This document summarizes a presentation given by Nicola Bazzurro of IREN Italy at the 2nd AQUAKNIGHT Conference in Aqaba, Jordan on May 21, 2014. The presentation discussed IREN's pilot project in Genoa, Italy to reduce non-revenue water. Key actions taken included installing pressure sensors and valves, leak detection and repairs. Results included a reduction in losses from 15 liters/second to 8 liters/second and pressure stabilization. Automatic meter reading was also implemented to better monitor usage and identify leaks or theft. A water balance calculation for the pilot area showed non-revenue water was reduced from 33% to 15% through these interventions.
CCXG global forum, April 2024, Brian Motherway and Paolo Frankl
2nd AQUAKNIGHT Conference Pilot Project Results
1. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy1
Genoa Pilot Project
Nicola Bazzurro, IREN Acqua Gas S.p.A., Italy (IREN)
nicola.bazzurro@irenacquagas.it
2nd AQUAKNIGHT Conference
"Water Loss Management in the Mediterranean
Countries:
the AQUAKNIGHT Project Results“
21 May 2014, Aqaba, Jordan
2. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy2
Iren Group
IREN is a major Italian multi-utility
active in water, gas, energy and
waste disposal operating in the
provinces of Turin, Genoa, Parma,
Piacenza and Reggio Emilia in the
northern part of Italy.
Water systems in Reggio
Emilia province are
managed by Enìa Reggio
Emilia (a branch of IREN
Group)
Water systems in Liguria
region are managed by
Mediterranea delle Acque
(a branch of IREN Group)
3. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy3
Integrated water services
Since 2003 Iren Acqua Gas manages
integrated water services in the
province of Genoa including :
67 municipalities
about 880.000 inhabitants
Water Services in Genoa
Inhabitants served: 700,000
Distributed volumes: 100,000,000 mc.
Personnel: 480 employed
Turnover: 120,000,000 Euro
7. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy7
Network details and criticalities
Details:
Surface area 1,032 sq Km.
Network lenght 8,092 Km
Minimum ground level 35 m.
Maximum ground level 260 m.
Number of customers 6143
Population served 15300 inhab.
Materials grey cast iron 60%
ductil iron 30%
polyethylene 10%
Criticalities:
High Pressure, High level of leakage, High Burst frequency
8. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy8
Some implemented actions
Leamara: actions already implemented
• Installation of flow meter at inlet point,
pressure sensors at inlet, average and
critical points
• Real time monitoring system of pressure
and flow
• Installation of a PRV
• Leak detection and repair
Flow
Pressure
Installation of PRV and flow meter at inlet point, pressure sensors at inlet, average and critical points
9. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy9
Some achieved results
• Reduction of losses (MNF from 15 l/sec to 8 l/sec)
• Stabilisation of pressure
• Continuous control of pressure and flow
• Real time alarm in case of pressure/flow outside fixed range
• Reduction of rate of rise of unreported losses
• Extention of infrastructure life
14. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy14
Meters replacement
Multi-Jet Sealed Register Water Meter
STATIC PULSE EMITTER WITH
INTEGRAL MICROPROCESSOR
5-WIRE TECHNOLOGY
(BIDIRECTIONAL)
PULSE OPTIONS: 1-10 LITRES
15. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy15
Automatic meter reading
District
meter
1 meter +
pressure
6 meters
3 meters
6 meters
4 meters
6 meters
AKN1
AKN7
AKN3
AKN4
AKN2
AKN5
2 meters
AKN6
AMR architecture
16. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy16
AMR implementation
Training courses and first setup
Technical visit held last may the 8th
17. 2nd AQUAKNIGHT Conference,
21 May 2014, Aqaba, Jordan
N.Bazzurro, IREN Italy17
Upgrading works in the pilot area
UFR Installation
upstream (or
downstream) and
adiacent the old revenue
water meter including
relevant civil works
aimed at rationalise and
adequate the existing
manholes enabling AMR
implementation