of the quality goals: Timeliness, Completeness, Leakage, Correct Cost, Customer Satisfaction, Process Compliance.
        • Actual data of the stage: Actual effort and actual schedule for the stage, customer satisfaction point.
      • Help
        • Compare Actual metrics with Fsoft norms and Project norms
        • Analyse in post mortem report
    • ETC: Estimated To Complete
      • Purpose
        • It helps to monitor project progress and predict complete project metrics.
      • Metrics
        • Effort ETC (= Effort spent/Actual requirement completeness - Effort spent) is used to forecast the effort needed to complete project.
        • Time ETC (= Current day + Actual duration/Actual requirement completeness – Actual duration) is used to forecast the finished day of the project.
        • Possible leakage (=Project size * Norm of weighted defect rate – Actual weighted defects found) is used to forecast the quality of deliverables.
      • Help
        • Change WO if the metric deviation >=30%
        • Re-plan if the metric deviation >=20%.
    • PPM: Process Performance Models
      • Purpose
        • A description of the relationship among attributes of a process and its work products that are developed from historical process performance data and calibrated using collected process and product measures from the project and that are used to predict results to be achieved by following a process.
      • Flow
      Select Measurement Parameters based on objective Collect Data Define Model Training Implementation of Model Collect Data Calibrate Model Select Process & Sub Process
    • PPM: Effort
      • Purpose
        • Effort PPM is used to forecast the effort needed for each process in each stage.
      • Metrics
        • Forecasted Engineering Effort (EE) = (1- Average (EE Deviation/Requirement Completeness (RCR) deviation)*Planned EE + Average(EE deviation/RCR deviation)*Planned EE/Planned RCR*Re-planned RCR.
        • Forecasted Management Effort = Planned ME/Planned EE*Re-planned EE
      • Help
        • In planning: The Fsoft norms + Project characteristics -> Planned values
        • At the end of each stage: Actual values of metrics + Change requests -> Issues + Forecasted -> Re-planned value of metrics
        • At the end of the project: Actual values of metric deviation -> Practices + Lessons.
    • PPM: Defect
      • Purpose
        • Defect PPM is used to forecast the defect to be moved by a QC activity in each stage.
        • Product Defect PPM is used to forecast the defect to be moved by a QC activity for each product.
      • Metrics
        • Project Replanned Defect Rate = Previous Project Planned Defect Rate * (1+ Average Project Defect found Deviation in previuos stages).
        • Product Replanned Defect Rate = Previous Product Planned Defect Rate * (1+ Average Defect found Deviation in released products).
      • Help
        • At the end of each stage for Project Defect.
        • After the releasing of each product for Product Defect.
    • Analysis tools: Cause-Effect
      • Purpose
        • It help to accurately identify causes (or results) of a problem.
      • Help
        • Brainstorming.
      Test Code Design Analysis SQA Technology Team Time Defect rate is high
    • Analysis tools: Pareto Chart
      • Purpose
        • It helps identify most important issues by data.
      • Help
        • The rule 80:20.
    • Analysis tools: Control Chart
      • Purpose
        • It helps to define and forecast uncontrolled cases.
