Your SlideShare is downloading. ×
0
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
The Agile PMP v2
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

The Agile PMP v2

4,626

Published on

Published in: Technology, Business
1 Comment
18 Likes
Statistics
Notes
No Downloads
Views
Total Views
4,626
On Slideshare
0
From Embeds
0
Number of Embeds
4
Actions
Shares
0
Downloads
42
Comments
1
Likes
18
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. The Agile PMP
  • 2. Mike Cottmeyer mike.cottmeyer@versionone.com www.linkedin.com/in/cottmeyer www.versionone.com blog.versionone.net www.leadingagile.com
  • 3. The essence of Project Management? Cost Time Scope
  • 4. The essence of Project Management? Time Cost Scope
  • 5. The essence of Project Management? Cost Time Scope
  • 6. The essence of Project Management? Scope Cost Time
  • 7. The essence of Project Management? Risk
  • 8. Manage out Uncertainty
  • 9. So… what is Agile? Engineering Project Management Leadership
  • 10. So… what is Agile? Engineering Project Management Leadership
  • 11. So… what is Agile? Engineering Project Management Leadership
  • 12. So… what is Agile? Engineering ject Managem Leadership
  • 13. Manage for Uncertainty
  • 14. The Agile Manifesto 2001
  • 15. The Agile Manifesto 17
  • 16. The Agile Manifesto
  • 17. Individuals Processes The Agile Manifesto &Interactions &Tools Working Comprehensive Software Documentation Customer Contract Collaboration Negotiation Responding Following to Change a Plan
  • 18. The Agile Manifesto Individuals Processes &Interactions &Tools Working Comprehensive Software Documentation Customer Contract Collaboration Negotiation Responding Following to Change a Plan
  • 19. The Agile Manifesto Individuals Processes &Interactions &Tools Working Comprehensive Software Documentation Customer Contract Collaboration Negotiation Responding Following to Change a Plan
  • 20. The Agile Manifesto Individuals Processes &Interactions &Tools Working Comprehensive Software Documentation Customer Contract Collaboration Negotiation Responding Following to Change a Plan
  • 21. Processes The Agile Manifesto Individuals &Interactions &Tools Comprehensive Working Software Documentation Contract Customer Collaboration Negotiation Following Responding to Change a Plan
  • 22. Individuals The Agile Manifesto Processes &Interactions &Tools Working Comprehensive Software Documentation Customer Contract Collaboration Negotiation Responding Following to Change a Plan
  • 23. Traditional Managing the triple constraints…
  • 24. Scope Cost Time
  • 25. Scope Cost Time
  • 26. Scope Cost Time
  • 27. Scope Cost Time
  • 28. Scope Cost Time
  • 29. Scope Let’s figure out what to build…
  • 30. Cost …how much are we going to spend,
  • 31. Time and when we are going to be done.
  • 32. Who? What Order? When?
  • 33. Who? What Order? When?
  • 34. Who? What Order? When?
  • 35. Scope Chicken or the egg? Cost Time
  • 36. Scope Cost Time
  • 37. Scope Cost Time
  • 38. Scope Cost Time
  • 39. Scope Cost Time
  • 40. Scope Cost Time
  • 41. Analysis Design Build Test Deploy
  • 42. Analysis Design Build Test Deploy
  • 43. Analysis Design Build Test Deploy
  • 44. Analysis Design Build Test Deploy
  • 45. Analysis Design Build Test Deploy
  • 46. Analysis Design Build Test Deploy 18 months to release!
  • 47. Analysis Design Build Test Deploy 20,000 hours = $1,500,000
  • 48. Cost Time Scope
  • 49. Cost Time Scope
  • 50. Cost Time Scope
  • 51. Phase One Analysis Design Build Test Deploy Can we add more people?
  • 52. Phase One Analysis Design Build Test Deploy
  • 53. Phase One Analysis Design Build Test Deploy
  • 54. Phase One Analysis Design Build Test Deploy
  • 55. Phase One Analysis Design Build Test Deploy
  • 56. Phase One Analysis Design Build Test Deploy 15 months to release!
  • 57. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Can we deliver in phases?
  • 58. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy
  • 59. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Two 9 month deliveries!
  • 60. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Can we do it in parallel?
  • 61. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy
  • 62. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy
  • 63. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy
  • 64. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy
  • 65. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy First in 9 months…
  • 66. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Second a month or so later…
