Extracts from the City of Huntingburg's Stellar Grant application. This details the projects Huntingburg identified as priorities for the Stellar Communities Grant. It also includes details regarding the budgets and timelines of the projects.

Published in: News & Politics
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
1,230
On SlideShare
0
From Embeds
0
Number of Embeds
4
Actions
Shares
0
Downloads
16
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Huntingburg Stellar projects, budget and timeline

  1. 1. 231 231 64 64 7 8 4 4 5 6 2 2 2 9 1 1.1 9.3 9.1 9.2 1.3 1.2 3 1 1.1 1 1.1 2 3 2 4 5 6 3 4 5 6 7 8 9 St. Joseph’s Hospital Redevelopment Senior Living Apartments 1.2 Campus Redevelopment 1.3 Senior Citizens Center Heritage Trail Maintenance & Emergency Shelter Heritage Trail Community Gateways Maintenance & Emergency Shelter 9th Street Extension Community Gateways 14th Street Reconstruction 9th Street Extension 4th & Market Street Park 14th Street Reconstruction 4th Street Water Main Replacement 4th & Market Street Park Workforce Housing 4th Street Water Main Replacement 9.1 Multi-family Workforce Housing 9.2 Detached Workforce Housing Workforce Housing 9.3 Future Residential Development Stellar Impact Zone Boundary Legend Heritage Trail (existing or future phase) A City Like No Other Stellar N Stellar Impact Zone Boundary 0 500’ 1000’ 2000’ Project Target Area Map | Stellar Impact Zone Stellar Project Key 7 8 9 St. Joseph’s Hospital Redevelopment Senior Living Apartments 1.2 Campus Redevelopment 1.3 Senior Citizens Center 9.1 Multi-family Workforce Housing 9.2 Detached Workforce Housing 9.3 Future Residential Development Heritage Trail (existing or future phase) Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 1
  2. 2. Senior Center Complimentary Ready to Proceed Project 1.1 Senior Apartments 3 3 3 Developer has received tax credits from IHCDA Designs have been developed Project is scheduled to go to bid in Fall 2014 A City Like No Other Stellar 1 St. Joseph’s Hospital Redevelopment Project 1.1: Senior Living Apartments addition (ongoing) Heritage Trail Project 1.1: Renovated Senior Living Apartments (ongoing) Project 1.2: Redeveloped south wing with complimentary uses Heritage Trail connection west to Chestnut St. Project 1.3: Redeveloped Senior Citizens Center Site & landscape improvements Project 1.2: Redeveloped out-parcels with complimentary uses Medical Arts Dr. Leland Dr. 17th St. 20th St. Project 1.2: Redevelopment Community Partner owns proper ty City incentives are in place to attract investment Project 1.3: Senior Center Community Partner owns property Ready to select consultant for design 3 3 3 3 redevelopment Project Key Map Project 1.1: Senior Living Apartments ■■ The north and west wings of the main building will become independent living senior housing for residents 55 and over ■■ Over 30,000 square feet will be renovated into 25 one and two bedroom apartments ■■ A 27,000 square foot addition will be constructed on the north side to provide an additional 20 units Project 1.2: Campus Redevelopment ■■ The south end of the former hospital and adjacent buildings will be targeted to provide community health care Project 1.3: Senior Citizens Center ■■ An unused building will be repurposed, allowing expansion of services to a growing senior population ■■ The facility will be near the new senior apartments ■■ The facility would provide improved ADA access to senior programs ■■ Moving the Senior Center from the Old Town Hall will allow better use of this historic structure Project 1.2: Campus Redevelopment Stellar Activities Senior Housing Campus Total Cost State Funds Local Funds Private Funds Completion Date $8,999,004 $6,800,000 $200,000 $8,799,004 2017 Project 1.3: Senior Citizens Center Total Cost State Funds Local Funds Private Funds Completion Date $499,728 $449,728 $50,000 $0 2017 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 2