      • Help
        • Average, Stdev, UCL, LCL of series of data
        • Color statuses of metrics (RED, YELLOW, BLUE)
      • Fsoft PCBs:
        • PCB: Process capability baseline
        • Based on data of post mortem projects and support activities
        • 1.0: June 30, 2001
        • Release Period: Quarterly, 6 months, Annually
        • Prepared by SEPG, reviewed and approved by BOM
      • Fsoft norms
        • Based on PCBs and Fsoft business goals
        • Established for 6 months
        • Suggested by SEPG, reviewed and approved by BOD
      Fsoft PCBs and Norms
      • All projects have postmortem in the reporting period
      • Methodology:
        • Average, Sigma, UCL, LCL
        • Causal analysis of out of control limits
        • Extraordinary cases are excluded
      • Summary:
        • The PCB of the period before the last period, the last PCB
        • Last norms, suggested norm
        • Improvement, issues
      Software PCB: Overview
      • Planned actions for last period
        • Collect customer related metrics
        • To use data effectively
      • Results of these actions
        • All mandatory software metrics are calculated
        • Metrics have been used for setting project norms
      • Issues in last period:
        • Schedule deviation is high
        • Review efficiency is low
      • Suggested actions for next period
        • Schedule estimation, customer communication, milestone control
        • Effort for review, review workshops, review guru
      Software PCB: Conclusions
    • Software PCB: Requirement
      • Accepted deliverable (%) 90|95| 94.4
      • Requirement completeness (%) 90|95| 93.83
      • Requirement stability (%) 7.5|5| 11.3
    • Software PCB: Schedule
      • Schedule control is the most serious problem
      • Timeliness (%) 84.9|95| 58.6
      • Project Schedule Deviation (%)
        • Development: 23.5|10| 62.5
        • Maintenance: 5|10| 30.6
      • Delivery Schedule Deviation (%)
        • Development: 13|10| 25.0
        • Maintenance: 5|10| 6.0
    • Software PCB: Effort
      • Effort Deviation (%)
        • Development: 29.8|10| 40.48
        • Maintenance: 4.9|10| 32.97
      • Project management effort (%)
        • Development: 4.5|7.5| 6.33
        • Maintenance: 3.8|7.5| 6.78
      • Quality Cost (%)
        • Development: 39|30| 34.49
        • Maintenance: 34.8|30| 47.66
      • Correction Cost (%)
        • Development: 16.3|12| 11.65
        • Maintenance: 18.4|12| 12.49
    • Software PCB: Quality
      • Review efficiency is too low
      • Defect Rate (WDef/UCP): 9.5|8.5| 9.0
      • Leakage (WDef/UCP) 0.5|0.3| 0.4
      • Defect Removal Efficiency (%)
        • Review 35|40| 36.4
        • Test 52|55| 57.9
      • Customer Satisfaction (Point) 80|85| 73.5
    • Software PCB: Productivity
      • Productivity (UCP/pd) 0.43|0.4| 0.53
      • Review Effectiveness (WDef/pd) 13.2|15| 16.1
      • Test Effectiveness (WDef/pd) 8.3|10| 12.4
    • Fsoft norms
      • For a period of 6 months
      • Improvement requirements based on last PCB
      • To use data effectively
        • Using PCB for plan: All processes
        • Re-estimate size: After SRS completion and at the end of the project
        • Analysis in progress: All milestones
        • Verification: SEPG
    • Fsoft norms
      • Requirement
        • Accepted deliverable: 95%
        • Requirement completeness: 95%
      • Schedule
        • Timeliness: 85%
        • Schedule Deviation: 10%
        • Delivery Schedule Deviation: 10%
      • Effort
        • Effort Deviation: 10%
        • Management Effort: 7.5%
        • Quality Cost: 30%
        • Correction Cost: 9%
    • Fsoft norms
      • Quality
        • Defect Rate: 7WDef/UCP
        • Leakage: 0.2WDef/UCP
        • Customer Satisfaction: 90 points
        • Process Compliance: 3NCs
      • Productivity
        • Coding: 0.5UCP/pd
        • Review: 15WDef/pd
        • Test: 12WDef/pd
    • S ources & references
      • S ources
        • Fsoft manual
        • Fsoft standard life cycle models and tailoring guidelines
        • Fsoft metric guidelines
        • Assessment and analysis tools guidelines
        • Project database and PPM templates
        • Fsoft process databases
        • Fsoft PCB reports
        • Fsoft norms
      • Recommended readings
        • TTVN/SYS/Fsoft QMS/document/master list
        • TTVN/SYS/ Fsoft QMS/Data/
        • TTVN/SYS/ Fsoft QMS/PCB&Norm/
    • Questions and Answers
    • Conclusion
      • Pls. give your assessment
    • Quiz
      • Total 100 points = 20 questions x 5 points/question
      • Duration: 15’
      • Pass criteria: 75 points
      • Feel free to use any available material
      • Don’t brainstorm.