    Pmo Fuction Point And Req Impact Sample - Presentation Transcript

    1. Project Management Office Impact Measures Program Sample 1
    2. Agenda A d Which Measures Collected Sample Reporting Project L P j Level, Organizational L l O i i l Level l Perception versus Facts Trends By Year, MAP Impact, Preliminary Offshore Results Estimation Validation Example Next S Steps Planned l d Global productivity measures Consolidation and Automation in EPIC 2
    3. Impact Measures Activities I tM A ti iti 10 Project Impact M P j I Measures Projects Sample over 1,000 Effort Hours Sampling = 20% of BUNA CIO Group Spend excluding Infrastructure Reported after Implementation Also Available upon Request Project Estimation Validation Application Support Productivity – Support FTE per function installed 3
    4. Impact Measures Collected I tM C ll t d Impact Measure Calculation / Raw Data Estimating Accuracy - (actual labor hours - estimated) ÷ 1 Effort estimated Estimating Accuracy - (actual calendar months - 2 Schedule estimated) ÷ estimated * function points produced ÷ 3 Productivity FTE month * 4 Unit Cost project cost ÷ function points * 5 System Delivery Rate function points ÷ calendar months (requirements added, changed, deleted) ÷ 6 Requirements Volatility total requirements in design 7 Client Satisfaction ratings by client area defects found in system test ÷ 8 System Test Effectiveness total project defects defects found in the first 30 days * 9 Production Defect Density of production ÷ function points total development costs ÷ actual 10 Cost per Hour labor hours * Measures using functionality count 4
    5. Impact Measures Project Level Reporting October 30, 2006 5
    6. INDIVIDUAL Project Scorecard Sample – 1 print out Adobe Acrobat Document 6
    7. INDIVIDUAL Project Scorecard Sample 7
    8. Perceptions vs Fact October 30, 2006 8
    9. Print copy only – don’t present py y p Use actual printouts below Single release funded by 2 clients g y Overlapped some development / testing Similar results Different client perception ff Adobe Acrobat Adobe Acrobat Document Document October 30, 2006 9
    10. Individual Project Scorecard – Sample 2 10
    11. Individual Project Scorecard – Sample 3 11
    12. Perception vs Facts Here are Projects (>30,000 Hrs) BTM Back Office B k Offi Core Teller / BTM Front Office eCommerce 2005 C Fin’l Fusion Upgrade (OLB) HELOC Trade Based Accounting Wires Ph1 Wi Wires Ph 2 & 3 Which performed the “best”? 12
    13. Perception vs Fact – Hours? p Projects sorted by Size in Hours Hrs Est * Wires Ph 2 & 3 75K Trade Based Accounting 55k HELOC 41K 34K eCommerce 2005 38k 36K Core Teller / BTM Front Office 35k 27K BTM Back Office 30k Wires Ph1 28k Fin l Fin’l Fusion Upgrade (OLB) 27k * Binding estimate at the end of design 13
    14. Perception vs Fact – Functionality ? p y Projects sorted by Size in FPs Hrs FPs Wires Ph 2 & 3 75K 13536 eCommerce 2005 38K 7587 HELOC 41K 5680 Core Teller / BTM Front Office 35K 5224 Trade Based Accounting 55K 3124 Fin’l Fusion Upgrade (OLB) 27K 2112 BTM Back Office 30K 1212 Proportion of Size in Hours NOT proportional to Size in FPs P ti f Si i H ti l t Si i FP 14
    15. Perception vs Fact – Productivity? p y Productivity Projects sorted by Productivity Hrs Size-FP (FPs/FTE month) eCommerce 2005 C 38K 7587 FP FPs 29.0 29 0 Wires Ph 2 & 3 ** 75K 13536 26.1 Core Teller / BTM Front Office** 35K 5224 21.7 HELOC 41K 5680 20.3 20 3 Fin’l Fusion Upgrade (OLB) 27K 2112 11.3 Trade Based Accounting ** 55K 3124 8.3 BTM Back Office** 30K 1212 5.9 Wires Ph1** 28K 1114 5.7 Industry avg = 16 The Organizationavg = 23 - 34 y g g g ** New Dev or Vendor pkg -- Expect below avg productivity 15
    16. Organization Level Reporting October 30, 2006 16
    17. ORGANIZATIONAL TRENDS * Improved since 2002 • Estimates – +50% • Reqts Volatility – +60% • Production Defects - +40% 2008 • Cost per hour – +15% Global? X Decline since 2002 • Satisfaction – -22% 2005 MAP & Offshore PreMap Before 2006 – 7 2003 Transition ? 2003-04 Transition 17
    18. Executive S E ti Summary -- O Overall ll Print this report Adobe Acrobat Document 18
    19. Measurement Trends by Y M t T d b Year + + + Improved since 2002 • Estimates – > +50% • Reqts Volatility – >+70% + • Production Defects - +65% x • Cost C t per hour – +20% h x Decline since 2002 • Satisfaction – -16% + 19
    20. Process Impacts – Pre- vs Post-MAP + + + MAP improvements • Estimates – >+35% • Reqts – +55% •Production Defects - +30% • Cost per hour – +20% x x Declined with MAP • Satisfaction – -14% + + 20
    21. Offshore Impacts x + Improved Offshore: = • Cost per Hour -- -28% • System Delivery (1) -- +70% + x Declined Offshore (2) • Productivity -- -30% = Same • Unit Cost + Notes: (1) Lower ABN Delivery due to ABN Resource Limit working on multiple projects in a given calendar month (2) Lower Offshore productivity due Harvest staff turnover with each release 21
    22. Project E ti ti Validation P j t Estimation V lid ti Requirements and Design Documents were used to determine number of Function Points 3 Vendors and The Organizationcounted FPs from Software Requirements Spec Results: # FPs Bid $ / FP Vendor 1 1200 $ 685K $ 571 Vendor 2 * 520 $ 392K $ 754 x Vendor 3 540 $ 259K * $ 480 * ABN AMRO 585 22
    23. Global Productivity Measures Gl b l P d ti it M Productivity Global Project Only 2 BUs do Function Point (FP) counting – NL and NA BUNA on steering committee setting up FP counting practices worldwide Key performance metric in the Harvest Vendor contracts Selected Global Vendor for FP Counting Reduce cost by eliminating in-house FP y g consultant Piloting new vendor now Expect vendor to be ramped up by end of November No embe 23
    24. Plan to Embed Measures into Clarity Automate Data Collection in 2007 Add fields to Clarity Connection to requirements, testing, and deployment tools Automatic calculation of measures NTO Executive Management Reporting and Visibility Individual project measures Organizational rollups of measures Executive Reporting 24
    25. Appendix A di October 30, 2006 25
    26. Oct O t 2006 S Spend vs M d Measured d 26
    27. Executive Summary With Min/Max -- Appendix Adobe Acrobat Document 27

    + Chevy  MarchoskyChevy Marchosky, 6 months ago

    custom

    132 views, 0 favs, 0 embeds more stats

    My team produced many resports, this notes the impa more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 132
      • 132 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 0
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?