  • 67. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 68. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 69. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 70. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 71. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 72. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 73. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 74. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 75. Phase One Analysis Design Build Test Deploy Phase Two Analysis Design Build Test Deploy Phase Three Analysis Design Build Test Deploy
  • 76. Scope Cost Time
  • 77. Scope Cost Time
  • 78. Risk Risk Risk Scope Risk Cost Risk Time Risk Risk Risk Risk
  • 79. Scope is our starting place Cost Time
  • 80. Scope Cost Time
  • 81. Agile
  • 82. Scope Cost is our starting place Time is our starting place
  • 83. Scope Cost Time
  • 84. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9 Timeboxes...
  • 85. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 86. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 87. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9 Fixed duration
  • 88. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9 Fixed duration No overlap
  • 89. Team A Team B Team C Team D Team E Team F Teams…
  • 90. Team A Team B Team C Team D Team E Team F
  • 91. Team A Team B Team C Team D Team E Team F
  • 92. Team A Team B Team C Team D Team E Team F Teams deliver
  • 93. Team A Team B Team C Team D Team E Team F Teams deliver Working software
  • 94. Epic Epic Epic Epic Project Planning
  • 95. Feature Epic Feature Feature Epic Feature Feature Epic Feature Epic Project Release Planning Planning
  • 96. User Story Feature User Story User Story Epic Feature User Story Feature User Story User Story Epic Feature User Story Feature Epic Feature Epic Project Release Iteration Planning Planning Planning
  • 97. User Story Feature User Story User Story Epic Feature User Story Feature User Story User Story Epic Feature User Story Feature Epic Feature Epic 18-24 3-6 2-4 Months Months Weeks
  • 98. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 99. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 100. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 101. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 102. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 103. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 104. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 105. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 106. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 107. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9
  • 108. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9 End on time
  • 109. Project (years) Release (months) Release (months) Release (months) I1 I2 I3 I4 I5 I6 I7 I8 I9 End on time Inspect and Adapt
  • 110. Release One Iteration 1 Iteration 2 Iteration 3 Analysis Analysis Analysis Design Design Design Build Build Build Test Test Test Deploy Deploy Deploy
  • 111. Release One Iteration 1 Iteration 2 Iteration 3 Analysis Analysis Analysis Design Design Design Build Build Build Test Test Test Deploy Deploy Deploy
  • 112. Release One Iteration 1 Iteration 2 Iteration 3 Analysis Analysis Analysis Design Design Design Build Build Build Test Test Test Deploy Deploy Deploy
  • 113. Release One Iteration 1 Iteration 2 Iteration 3 Analysis Analysis Analysis Design Design Design Build Build Build Test Test Test Deploy Deploy Deploy
  • 114. Release One Iteration 1 Iteration 2 Iteration 3 Analysis Analysis Analysis Design Design Design Build Build Build Test Test Test Deploy Deploy Deploy Everyone on deck
  • 115. Release One Iteration 1 Iteration 2 Iteration 3 Analysis Analysis Analysis Design Design Design Build Build Build Test Test Test Deploy Deploy Deploy Everyone on deck Everyone accountable
  • 116. Release One Iteration 1 Iteration 2 Iteration 3 Team Team Team
  • 117. Release One Iteration 1 Iteration 2 Iteration 3 Team Team Team
  • 118. Release One Iteration 1 Iteration 2 Iteration 3 Team Team Team
  • 119. Release One Iteration 1 Iteration 2 Iteration 3 Team Team Team
  • 120. Release One Iteration 1 Iteration 2 Iteration 3 Team Team Team Cross-Functional
  • 121. Release One Iteration 1 Iteration 2 Iteration 3 Team Team Team Cross-Functional Specializing Generalists
  • 122. INVEST Test Automation Daily Builds Refactoring
  • 123. INVEST Test Automation Daily Builds Refactoring
  • 124. INVEST Test Automation Daily Builds Refactoring
  • 125. INVEST Test Automation Daily Builds Refactoring
  • 126. Fully functional Not fully capable Always working
  • 127. Fully functional Not fully capable Always working
  • 128. Fully functional Not fully capable Always working
  • 129. Burndown Graphs Project Burndown
  • 130. Burndown Graphs Release Burndown
  • 131. Burndown Graphs Iteration Burndown
  • 132. Earn value
