B1 Fty Power Sys

Loading...

Flash Player 9 (or above) is needed to view presentations.
We have detected that you do not have it on your computer. To install it, go here.

0 comments

Post a comment

    Post a comment
    Embed Video
    Edit your comment Cancel

    Favorites, Groups & Events

    B1 Fty Power Sys - Presentation Transcript

    1. Section B: Bottling Up Plant Improvement Opportunities 2009 B1: Factory Power System Executive Summary This report lists the findings/observations of Walkthrough Survey, options generated for improvement and detailed explanation of suggestions. The options generated are based upon findings of a half day survey. As it was not a planned survey, no measurements could be organized. The data available at the plant was not adequate. Hence, most of the options do not contain a saving figure and payback. The options generated are well over 200 under 10 Madan Karki main headings. 9/2/2009
    2. Headwise Options Generated Section Heading No. of Options B1 Factory Power System 8 B2 Compressed Air System 35 B3 Boiler & Steam System 36 B4 Refrigeration System 38 B5 Cooling Towers 25 B6 Motors & Drive System 20 B7 Building & Premises 21 B8 Water Conservation 23 B9 Pumps, Pumping System & 9 WTP B10 Energy Management 11 B11 Process Equipments Total 226 Factory Power System Existing System • 2x500 kVA Kirlosker gensets have been just installed. Grid Power has been received through 11 kV grid via 800 kVA transformer. • A new changeover system has been installed with auto start & auto changeover system comprising electro-mechanically interlocked ACBs & motors for switch transfer. It is a conventional method. Observations The power is not seamless even after investment in new changeover system with a gap of at least 40 seconds, which will develop transients & spikes and cause crippling effect resulting into failure of electronic cards. Suggestions 1. Install bio-mass based Tri-Generation System thru gasifier route 2. Upgrade safety standard of DBs. Page 2 of 16
    3. 3. Improve Power Quality by installing Online UPS 4. Minimize the losses between Transformer & Main LT Panel by energy efficient cabling. 5. Check Transformer Efficiency 6. Maintain High Power Factor 7. Upgrade Earthing & Lightening Protection System to TNS System 8. Use LED lamps for all panel indication Page 3 of 16
    4. Factory Power System & Electricals 1. Install bio-mass based Tri-Generation System hrtu gasifier route. Cost saving Rs. 1.45 Lacs daily, 3 Crore annually. Payback 6 months. • Running Load - 600 kVA, Avg. load of chiller - 150 kVA, Plant pf - ?? • Daily Consumption: NEA Units – 10,000 kWh, Captive Generation – 4000 kWh • Furnace Oil Consumption in boiler – 1200 L • Daily energy cost – Rs. 1.75 Lacs Alternative to current arrangement, a biomass based tri-generation system through gasifier route is proposed here. The gasifier will gasify rice husk into combustible gas, which can be fed to an IC engine. The 650 kVA old genset lying at Bottler’s premise is ideal for this conversion. The exhaust gas from the genset will be into boiler. There will be some heat available from boiler exhaust also to be utilized for the application like dehumidification etc. A process flow chart with energy and mass balance is given here: Gasifier – converts biomass into 2100 kW combustible gas – 600 kg/hr of Electrical Power rice husk, heat generated 2100 IC 400 kW, 480 kVA kW Engine 1600 kW VAM Chiller, 800 Boiler - 1200 kW- 1800 kg/hr of steam kg/hr, 200 TR (1000 kg/hr to the plant, 800 kg/hr to VAM Chiller) Process 400 kW application in the plant (1000 kg/hr) Stack Loss from 200 kW 200 kW available for waste heat chimney 200 kW recovery application; e.g. 10% of total dehumidification of plant, Page 4 of 16
    5. The schematic arrangement of the equipment is given here: The space required is 15mx15m (225 m2). Page 5 of 16
    6. It shall be noted here that VAM chillers are available on direct fire type; i.e. the flue gas exhaust from the gas engine can be fed directly to the chiller without converting it into steam. In this arrangement, the losses will be much lesser. • Absorption cooling systems, like vapor compression systems, rely on a cycle of condensation and evaporation to produce cooling. • But, the absorption unit has an absorber and a generator to take low- pressure refrigerant vapor and make it into high-pressure vapor. • The absorption chiller does not use a compressor Gas Fired Absorption Chillers In this proposed scenario, only cost is the rice husk. With hourly consumption of 600 kg/hr, the daily consumption would be 14.4 Ton. Going by Biratnagar price (Rs. 1/ kg), the daily cost would be Rs. 14,400 against the existing cost of 1.75 Lacs. Since, an industry (Wai Wai) is already using rice husk within BID, their cost can be obtained for this evaluation. In my opinion, it may not be more than Rs. 2/kg, which means Rs. 29000 per day; i.e. a saving of Rs. 1.45 Lacs daily. Assuming an 8 month operation (200 days), the annual saving will be 3 Cr. The cost of investment will be 1.5 Cr including rice husk storage shed, which means a payback period of 6 month, & 200% ROI. Page 6 of 16