  3. 3. A City Like No Other Stellar 1 St. Joseph’s Hospital Redevelopment Project 1.3: Senior Citizens Center Project 1.1: New Senior Living Project 1.1: Renovated Senior Living Apartments (ongoing) Apartments Addition (ongoing) Project 1.2: Redeveloped south wing with complimentary uses Project 1.2: Redeveloped out-parcels with complimentary uses Senior Housing Campus Project 1.1: Senior Housing Elevation Huntingburg Senior Residence. [eplusaserver.local] Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 3
  4. 4. A City Like No Other Stellar Heritage Trail 231 231 64 Stellar Impact Zone Boundary 64 A B D C Connection to St. Joseph’s Hospital Redevelopment E F Charles C. Niehaus Memorial Park 4th St. 3rd St. Chestnut St. Chestnut St. Geiger St. Main St. Jackson St. Van Buren St. 5th St. 12th St. 19th St. Moekenhaus Dr. Styline Dr. 13th St. Downtown Underpass crossing below SR 64 Loop trail around Huntingburg Event Center Lake Connection to Huntingburg Event & Community Center Connection to workforce housing site Existing trail through Charles C. Niehaus Park See 4th Street Downtown Trail graphics Heritage Trail Master Plan 2 N Stellar Activities Ready to Proceed 3 3 3 Site control is in place Conceptual designs have been developed Ready to select consultant for design of Veterans Trail and Historic Downtown Trail portions of Heritage Trail Heritage Trail Heritage Tra il (not in Stellar application) The Heritage Trail will be developed in 3 phases. Veterans Trail ■■ Will utilize the Railroad Overpass to tie the St. Joseph Hospital Redevelopment and new residential areas to the Huntingburg Event and Community Center, Dubois County Veterans Monument, and the Charles C. Niehaus Memorial Park Historic Downtown Trail ■■ Will connect Charles C. Niehaus Memorial Park to the Historic Business District, the 4th & Market Street Park and east to Van Buren Street Railway Trail ■■ Will connect the Historic Business District to the Northeast neighborhoods, to the IGA, and to the Veterans Monument/ Event Center area. Most critical for this route is the pedestrian bridge necessary to cross the Dubois County Railroad The Heritage Trail will allow all quadrants of Huntingburg to be connected for the first time without having to cross an at grade railroad track Heritage Trail Total Cost State Funds Local Funds Private Funds Completion Date $8,195,507 $5,000,000 $2,315,507 $880,000 2018 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 4
  5. 5. A City Like No Other Stellar 2 Heritage Trail Heritage Trail 3.0 Trail wayfinding signage Trail-side tree plantings where appropriate Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 5 Bench located 10’ Trail, typ. approximately every 1/2 mile Trail Cross-Section A: Independent
  6. 6. A City Like No Other Stellar 2 Heritage Trail Heritage Trail 3.0 Heritage Trail 3.0 10’ Trail 5’ Min. parkway strip Trail wayfinding signage 10’ Trail Reconfigured parking lot 5’ Min. parkway strip Trail wayfinding signage Crash-worthy barrier 8’-0” Trail Trail Cross-Section B: Chestnut St. Heritage Trail 3.0 Heritage Trail 3.0 10’ Trail 5’ Min. parkway strip Trail wayfinding signage 10’ Trail Reconfigured parking lot 5’ Min. parkway strip Trail wayfinding signage Crash-worthy barrier 8’-0” Trail Trail Cross-Section C: 12th Street Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 6
  7. 7. A City Like No Other Stellar 2 Heritage Trail HERITAGE 3.0 Bench located 10’ Trail, typ. approximately every 1/2 mile 10’ Trail 5’ Min. parkway strip Trail wayfinding signage Heritage Trail 3.0 10’ Trail Reconfigured parking lot 5’ Min. parkway strip Trail wayfinding signage Crash-worthy barrier 8’-0” Trail 42” Pedestrian railing MSE abutment wall Trail Cross-Section D: Overpass Trail Cross-Section E: Urban Residential Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 7
