• Save
04 project cost management
Upcoming SlideShare
Loading in...5
×
 

04 project cost management

on

  • 644 views

 

Statistics

Views

Total Views
644
Views on SlideShare
615
Embed Views
29

Actions

Likes
1
Downloads
0
Comments
0

1 Embed 29

http://www.progate.vn 29

Accessibility

Categories

Upload Details

Uploaded via as Adobe PDF

Usage Rights

© All Rights Reserved

Report content

Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
  • Full Name Full Name Comment goes here.
    Are you sure you want to
    Your message goes here
    Processing…
Post Comment
Edit your comment

    04 project cost management 04 project cost management Presentation Transcript

    • Session 4Project CostManagement
    • Agenda  Project Cost Management Overview  3 Processes  Estimate Costs  Determine Budget  Control CostsProject Cost Management 2
    • Goals  By the end of this session, you will be able to:  Have an overview of Project Cost Management;  Have a deep understanding of Inputs, T&Ts, and Outputs of the 3 processes in Project Cost Management;  Use EVM technique; Calculate PV, VE, AC, BAC, EAC, ETC, VAC, CV, SV, CPI, SPI, TCPI, etc.Project Cost Management 3
    • Copyright  Most of the material of this presentation has been taken from the PMBOK® Guide 4th Edition of PMI (Project Management Institute)  The material is for LARION Computing internal use only, NOT for reproduction or distribution.Project Cost Management 4
    • Progress  Project Cost Management Overview  3 Processes  Estimate Costs  Determine Budget  Control CostsProject Cost Management 5
    • Project Cost Management Overview  04 Project Cost Management Overview.pdfProject Cost Management 6
    • Progress  Project Cost Management Overview  3 Processes  Estimate Costs  Determine Budget  Control CostsProject Cost Management 7
    • 3 ProcessesProject Cost Management 8
    • Progress  Project Cost Management Overview  3 Processes  Estimate Costs  Determine Budget  Control CostsProject Cost Management 9
    • Estimate Costs (1 of 3)  Reserve analysis  Contingency reserves  Cost of quality  Cost of all of quality-related activities  Vendor bid analysis  Evaluating bids from external contractors and choose oneProject Cost Management 10
    • Estimate Costs (2 of 3)  Activity cost estimates  Direct & indirect costs???  Basis of estimates  Additional details supporting cost estimates  How cost estimate was derivedProject Cost Management 11
    • Estimate Costs (3 of 3)  Accuracy of estimates  Rough Order of Magnitude (ROM) estimate  +/- 50%  Budget estimate  -10% to +25%  Definitive estimate  +/- 10%Project Cost Management 12
    • Progress  Project Cost Management Overview  3 Processes  Estimate Costs  Determine Budget  Control CostsProject Cost Management 13
    • Determine Budget (1 of 4)  PProject Cost Management 14
    • Determine Budget (2 of 4)  Cost aggregation  Reserve analysis  Contingency reserves  Allowances for unplanned but potentially required changes  Related to risk  Management reserves  Budgets reserved for unplanned changes to project scope & cost  Not part of cost baseline  Not as part of EVM calculationsProject Cost Management 15
    • Determine Budget (3 of 4)  Historical relationships  Funding limit reconciliationProject Cost Management 16
    • Determine Budget (4 of 4)  Cost performance baseline & Project funding requirementsProject Cost Management 17
    • Progress  Project Cost Management Overview  3 Processes  Estimate Costs  Determine Budget  Control CostsProject Cost Management 18
    • Control Costs (1 of 14)  Earned Value Management  To measure project performance against the scope, schedule and cost baselines  The combination of scope, schedule and cost baselines is called performance measurement baselineProject Cost Management 19
    • Control Costs (2 of 14)  Earned Value Management (cont.)  PV, EV, ACProject Cost Management 20
    • Control Costs (3 of 14)  Earned Value Management (cont.)  Planned Value (PV)  The authorized budget assigned to the work to be accomplished for an activity or a WBS component  BCWS, Budgeted Cost of Work Scheduled, is another name of PV  Earned Value (EV)  The value of work performed (in term of approved budget)  BCWP, Budgeted Cost of Work Performed, is another name of EV  EV = BAC * % of physical progress  Actual Cost (AC)  The total cost actually incurred & recorded in accomplishing work performed  ACWP, Actual Cost of Work Performed, is another name of ACProject Cost Management 21
    • Control Costs (4 of 14)  Earned Value Management (cont.)  Variances from approved baselines  Schedule Variance (SV)  A measure of schedule performance on a project  SV = EV – PV  SV < 0 → behind schedule; >0 → ahead of schedule  Cost Variance (CV)  A measure of schedule performance on a project  CV = EV – AC  CV < 0 → over budget; >0 → under budgetProject Cost Management 22
    • Control Costs (5 of 14)  Earned Value Management (cont.)  Schedule Performance Index (SPI)  A measure of progress achieved compared to progress planned on a project  SPI = EV / PV  SPI < 1 → behind schedule; >1 → ahead of shcedule  Cost Performance Index (CPI)  A measure of the value of work completed compared to the actual cost or progress made on a project  CPI = EV / AC  CPI < 1 → over budget; >1 → under budgetProject Cost Management 23
    • Control Costs (6 of 14)  Earned Value Management (cont.)  Example: Over budget and behind scheduleProject Cost Management 24
    • Control Costs (7 of 14)  Earned Value Management (cont.)  Tips  If it is a variance: the formula is EV minus something  If it is an index: it is EV divided by something  If the formula relates to schedule: use PV  If the formula relates to cost: use ACProject Cost Management 25
    • Control Costs (8 of 14)  Earned Value Management (cont.)  Budget At Completion (BAC)  How much did we budget for the total project effort?Project Cost Management 26
    • Control Costs (9 of 14)  Forecasting  Estimate At Completion (EAC)  What do we currently expect the total project to cost?  Estimate To Complete (ETC)  How much more do we expect it to cost to finish the project?  Variance At Completion (VAC)  How much over or under budget do we expect to be at the end of the project?Project Cost Management 27
    • Control Costs (10 of 14)  Forecasting (cont.)  Estimate At Completion (EAC)  Initial estimates are flawed → re-estimate  EAC = AC + bottom-up ETC  Continue at the same rate of spending  EAC = BAC / CPI  Current variances are thought to be atypical of the future  EAC = AC + (BAC-EV)  Current variances are thought to be typical of the future  EAC = AC + (BAC-EV)/(CPI*SPI)Project Cost Management 28
    • Control Costs (11 of 14)  Forecasting (cont.)  Estimate To Complete (ETC)  ETC = EAC – AC  ETC = re-estimate  Variance At Completion (VAC)  VAC = BAC - EACProject Cost Management 29
    • Control Costs (12 of 14)  To Complete Performance Index (TCPI)  In order to stay within budget, what rate must we meet for the remaining work? (divides the work remaining to do by the money remaining to do it)  TCPI = (BAC-EV) / (BAC-AC)Project Cost Management 30
    • Control Costs (13 of 14)  EVM Exercise  04 Exercise 01.pdf, calculate:  PV, EV, AC  BAC  CV, CPI  SV, SPI  EAC, ETC, BAC  04 Exercise 02.pdfProject Cost Management 31
    • Control Costs (14 of 14)  Performance Reviews  Variance Analysis  Work performance measurements  Budget forecastsProject Cost Management 32
    • Recap  Project Cost Management  3 processesProject Cost Management 33
    • Questions?Project Cost Management 34
    • Thank you!Project Cost Management 35