Pmp acronyms

  • 138 views
Uploaded on

 

More in: Business , Technology
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Be the first to comment
    Be the first to like this
No Downloads

Views

Total Views
138
On Slideshare
0
From Embeds
0
Number of Embeds
0

Actions

Shares
Downloads
14
Comments
0
Likes
0

Embeds 0

No embeds

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
    No notes for slide

Transcript

  • 1. AC  Actual Cost ACWP  Actual Cost of Work Performed AD  Activity Description ADM  Arrow Diagramming Method AE  Apportioned Effort AF  Actual Finish date AOA  Activity – On – Arrow AON  Activity – On – Node AS  Actual Start date BAC  Budget At Completion BCWP  Budgeted Cost of Work Performed BCWS  Budgeted Cost of Work Scheduled BOM  Bill Of Materials CA  Control Account CAP  Control Account Plan CCB  Change Control Board COQ  Cost Of Quality CPF  Cost‐Plus‐Fee CPFF  Cost‐Plus‐Fixed‐Fee CPI  Cost Performance Index CPIF  Cost‐Plus‐Incentive‐Fee CPM  Critical Path Method CPPC  Cost‐Plus‐Percentage of Cost CV  Cost Variance CWBS  Contract Work Breakdown Structure DD  Data Date DU  Duration DUR  Duration EAC  Estimate at Completion EF  Early Finish Date EMV  Expected Monetary Value 
  • 2. ES  Early Start Date ETC  Estimate to Complete EV  Earned Value EVM  Earned Valued Management EVT  Earned Valued Technique FF  Finish‐to‐Finish FF  Free Float FFP  Firm‐Fixed‐Price FMEA  Failure Mode and Effect Analysis FPIF  Fixed‐Price‐Incentive‐Fee FS  Finish‐to‐Start IFB  Invitation for Bid LF  Late Finish date LOE  Level of Effort LS  Late Start date OBS  Organizational Breakdown Structure OD  Original Duration PC  Percent Complete PCT  Percent Complete PDM  Precedence Diagramming Method PF  Planned Finish date PM  Project Management PM  Project Manager PMBOK Project Management Body Of Knowledge PMIS Project Management Information System PMO  Program Management Office PMO  Project Management Office PMP  Project Management Professional PS  Planned Start Date 
  • 3. PSWBS Project Summary Work Breakdown Structure PV  Planned Value QA  Quality Assurance QC  Quality Control RAM  Responsibility Assignment Matrix RBS  Resource Breakdown Structure RBS  Risk Breakdown Structure RD  Remaining Duration RFP  Request for Proposal RFQ  Request for Quotation SF  Scheduled Finish date SF  Start‐to‐Finish SOW  Statement of Work SPI  Scheduled Performance Index SS  Scheduled Start date SS  Start‐to‐Start SV  Schedule Variance SWAG  Sophisticated Wild Ass Guess SWOT Strenths, Weaknees, Oppurtunities, and Threads TC  Target Completion date TF  Target Finish date TF  Total Float T&M  Time and Material TQM  Total Quality Management TS  Target Start date VE  Value Engineering WBS  Work Breakdown Structure