  8. 8. A City Like No Other Stellar Heritage Trail 10’ Trail Flex space, 10’ Trail 10’ Travel Lane 10’ Travel Lane outdoor seating or parking Trail Cross-section: Downtown Street trees Decorative trail lighting with identity banners Flex space, outdoor seating or parking Trench drain, typ. Movable bollard or fencing 2 Typical Downtown Trail Plan Jackson Street Alley Main Street Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 8
  9. 9. A City Like No Other Stellar Heritage Trail Downtown Trail Perspective 2 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 9
  10. 10. A City Like No Other Stellar Heritage Trail Downtown Trail Perspective 2 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 10
  11. 11. A City Like No Other Stellar 3 Maintenance and Emergency Shelter Storage Yard Equipment Maintenance / Shelter Parking (+/- 37 Spaces) Parking lot landscaping Entry sign 12th Street Buffer Plantings Fleet Maintenance / Shelter Offices Fence Project Key Map Ready to Proceed Community Partner 3 3 3 owns property Conceptual designs have been developed Ready to select consultant Schematic Site Plan N Stellar Activities ■■ The facility will serve a dual purpose as a maintenance and operations facility for the city Street Department and emergency shelter in case of emergency for the community and local workforce ■■ Location near the overpass facilitates provides ease of access in case of emergency ■■ The facility would be approximately 17,000 square feet ■■ These areas would double as training facilities for local emergency management personnel and back-up control center for Dubois County EMA Maintenance and Emergency Shelter Total Cost State Funds Local Funds Private Funds Completion Date $1,997,998 $1,000,000 $997,998 $0 2018 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 11
  12. 12. A City Like No Other Stellar US 231 4 Community Gateways 14th Street Perennial median plantings Decorative median paving Perennial and evergreen foundation plantings Masonry gateway sign Ornamental tree backdrop Project Key Map US 231 Gateway Plan Spire element customized with name of appropriate landmark Ornamental tree backdrop Stone masonry sign Perennial and evergreen foundation planings Stellar Activities Ready to Proceed Gateway locations 3 3 3 have been identified Site control is in place Conceptual designs have been developed US 231 Gateway Elevation ■■ With the Railroad Overpass, new major intersections will be created ■■ This will create gateways at these intersections welcoming visitors and residents to Huntingburg ■■ An inviting and welcoming atmosphere will be created, with the theme to be used throughout the city and along the Heritage Trail ■■ The Gateways will guide visitors to the Heritage Trail, the Event and Community Center and the Veterans Monument Community Gateways Total Cost State Funds Local Funds Private Funds Completion Date $360,686 $0 $210,686 $150,000 2018 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 12
  13. 13. A City Like No Other Stellar Gateway pillar incorporated into headwall of trail underpass Decorative guardrail Decorative MSE wall Art / lighting on tunnel walls Enhanced slope plantings State Road 64 State Road 64 Ornamental Tree Perennial color Gateway pillar incorporated into underpass headwall Slope plantings Textured MSE retaining wall HUNTINGBURG 4 Community Gateways Rest node with bench & trash receptacle Trail underpass culvert Gateway pillar incorporated into headwall of underpass Trail wayfinding State Road 64 Gateway Plan State Road 64 Styline Dr. Trail wayfinding Gateway pillar incorporated into headwall of underpass N State Road 64 Gateway Treatment Gateway Pillar Detail Old City Hall Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 13
