Your SlideShare is downloading. ×
0
23 03-2013
23 03-2013
23 03-2013
23 03-2013
23 03-2013
23 03-2013
23 03-2013
23 03-2013
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

23 03-2013

179

Published on

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
179
On Slideshare
0
From Embeds
0
Number of Embeds
2
Actions
Shares
0
Downloads
1
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. STATUS REPORT OF MY HOME ABHRA Tower-”A”As On 23.03.131.Basement-II Slab Completed.2. Basement-I slab flat no 1 & 2 completed reaming slab planning today3.Ground Floor slab Flat No 01 & 02 Shuttering Completed
  • 2. STATUS REPORT OF MY HOME ABHRA Tower-”B”As On 23.03.131.Basement-II Slab Completed.2.Basement-I Slab completed3.Ground floor slab flat no 1 & 2 completed4.First Floor flat no 01 & 02 Shuttering In Progress
  • 3. STATUS REPORT OF MY HOME ABHRA Tower-”C”As On 23.03.131.Basement II Slab Completed.2.Basement I flat no 01 Completed3.Basement I flat no 02 Beam Bottom Shuttering work in progress
  • 4. STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 23.03.131.Basement II Slab Completed.2.Basement I Slab Completed3.Ground Floor flat no 1 & 02 Shuttering Completed
  • 5. STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 23.03.131.Basement II Slab Completed2. Basement I slab for flat 1 &2 completed3.Remains Slab Beam Bottom Shuttering Work In Progress
  • 6. STATUS REPORT OF MY HOME ABHRA “CENTRAL LAWN”As On 23.03.131.Grade Slab- (Out Of 3-Parts) 1 Part Completed2.Sand Leveling Work in Progress
  • 7. STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 23.03.131.Total Site Basement II slab- Completed2.Total site Basement I Slab (Except Tower-C 1flat and Tower-E 3 Flats)-Remaining Completed3.Ground Floor slab Tower B 1&2 flats completed
  • 8. SWIMMING POOL

×