    7. The only risk in this scheme is the availability and price of fuel. It is to be noted here that except Rice Husk, following Biomass can be used in the Gasifiers as fuel:  Agricultural residues (straw/chaff of rice, wheat, mustard etc)  Energy crops (hybrid poplars, switch-grass, willows)  Wood residues (chunks, sawdust, pellets, chips) By using rural agro-waste as fuel, the unit can directly contribute to the rural economy & leverage it as a CSR (Corporate Social Responsibility) activity. Biomass is a carbon neutral fuel as plants remove Carbon Dioxide from the atmosphere & store it while they grow. Burning biomass will return this sequestered CO2 to the atmosphere. New plant will capture this CO2 & keep the atmosphere’s carbon cycle in balance. This net-zero carbon cycle can be repeated indefinitely, as long as biomass is re-grown in the next cycle. In contrast, fossil fuels are not carbon neutral because they release CO2 stored since millions of years & do not have any storage or sequestration capacity. It means “Biomass fuels contribute to Zero net production of greenhouse gases”. By switching over to biomass gasification system, the unit will reduce the emission of 1000 M Tons of CO2 annually to the atmosphere. Carbon Credits are available for these, which can be sold in the open market. Biomass has very Low sulfur content – which reduces acid rain. What is a gasifier? It is a conversion of solid fuel into a combustible gaseous fuel mixture called Producer Gas by partial combustion of biomass. The gasifier is essentially a chemical reactor, where the biomass fuel undergoes following physical & chemical processes to produce a gaseous fuel: Drying, Pyrolysis, Combustion & Oxidation. 2. Upgrade safety standard of DBs. Observations:  Earth-fault protection with ELCB/RCCB is not provided in the electrical circuits. Page 7 of 16
    8.  Color coding of the cables & wires not maintained in the DBs.  Proper termination of cabling not done. Cable Lugs & glands not used.  Ferrules are not provided for cable identification.  Numbering of switches & other components not done for identification & tracking.  Cable sizing inadequate. Fault current level not considered while selecting cable sizes.  The DBs shall be lockable, which is not the case. Page 8 of 16
    9. 3. Improve Power Quality by installing Online UPS – for seamless high quality power (free of transients, spikes & harmonics). It is recommended here to install a 400 kVA static (Inverter Rectifier combination) Online UPS with 68 nos. of (250 AH, 12V) Sealed maintenance free battery in two banks connected in parallel for improved equipment reliability due to reasons given below. Due to acute power shortage in the country, no. of power cuts have increased drastically causing failure of electronic control cards resulting into huge maintenance cost & machine downtime. Several industries use servo voltage stabilizer to get rid of voltage problem, but this equipment has more demerits than the benefit it can provide. First, servo voltage stabilizer has very high losses, i.e. in the range of 15%. Efficiency of a voltage stabilizer is around 85%. An Online UPS is will have the efficiency above 93%. Hence the efficiency gain will be by 8 point. For a 600 kVA average load for 24 hours a day & 200 days per annum with 0.8 as power factor, the energy saved per annum will be 230 MWh, which is 23 Lacs in terms of monitory value (weighted average price of NEA & Captive generation, Rs. 10/kWh). The voltage correction is done through a mechanical servomotor in a servo stabilizer, which takes some time. By the time it corrects, the voltage is changed already. Hence, in most of the stabilizers, the motor works continuously trying to achieve the setpoint, but it will never be able to achieve that. The proposed equipment will provide very good power quality with drastically reduced loss (at least 10 point higher than existing stabilizer) & seamless power supply on downstream irrespective of number of power cuts with nil machine downtime & nil card failures. Power Quality & Life of Electronic control cards – Voltage stabilizer can not reduce but actually increases transients, spikes and harmonics. Due to this, electronic control cards of machines are failing frequently. With the online UPS, the supply is first converted into DC and then back to AC again at the exactly desired parameter. In this process, all transients and spikes get filtered out and the downstream power will be of utmost quality. With this system, the power on downstream will be seamless, i.e. people on shopfloor will not know whether there was any power cut, because during the changeover period form grid supply to captive generation, the power will be supplied through the battery backup. Page 9 of 16