  14. 14. A City Like No Other Stellar 9th Street Extension Project Key Map 5 Completion Date $699,799 $0 $699,799 $0 2016 9th St. Private Funds Styline Dr. Moenkhaus Dr. 9th Street Extension Total Cost State OFS Brands Holdings, Inc. Potential development sites Touch of Class Stellar Activities Potential development site New road extension (approx. 1175’) Utility adjustments needed 9th Street Plan N OFS Headquarters Touch of Class Headquarters Ready to Proceed 3 3 3 Site control is in place Preliminary design has been completed Ready to issue RFP for project. ■■ Is a complimentary project to the Railroad Overpass project ■■ The extension provides a safe connection to the industrial property to the north and west of the Norfolk and Southern Railroad ■■ Is critical to the success of the overpass project by providing traffic flow into the industrial park while the overpass project is under construction ■■ Allows for the future expansion plans of OFS Brands and Touch of Class, two of our community partners Funds Local Funds Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 14
  15. 15. A City Like No Other Stellar 14th Street Reconstruction Project Key Map 6 Completion Date US 231 / Main St. US 231 / Main St. Geiger St. N. Chestnut St. Huntingburg Event & Community Center 3 3 14th Street Reconstruction Total Cost State Local Funds $1,851,143 $1,351,143 $500,000 $0 2017 Veterans Monument Private Funds Dairy Queen New Community Gateway, see Stellar Project 4 New median with left turn lanes to Main St. & N. Geiger St. Vacant property with development potential Ongoing overpass project Street tree, typ. Heritage Trail connection north Heritage Trail connection west via overpass project Street lighting, typ. New median with pedestrian crossing for Heritage Trail Heritage Trail connection north to St. Joseph’s Hospital Redevelopment Heritage Trail connection south along N. Geiger St. 14th Street Plan Stellar Activities N Ready to Proceed Site control is in place for the project Ready to issue RFP for project ■■ 14th Street Reconstruction provides a key pedestrian and vehicular connection to the Overpass Project and US 231 ■■ 14th Street needs to be upgraded to handle heavy truck traffic when the overpass project is complete ■■ This upgrade will enhance the use of Huntingburg Event and Community Center ■■ The Heritage Trail will connect the Event Center to the east side of Huntingburg and to the St. Joseph Hospital Redevelopment Project ■■ This will also enhance the ability to develop the available city-owned property on the south side of 14th Street as a hospitality corridor Huntingburg Event Center Veterans monument Funds Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 15
  16. 16. Restrooms / storage Gary Price “Circle of Peace” sculpture Amphitheater seating Bandshell Secondary bandshell oriented towards Farmers Market Service access to bandshell Sculpture Farmers Market area Project Key Map Park Site Plan 7 Overflow market area Existing fountain Geiger Street US 231 / Main Street 3rd Street 4th Street Access drive to shelter Shelter Egg lawn Screening Market pavilion Old Town Hall Patio Market pavilion N A City Like No Other Stellar 4th & Market Street Park Ready to Proceed Identified as a key element in the Downtown Revitalization Plan Conceptual Design has been completed 3 3 Stellar Activities ■■ Creates a space in the heart of downtown for events and activities that connects 4th Street to Market Street ■■ Improves Market Street and creates a community gathering point ■■ Enhances the use of Old Town Hall as a gathering and meeting space Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 16 4th & Market Street Park Total Cost State Funds Local Funds Private Funds Completion Date $1,535,402 $1,035,402 $500,000 $0 2018