  • 133. for Real
  • 134. Inspect and Adapt
  • 135. Minimize the Cost of Change
  • 136. The essence of Project Management? Cost Time Scope
  • 137. The essence of Project Management? Time Cost Scope
  • 138. The essence of Project Management? Cost Time Scope
  • 139. The essence of Project Management? Scope Cost Time
  • 140. The essence of Project Management? Risk
  • 141. Embrace Uncertainty
  • 142. Agile is risk mitigation
  • 143. Agile is a value system…
  • 144. Empowerment Self-Organization Trust Individuals Accountability
  • 145. Empowerment Self-Organization Trust Individuals Accountability
  • 146. Empowerment Self-Organization Trust Individuals Accountability
  • 147. Empowerment Self-Organization Trust Individuals Accountability
  • 148. PM
  • 149. A PM
  • 150. PMBOK
  • 151. Time Deliverables not activities Reduce Dependencies Prioritize don’t sequence Always finish on-time
  • 152. Time Deliverables not activities Reduce Dependencies Prioritize don’t sequence Always finish on-time
  • 153. Time Deliverables not activities Reduce Dependencies Prioritize don’t sequence Always finish on-time
  • 154. Time Deliverables not activities Reduce Dependencies Prioritize don’t sequence Always finish on-time
  • 155. Cost Cost = team size X duration Invest don’t spend
  • 156. Cost Cost = team size X duration Invest don’t spend
  • 157. Scope Plan scope in rolling waves Make trade-offs Allow room for negotiation Frequent customer interaction
  • 158. Scope Plan scope in rolling waves Make trade-offs Allow room for negotiation Frequent customer interaction
  • 159. Scope Plan scope in rolling waves Make trade-offs Allow room for negotiation Frequent customer interaction
  • 160. Scope Plan scope in rolling waves Make trade-offs Allow room for negotiation Frequent customer interaction
  • 161. Risk Business and Technical Risk management built in Continuous visibility
  • 162. Risk Business and Technical Risk management built in Continuous visibility
  • 163. Risk Business and Technical Risk management built in Continuous visibility
  • 164. Quality Quality not an afterthought Test driven development Continuous integration Continuous testing
  • 165. Quality Quality not an afterthought Test driven development Continuous integration Continuous testing
  • 166. Quality Quality not an afterthought Test driven development Continuous integration Continuous testing
  • 167. Quality Quality not an afterthought Test driven development Continuous integration Continuous testing
  • 168. Comm. Outside the team… the same Co-location Osmotic communication Information radiators
  • 169. Comm. Outside the team… the same Co-location Osmotic communication Information radiators
  • 170. Comm. Outside the team… the same Co-location Osmotic communication Information radiators
  • 171. Comm. Outside the team… the same Co-location Osmotic communication Information radiators
  • 172. Int. Charter or vision is okay Agile PM plan and approach Individual accountability Change control built in
  • 173. Int. Charter or vision is okay Agile PM plan and approach Individual accountability Change control built in
  • 174. Int. Charter or vision is okay Agile PM plan and approach Individual accountability Change control built in
  • 175. Int. Charter or vision is okay Agile PM plan and approach Individual accountability Change control built in
  • 176. Proc. Build contracts for change Build relationships on trust Create win-win agreements
  • 177. Proc. Build contracts for change Build relationships on trust Create win-win agreements
  • 178. Proc. Build contracts for change Build relationships on trust Create win-win agreements
  • 179. HR Motivated individuals Give them tools Remove impediments Self-organization
  • 180. HR Motivated individuals Give them tools Remove impediments Self-organization
  • 181. HR Motivated individuals Give them tools Remove impediments Self-organization
  • 182. HR Motivated individuals Give them tools Remove impediments Self-organization
  • 183. What can…
  • 184. I do…
  • 185. Now?
  • 186. Agile PM Plans Plan Features Iterative Planning Daily Stand-Up
  • 187. Agile PM Plans Plan Features Iterative Planning Daily Stand-Up
  • 188. Agile PM Plans Plan Features Iterative Planning Daily Stand-Up
  • 189. Agile PM Plans Plan Features Iterative Planning Daily Stand-Up
  • 190. Team PM PM Team Team Team Team APM Team Team APM Team
  • 191. Know where you are… know what’s left to go
  • 192. Take input from reality and deal with it
  • 193. AgilePMI finance.groups.yahoo.com /group/pmiagile/
  • 194. The Agile PMP
  • 195. Mike Cottmeyer mike.cottmeyer@versionone.com www.linkedin.com/in/cottmeyer www.versionone.com blog.versionone.net www.leadingagile.com

×