Halifax Area School District
Halifax Area Middle / High School
February 27, 2014
Halifax Middle / High School

Project
Information

Financial
Information

Design
Concept
Project Schedule
Halifax Area Middle/High School

September 2012

•

BOE Approval PlanCon A/B

October 2012

•

Submission...
Scope of Project
Full Renovations

Building Improvement Items


HVAC Upgrades



Electrical & Lighting Upgrades



Plum...
Halifax Area Middle / High School
Halifax Area Middle / High School
Halifax Area Middle / High School
Halifax Area Middle / High School

152,000 SF
Halifax Area Middle / High School

163,000 SF
Halifax Middle / High School

Project
Information

Financial
Information

Design
Concept
Project Cost Breakdown
PlanCon Submission

11
Schematic Cost Estimate – 18 Year Bond

Millage Impact

Amount Financed

$18,500,000

Estimated Savings

0.00

Annual Savi...
A.C.E. Program Grant
Alternative and Clean Energy Grant Program
High Performance Building Design

• Announced July 10, 201...
LEED v3.0
GREEN BUILDING RATING SYSTEM
INDOOR ENVIRONMENTAL
QUALITY: DAYLIGHTING & VIEWS

Sustainable Sites………………… 24 poin...
LEED Checklist

16
Halifax Middle / High School

Project
Information

Financial
Information

Design
Concept
Building Organizational Diagram

18
Halifax Area Middle / High School

MIDDLE SCHOOL

SHARED
CENTRAL CORE

HIGH SCHOOL

ADMINISTRATION/
DAO
Halifax Area Middle / High School

MIDDLE SCHOOL
Halifax Area Middle / High School

HIGH SCHOOL
Halifax Area Middle / High School

SHARED
CORE
Halifax Area Middle / High School

ADMINISTRATION / DAO
24
25
26
HIGH SCHOOL ENTRY VESTIBULE
27
AUDITORIUM LOBBY
28
MEDIA CENTER
29
MEDIA CENTER
30
MEDIA CAFE
31
MEDIA CAFE
32
HIGH SCHOOL STUDENT COMMONS
33
MIDDLE SCHOOL STUDENT COMMONS
34
MIDDLE SCHOOL STUDENT COMMONS
35
36
Halifax Area Middle / High School

MIDDLE SCHOOL

SHARED
CENTRAL CORE

HIGH SCHOOL

ADMINISTRATION/
DAO
Halifax HS/MS Building Project
Upcoming SlideShare
Loading in...5
×

Halifax HS/MS Building Project

161,318

Published on

Published in: Education
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total Views
161,318
On Slideshare
0
From Embeds
0
Number of Embeds
17
Actions
Shares
0
Downloads
5
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide

Halifax HS/MS Building Project

  1. 1. Halifax Area School District Halifax Area Middle / High School February 27, 2014
  2. 2. Halifax Middle / High School Project Information Financial Information Design Concept
  3. 3. Project Schedule Halifax Area Middle/High School September 2012 • BOE Approval PlanCon A/B October 2012 • Submission to PlanCon (prior to November 2012 • PlanCon A/B PDE Review February – May 2013 • Schematic Design moratorium) June – November 2013 • Design Development July 2013 $1.5 Million awarded in ACE Grant • Dec. 2013 – April 2014 • Develop Construction Documents May - June 2014 • Bid Project / Award July 2014 • Begin Construction Project Completed December 2015 3
  4. 4. Scope of Project Full Renovations Building Improvement Items  HVAC Upgrades  Electrical & Lighting Upgrades  Plumbing Upgrades  Acoustical Ceilings  Exterior Door Replacement  Interior Door & Hardware Replacement  Building Code & Accessibility Upgrades  Upgrade Security Systems and Secure Entry  Technology Upgrades  Paving Repair & Drainage System Upgrades  Additional Site Circulation Upgrades  Refurbish Interior Finishes & Equipment 4
  5. 5. Halifax Area Middle / High School
  6. 6. Halifax Area Middle / High School
  7. 7. Halifax Area Middle / High School
  8. 8. Halifax Area Middle / High School 152,000 SF
  9. 9. Halifax Area Middle / High School 163,000 SF
  10. 10. Halifax Middle / High School Project Information Financial Information Design Concept
  11. 11. Project Cost Breakdown PlanCon Submission 11
  12. 12. Schematic Cost Estimate – 18 Year Bond Millage Impact Amount Financed $18,500,000 Estimated Savings 0.00 Annual Savings Energy Savings Water Savings Maintenance Savings $72,000 $8,000 $20,000 Total : Annually $100,000 -0.315 Site Alternates 1 - Driveway / Bus Drop-Off 6,000 SY $65.00 $400,000 2 - Practice Field (225' x 125') 35,525 SF $2.75 $100,000 Net Estimated Net Estimated Millage Impact Millage Impact 0.00 Mills 0.00 Mills 12
  13. 13. A.C.E. Program Grant Alternative and Clean Energy Grant Program High Performance Building Design • Announced July 10, 2013 Halifax Area Middle School / High School Amount Awarded $1,500,000 13
  14. 14. LEED v3.0 GREEN BUILDING RATING SYSTEM INDOOR ENVIRONMENTAL QUALITY: DAYLIGHTING & VIEWS Sustainable Sites………………… 24 points Water Efficiency………………….. 11 points Energy & Atmosphere……........... 33 points WATER EFFICIENCY: RAINWATER HARVESTING Materials & Resources…………... 13 points Indoor Environmental Quality….. 19 points Innovation in Design……………... up to 6 points SUSTAINABLE SITES: SUSTAINABLE SITES: GREEN ROOFS GREEN ROOFS Regional Priority Credits……….... up to 4 points TOTAL Achievable ENERGY & ATMOSPHERE: GEO-THERMAL ENERGY 110 points
  15. 15. LEED Checklist 16
  16. 16. Halifax Middle / High School Project Information Financial Information Design Concept
  17. 17. Building Organizational Diagram 18
  18. 18. Halifax Area Middle / High School MIDDLE SCHOOL SHARED CENTRAL CORE HIGH SCHOOL ADMINISTRATION/ DAO
  19. 19. Halifax Area Middle / High School MIDDLE SCHOOL
  20. 20. Halifax Area Middle / High School HIGH SCHOOL
  21. 21. Halifax Area Middle / High School SHARED CORE
  22. 22. Halifax Area Middle / High School ADMINISTRATION / DAO
  23. 23. 24
  24. 24. 25
  25. 25. 26
  26. 26. HIGH SCHOOL ENTRY VESTIBULE 27
  27. 27. AUDITORIUM LOBBY 28
  28. 28. MEDIA CENTER 29
  29. 29. MEDIA CENTER 30
  30. 30. MEDIA CAFE 31
  31. 31. MEDIA CAFE 32
  32. 32. HIGH SCHOOL STUDENT COMMONS 33
  33. 33. MIDDLE SCHOOL STUDENT COMMONS 34
  34. 34. MIDDLE SCHOOL STUDENT COMMONS 35
  35. 35. 36
  36. 36. Halifax Area Middle / High School MIDDLE SCHOOL SHARED CENTRAL CORE HIGH SCHOOL ADMINISTRATION/ DAO
  1. A particular slide catching your eye?

    Clipping is a handy way to collect important slides you want to go back to later.

×