  17. 17. A City Like No Other Stellar 4th & Market Street Park Event Space Perspective Farmer’s Market Perspective Gary Price sculpture Existing fountain 7 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 17
  18. 18. A City Like No Other Stellar 4th Street Water Main Replacement Project Key Map Schematic Cross-Section Sidewalk Parking Travel Lane Travel Lane Parking Sidewalk Existing water line abandon in place Approximate disturbance limits New water line (7’ depth) 8 2008 Water line leak 5th St. ■■ Replaces 120 year old water line ■■ Will improve fire protection and provide more reliable water source for the business district, securing the long-term viability of the Historic Downtown ■■ The enhanced infrastructure will promote renovation and improvements to vacant and under-utilized second story structures for use as downtown apartments 4th Street Water Main Replacement Total Cost State $826,010 $500,000 $326,010 $0 2017 4th St. 4th St. Ready to Proceed Site control is in place. Preliminary design completed as part of the Downtown Revitalization study Ready to issue RFP for project Funds Local Funds w w w w w Market St. 3rd St. Chestnut St. Walnut St. Geiger St. US 231 / Main St. Jackson St. Completion Date Van Buren St. Project Map N 3 3 3 Private Funds Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 18 Stellar Activities
  19. 19. A City Like No Other Stellar 9 Workforce Housing Project Key Map Multi-Family Preliminary Elevation Ready to Proceed 3 3 Options on the property have been secured Martin Commercial Group has completed a market study and developed preliminary site plans 3 Huntingburg Housing Authority has approved a resolution of support as a par tner in the development Stellar Activities The Workforce Housing will be developed in two phases: 1) Multi-Family and 2) Detached Homes ■■ Addresses the top priority in Dubois Strong’s Strategic plan to meet the need for workforce housing in Dubois County ■■ 75 rental units will be developed my Martin Commercial Group ■■ As many as 80 single-family detached workforce housing units will be developed by Boxer Girl LLC ■■ S&S Properties will develop an adjacent undeveloped site ■■ It is anticipated that the majority of the funds would come from LIHTC and HTC equity with some grants and a small first mortgage ■■ The housing would be affordable for a family making $10 to $15 per hour ■■ This translates to a $17.2 to $20.8 million in investment Workforce housing Project 9.2 Detached Workforce Housing Total Cost State Funds Local Funds Private Funds Completion Date $9,267,928 $0 $500,000 $8,767,928 2017 Huntingburg, Indiana | 2014 Stellar Communities Application 5 - 19 Project 9.1: Multi-Family Workforce Housing Total Cost State Funds Local Funds Private Funds Completion Date $6,523,229 $2,500,000 $550,000 $3,473,229 2017
  20. 20. A City Like No Other Stellar 9 Workforce Housing Project 9.3: Future residential development Project 9.2: Detached single family (80 units) Project 9.1: Phase II Multi-family (35 units) Landscape buffer Leasing office Project 9.1: Phase I Multi-family (40 units) Potential multi-family infill development Ongoing overpass project Chestnut St. 14th St. Preliminary Site Plan N Huntingburg, Indiana | 2014 Stellar Communities Application 5 -20
  21. 21. Huntingburg, Indiana | 2014 Stellar Communities Application 8 - 1 A City Like No Other Stellar Detailed Project Budgets City of Huntingburg, IN Budget & Leverage Matrix Project Stellar Activities Total Project Cost Private Investment Local Leverage Other Sources (foundations, etc.) Gap % of Local Leverage 1.2 St. Joseph Hospital Redevelopment Phase 2 $8,999,004 $8,799,004 $200,000 $0 $0 100% 1.3 St. Joseph Senior Center $499,728 $50,000 $449,728 10% 2 Heritage Trail - Phase 1 $8,195,507 $2,315,507 $880,000 $5,000,000 39% 3 Maintenance / Community Shelter $1,997,998 $997,998 $1,000,000 $0 100% 4 Community Gateways $360,686 $210,686 $150,000 $0 100% 5 9th Street Extension $699,799 $699,799 $0 100% 6 14th Street Reconstruction $1,851,143 $500,000 $1,351,143 27% 7 4th and Market Streets Park $1,535,402 $500,000 $1,035,402 33% 8 4th Street Water Main $826,010 $326,010 $500,000 39% 9.1 Workforce Housing - Multi - Family $6,523,229 $3,473,229 $500,000 $50,000 $2,500,000 62% 9.2 Workforce Housing - Detached Homes $9,267,928 $8,767,928 $500,000 $0 100% Complementary Projects Total Project Cost Private Investment Local Leverage Other Sources (foundations, etc.) US 231 ‐ Midstate Corridor $15,000,000 0% Heritage Trail $2,500,000 $500,000 $2,000,000 20% Affordable Housing $500,000 $500,000 100% Patoka Lake Water Line $500,000 $450,000 $50,000 90% Hotel Development $10,500,000 $10,000,000 $500,000 100%
  22. 22. Huntingburg, Indiana | 2014 Stellar Communities Application 8 - 2 A City Like No Other Stellar Detailed Project Budgets City of Huntingburg, Indiana Local Investment Detai City of Huntingburg, IN - Local Investment Detail Funding Source Available Funds 1.2 - St. Joseph Redevelopment Hospital Phase 2 1.3 - St. Joseph Senior Center 2 - Heritage Trail 2015-2019 3 - Maintenance / Community Shelter 4 - Community Gateways 5 - 9th Street Extension 6 - 14th Street Reconstruction 7 - 4th and Market Streets Park 8 - 4th Street Water Main 9.1 - Workforce Housing - Multi - Family 9.2 - Workforce Housing - Detached Homes Total Project Cost $8,999,004 $499,728 $8,195,507 $1,997,998 $360,686 $699,799 $1,851,143 $1,535,402 $826,010 $6,523,229 $9,267,928 $40,756,433 IHCDA - Section 42 Tax Credits $2,500,000 $2,500,000 $2,500,000 INDOT $6,351,143 $5,000,000 $1,351,143 $6,351,143 OCRA $1,485,130 $449,728 $1,035,402 $1,485,130 $10,336,273 Huntingburg Redevelopment Commission (TIF) $5,800,000 $200,000 $50,000 $1,815,507 $497,998 $210,686 $699,799 $500,000 $500,000 $326,010 $500,000 $500,000 $5,800,000 City of Huntingburg - Economic Development Fund (EDIT) $500,000 $500,000 $500,000 Dubois County Government $500,000 $500,000 $500,000 OFS $150,000 $150,000 $150,000 Greg and Carol Olinger $80,000 $80,000 $80,000 Old National Bank $75,000 $75,000 $75,000 Jasper Engines $50,000 $50,000 $50,000 Dubois County Community Foundation $50,000 $50,000 $50,000 United Minerals $20,000 $20,000 $20,000 Dunn & Associates $5,000 $5,000 $5,000 German American Bank $100,000 $100,000 $100,000 Dubois County Community Foundation - Campaign $650,000 $550,000 $550,000 USDA $500,000 $500,000 $500,000 FEMA $500,000 $500,000 $500,000 Homeland Security $500,000 $500,000 $500,000 Subtotal $9,480,000 $200,000 $50,000 $3,195,507 $1,997,998 $360,686 $699,799 $500,000 $500,000 $826,010 $550,000 $500,000 $9,380,000 Subtotal $200,000 $499,728 $8,195,507 $1,997,998 $360,686 $699,799 $1,851,143 $1,535,402 $826,010 $3,050,000 $500,000 Private Development $8,799,004 $3,473,229 $8,767,928 $21,040,161 Total Funds $9,480,000 $8,999,004 $499,728 $8,195,507 $1,997,998 $360,686 $699,799 $1,851,143 $1,535,402 $826,010 $6,523,229 $9,267,928
  23. 23. A City Like No Other Stellar Detailed Timeline & Benchmarks Project Huntingburg Stellar CommunitySchedule Stellar Projects 1.2 St. Joseph Hospital Redevelopment 1.3 Senior Center 2 Heritage Trail 3 Maintenance & Emergency Shelter 4 Community Gateways US 231 & 14th Street SR 64 7 Styline Drive 5 9th Street Extension 6 14th Street Reconstruction 7 4th and Market Streets Park 8 4th Street Waterline 9.1 Workforce Housing - For Rent 9.2 Workforce Housing - For Sale Preliminary Design and Cost Estimate Funding Applications and Contracts Environmental, Design and Bidding Construction City of Huntingburg, Indiana Detailed Timeline 2015-2019 2014 2015 2016 2017 2018 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Huntingburg, Indiana | 2014 Stellar Communities Application 9 - 1 City of Huntingburg, IN Detailed Timeline | 2015-2019

×