    10. Landed Cost of proposed system will be 50 Lacs and will require a 10’x10’ room. In this case the payback period will be around 1.5 years. Page 10 of 16
    11. 4. Minimize the losses between Transformer & Main LT Panel by energy efficient cabling. It is highly recommended to use energy efficient cabling system that will reduce energy consumption through lower copper losses and improve safety through better power quality at the same time. The location of the transformer room and main switch room should be immediately adjacent to, above or below each other. But, in the unit, they are situated at significant distance, which is a design fault. According to norms, the copper losses should not exceed 0.5% of the total active power transmitted along the circuit conductors at the rated circuit current. The design guideline for this can be found in the Code of Practice for Energy Efficient Electrical Installations. In case of the unit, we have two options. First, explore the possibility of shifting transformer near to main LT panel. If it is not possible, then add energy efficient additional cable length to the existing ones between Transformer and the main LT panel. 5. Check Transformer Efficiency  Check efficiency and sizing of step-down transformer. Older, underloaded, or overloaded transformers are often inefficient.  Use the optimum transformer taps. 6. Maintain High Power Factor Low power factor reduces the efficiency of the electrical distribution system both within and outside of your facility. Low power factor results when induction motors are operated at less than full load. Many utilities charge a penalty if power factor dips below 95%. Installing single capacitors or banks of capacitors either at the motor or the motor control centers addresses this problem. A. Group Compensation 2. Eliminates kVA surcharge 3. Increases service panel capacity B. Substation Compensation i. Eliminates kVA surcharge ii. Increases service panel capacity iii. Partial reduction in line losses iv. Partial increase in plant distribution capacity C. Individual Compensation i. Eliminates kVA surcharge ii. Increases service panel capacity iii. Maximizes reduction of line losses Page 11 of 16
    12. iv. Improves voltage unbalance between phases v. Increases life expectancy of motors vi. Adds flexibility for future expansion and changes Page 12 of 16
    13. 7. Upgrade Earthing System The earthing system of a building or site is a critical part of the electrical infrastructure and can determine the future viability of businesses operating in it. It is required to deal with short duration fault currents of several hundred Amperes, standing currents of a few Amperes and high frequency noise currents returning them to source or ground with close to zero voltage drop for noise currents and with no risk of damage for fault currents. At the same time, it must protect the equipment and personnel housed in the building during lightning strikes (fast transients in the kA region) in the interconnected earthing system. In traditional electrical engineering, separate earthing systems were used, for example, signal earth, computer earth, power earth, lightning earth etc. In today’s electrical engineering new insights have been gained on the aspect of earthing and grounding and its relation to instrument protection. The concept of separate earthing systems has been abandoned and the international standards now prescribe one overall earthing system. There is no such thing as ‘clean’ and ‘dirty’ earth. This single earthing concept means in practice that protective earth (PE) conductors, parallel earthing conductors, cabinets and the shields and screens of data or power cables are all interconnected. Also steel construction parts and water and gas pipes are part of this system. Ideally all cables entering a zone must enter at one point at which all screens and other earth conductors are connected. To reduce interference on equipment the earthing loops between cable- screens and other earthing structures must be kept small. Bonding cables against metal structures makes these structures act as parallel earthing conductors (PEC). Parallel earthing structures are used both for data and power cables. Examples are, in ascending order of effectiveness: earthing wires, cable ladders, flat metal surfaces, cable trays or ultimately metal pipes. The PEC reduces the impedance of the loop formed by the cable and the earthing network. The earthing resistance to mother earth is mostly not important for the protection of equipment. A very effective form of a PEC is a densely woven or completely closed cable screen with a large metal cross-section, connected all around at both ends of the cable. To keep the impedance of bonding connections in the earthing network small for high frequencies, litz wire (stranded, individually insulated) or metal strips with a length to width ratio smaller than 5 must be used. For frequencies higher than 10 MHz round wires should not be used. Page 13 of 16
    14. A raised floor can serve as a good equipotential plane. The copper grid underneath it must have a maximum spacing of 1.2 meters and be connected to the common bonding network via many equipotential bonding conductors. The grid should be connected to a 50 mm2 copper ring placed around the raised floor area, within the boundaries of the floor, at 6 metre intervals. Power and signal cables should be at least 20 cm apart and where they cross, they should do so at right angles. The design of the earthing system of a building, including the lightning protection system, requires great care if all the objectives are to be met. It is, as usual, best and cheapest if it is designed correctly from the start, considering the lifetime of the building and, as far as possible, the potential usage during that lifetime. Page 14 of 16
    15. 8. Use LED lamps for all panel indication. Incandescent lamps have been used as indicator lamps in electrical control panels, which consumes lot of power. It will be good idea to replace them with LED lamps. Light Emitting Diodes (LEDs) are made of an advanced semi-conductor material that emits visible light when current passes through it. Different conductor materials are used, each emitting a distinctive wavelength of light. LEDs come in red, amber, blue, green, and a cool white, and have limited applications at this time. LED lamps are the newest addition to the list of energy efficient light sources. While LED lamps emit visible light in a very narrow spectral band, they can produce "white light". This is accomplished with either a red-blue-green array or a phopshor-coated blue LED lamp. LED lamps last 40,000 to 100,000 hours depending on color. The current challenges of the LED source are a poor Color Rendering Index (CRI) of 65 or lower and poor efficacy, often less than 30 lumens per watt. LED lamps have made their way into numerous lighting applications including exit signs, traffic signals, under-cabinet lights, and various decorative applications. Though still in their infancy, LED lamp technologies are rapidly progressing and show promise for the future. LED light strips for under-cabinet lighting, for cove lighting, for shelf and cabinet interior lighting, and for edge lighting. LED Lamp advantages, disadvantages, and appropriate uses Advantages:  Impact resistant  Operate best at cooler temperatures so good for outdoor applications  Small size  Low to medium efficacy, depending on the color. Red is highest, followed by amber, green, white & blue. A more efficient white light can be created by combining red, green, and blue LEDs. White LEDs are currently about 30 lumens per watt, but efficacies are expected to increase steadily.  Monochromatic color for exit signs, signals, and special effects  Effective for rapid or frequent switching applications Disadvantages: Page 15 of 16
    16.  Rapid lumen depreciation: White LEDs may last 12,000 hours or longer, but “useful life” is only 6,000 hours, the point at which point light output has reduced 50%.  Monochromatic color  Heat buildup  Cost  White LEDs are still bluish & provide low lumens per watt, similar to incandescent. Both conditions are expected to improve rapidly over the next 15 years. Appropriate Uses:  Currently used primarily in exit signage, traffic signaling, and certain special effects  Excellent for projecting words or an image – as in walk/don’t walk signs or exit signs. FEMP recommends them for these uses.  LED sources may have the greatest potential for technical improvements and new applications in the next 15 years. Page 16 of 16
    SlideShare Zeitgeist 2009

    + Madan KarkiMadan Karki Nominate

    custom

    48 views, 0 favs, 0 embeds more stats

    Improvement opportunities in Factory Power System

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 48
      • 48 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 1
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories