Legacy Lawsuit School        R.S. 30:29         ACT 312
Oil and Gas Operations The last operator of record is responsible for bringing the location into compliance with state sta...
Operations Cont...Only the current operator of record has aright to access the site without the consentof the landownerThe...
Why RECAP or 29-BRECAP is the standard used by DEQ forhazardous wasteThere are instances when RECAP is a betterstandard to...
Why RECAP or 29-BEXAMPLE  29B has limits on salt concentrations in soil that are based on  agriculture standards and are n...
SERPIn 2010 the Office of Conservationintroduced SERP as an alternative to 29-BSERP was largely based off the RECAPprogram ...
Landowner          Courses of ActionLandowner has 3 different courses of action if they feel there land iscontaminated   C...
DNR Report on LegacyHCR 167 by Rep. Karen St. Germain   Directed DNR to report on Legacy LawsuitsExcerpts   271 Lawsuits  ...
DNR Report Cont...Issues Impacting Evaluation or Remediation Timelines1.   Allowing all parties access to the property for...
Where are the suits
Problems with ACT 312Courts have interpreted the ACT 312 processincorrectly and inconsistently  Many Courts awarding damag...
What we would like to fix in ACT 312Timelines and Schedules   This would establish timeframes for each step to happen holdi...
Timelines and Schedules   This would establish timeframes for each step to happen holding   everyone accountableDelay  Can...
Delay  Cannot move to trial on the merits until DNR submits planJury Instructions  Juries are not being told what the ACT ...
Jury Instructions  Juries are not being told what the ACT 312 process isAccess  Landowner cannot deny defendant access to ...
Access  Landowner cannot deny defendant access to evaluate if notice is givenAdmission of Liability  Allow the admission t...
Admission of Liability  Allow the admission to be limited to regulatory damages
Admission of Liability  Allow the admission to be limited to regulatory damages
What are we proposing to fixAdmission of Liability  Allow the admission to be limited to regulatory damages
Why can’t a compromise be reachedWhat we want that they will not agree to?  DNR public hearing to develop plan (which is  ...
Why can’t a compromise be reachedWhat are they saying is wrong with what we want  Costs - This will be an unfair burden on...
How ACT 312 was intended to work   Responsible Party                  Regulatory                   “Other” Damages    Dete...
THE PROCESS  LANDOWNER FILES LAWSUIT      FORCONTAMINATION
THE PROCESS  LANDOWNER FILES LAWSUIT      FORCONTAMINATION
THE PROCESS  LANDOWNER       NOTIFICATION FILES LAWSUIT    THAT SUIT HAS      FOR         BEEN FILED ISCONTAMINATION      ...
THE PROCESS                                       OPERATORS                                        ADMITS                 ...
THE PROCESS                                       OPERATORS       R.S. 30:29 C(1)                                        A...
THE PROCESS                                       OPERATORS       R.S. 30:29 C(1)                                        A...
THE PROCESS                                       OPERATORS       R.S. 30:29 C(1)                                        A...
THE PROCESS                                       OPERATORS                         R.S. 30:29 C(1)                       ...
THE PROCESS                                                    OPERATORS                         R.S. 30:29 C(1)          ...
THE PROCESS                                                    OPERATORS                         R.S. 30:29 C(1)          ...
THE PROCESS                                                        OPERATORS                         R.S. 30:29 C(1)      ...
THE PROCESS                                                        OPERATORS                         R.S. 30:29 C(1)      ...
THE PROCESS                                                          OPERATORS                         R.S. 30:29 C(1)    ...
THE PROCESS                                                          OPERATORS                         R.S. 30:29 C(1)    ...
THE PROCESS                                                          OPERATORS                         R.S. 30:29 C(1)    ...
THE PROCESS                                                          OPERATORS                         R.S. 30:29 C(1)    ...
Reality  LANDOWNER FILES LAWSUIT      FORCONTAMINATION
Reality  LANDOWNER FILES LAWSUIT      FORCONTAMINATION
Reality  LANDOWNER       NOTIFICATION FILES LAWSUIT    THAT SUIT HAS      FOR         BEEN FILED ISCONTAMINATION      SENT...
Reality                                      LANDOWNER                                     SETTLES SUIT                   ...
Reality                                      LANDOWNER                                     SETTLES SUIT                   ...
Reality                                      LANDOWNER                                     SETTLES SUIT                   ...
Reality                                      LANDOWNER                                     SETTLES SUIT                   ...
Reality                                      LANDOWNER                                     SETTLES SUIT                   ...
Reality                                         LANDOWNER                                        SETTLES SUIT             ...
Reality                                         LANDOWNER                                        SETTLES SUIT             ...
Reality                                             LANDOWNER                                            SETTLES SUIT     ...
Reality                                             LANDOWNER                                            SETTLES SUIT     ...
Reality                                              LANDOWNER                                             SETTLES SUIT   ...
Reality                                              LANDOWNER                                             SETTLES SUIT   ...
Reality                                              LANDOWNER                                             SETTLES SUIT   ...
Proposed Solution to ACT 312                              Regulatory                   “Other” Damages                    ...
The Solution  LANDOWNER FILES LAWSUIT      FORCONTAMINATION
The Solution  LANDOWNER FILES LAWSUIT      FORCONTAMINATION
The Solution  LANDOWNER       NOTIFICATION FILES LAWSUIT    THAT SUIT HAS      FOR         BEEN FILED ISCONTAMINATION     ...
The Solution  LANDOWNER       NOTIFICATION FILES LAWSUIT    THAT SUIT HAS       OPERATORS      FOR         BEEN FILED IS  ...
R.S. 30:29.2The Solution                           Defendant                                   limits admission           ...
R.S. 30:29.2The Solution                           Defendant                                   limits admission           ...
R.S. 30:29.2The Solution                           Defendant                                   limits admission           ...
R.S. 30:29.2The Solution                           Defendant                                   limits admission           ...
R.S. 30:29.2The Solution                           Defendant                                   limits admission           ...
R.S. 30:29.2The Solution                                        Defendant                                                l...
R.S. 30:29.2The Solution                                        Defendant                                                l...
R.S. 30:29.2The Solution                                            Defendant                                             ...
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Legacy School
Upcoming SlideShare
Loading in …5
×

Legacy School

707 views
664 views

Published on

Published in: News & Politics
0 Comments
1 Like
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
707
On SlideShare
0
From Embeds
0
Number of Embeds
280
Actions
Shares
0
Downloads
1
Comments
0
Likes
1
Embeds 0
No embeds

No notes for slide
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • \n
  • Legacy School

    1. 1. Legacy Lawsuit School R.S. 30:29 ACT 312
    2. 2. Oil and Gas Operations The last operator of record is responsible for bringing the location into compliance with state standards - 29-B (regulatory damages) LSA R.S. 30:82(9) The last operator is also responsible for full-filling any contractual obligation that he has to the landowner (private claims)
    3. 3. Operations Cont...Only the current operator of record has aright to access the site without the consentof the landownerThe standard by which the operatorremediates is 29-BThe operator may use the standards that arein place at DEQ / EPA called RECAPRECAP may only be used with landownerconsentOutside of lawsuits, consent to use RECAP isnormally easily attainable
    4. 4. Why RECAP or 29-BRECAP is the standard used by DEQ forhazardous wasteThere are instances when RECAP is a betterstandard to apply for the environmentEXAMPLE 29B has a limit on oil and grease concentration in soil 29B does not have any limits on individual hydrocarbon fractions (the individual carbon chains that make up hydrocarbons) like benzene A site could therefore pass 29B standards for oil and grease (and require no remediation) but fail the standards for benzene under RECAP
    5. 5. Why RECAP or 29-BEXAMPLE 29B has limits on salt concentrations in soil that are based on agriculture standards and are not health risk based A given salt concentration could exceed 29B but have no risk to human health If the location has no present or future utility as farmland, RECAP would suggest that the most environmentally responsible course of action is to leave the salt in place To dig and haul the salt impacted soil would cause a negative impact by taking up limited space at a disposal facility when the salt in place has no health risk If land has utility as farmland, treatment of the salt in place is the environmentally preferred course of action.
    6. 6. SERPIn 2010 the Office of Conservationintroduced SERP as an alternative to 29-BSERP was largely based off the RECAPprogram at DEQ / EPASERP never became law as it was pulled thenight before it went into the register forunknown reasons
    7. 7. Landowner Courses of ActionLandowner has 3 different courses of action if they feel there land iscontaminated Contact the current operator of record and ask them to remediate (bills filed by T.Burns and Cortez would make this mandatory) File an environmental complaint with the Department of Natural Resources / Office of Conservation - which may result in compliance order 7 of these filed in 2011 2 required no action by operator 1 operator and landowner were directed to meet and resolved the issues 4 resulted in one or more compliance orders for evaluation and/or remediation which are currently being carried out File a lawsuit under ACT 312
    8. 8. DNR Report on LegacyHCR 167 by Rep. Karen St. Germain Directed DNR to report on Legacy LawsuitsExcerpts 271 Lawsuits 210 with no environmental data 64 Settlements 3 Remediated 35 no remediation required 29 -being evaluated, remediated and assessed
    9. 9. DNR Report Cont...Issues Impacting Evaluation or Remediation Timelines1. Allowing all parties access to the property for evaluation is often disputed2. Discovery and sampling time-lines have to be agreed upon by parties or ordered by the court3. Limitations on the ability of parties to admit regulatory responsibility without admitting liability for other claims4. Proving responsibility through trial and the delays inherent in all litigation5. Remedial work requires time to complete in accordance with regulatory standards6. OOC role under ACT 312 in submitting to the Court its most feasible evaluation or remediation plan to meet applicable State Regulatory standards generally occurs after the completion of the trial on the merits in its entirety7. ACT 312 provides no way to enforce requirement in R.S> 30:29.1 that all environmental sample data associated with E & P activity be submitted to OOC within 10 days of receipt by all parties8. For various reasons recent oil & gas operators without any specific causal connection to environmental damage are subject to ACT 312 litigation9. Reimbursement for ACT 312 expenses by Conservation and the AGs office only occurs after a responsible party has been determined10. The complexity of the legal issues addressed in ACT 312 cases
    10. 10. Where are the suits
    11. 11. Problems with ACT 312Courts have interpreted the ACT 312 processincorrectly and inconsistently Many Courts awarding damages for private claims and regulatory claims before hearing from DNRSlowness in execution leads to higher attorneysfeesCompromises of 2006 have reared their head Most importantly, inability to admit responsibility for the regulatory damages onlyLandowners not giving consent to defendants toevaluate or remediate Have even blocked compliance orders from the Office of Conservation (Sweet Lake Land)
    12. 12. What we would like to fix in ACT 312Timelines and Schedules This would establish timeframes for each step to happen holding everyone accountableDelay Cannot move to trial on the merits until DNR submits planJury Instructions Juries are not being told what the ACT 312 process isAccess Landowner cannot deny defendant access to evaluate if notice is givenAdmission of Liability Allow the admission to be limited to regulatory damages
    13. 13. Timelines and Schedules This would establish timeframes for each step to happen holding everyone accountableDelay Cannot move to trial on the merits until DNR submits planJury Instructions Juries are not being told what the ACT 312 process isAccess Landowner cannot deny defendant access to evaluate if notice is givenAdmission of Liability Allow the admission to be limited to regulatory damages
    14. 14. Delay Cannot move to trial on the merits until DNR submits planJury Instructions Juries are not being told what the ACT 312 process isAccess Landowner cannot deny defendant access to evaluate if notice is givenAdmission of Liability Allow the admission to be limited to regulatory damages
    15. 15. Jury Instructions Juries are not being told what the ACT 312 process isAccess Landowner cannot deny defendant access to evaluate if notice is givenAdmission of Liability Allow the admission to be limited to regulatory damages
    16. 16. Access Landowner cannot deny defendant access to evaluate if notice is givenAdmission of Liability Allow the admission to be limited to regulatory damages
    17. 17. Admission of Liability Allow the admission to be limited to regulatory damages
    18. 18. Admission of Liability Allow the admission to be limited to regulatory damages
    19. 19. What are we proposing to fixAdmission of Liability Allow the admission to be limited to regulatory damages
    20. 20. Why can’t a compromise be reachedWhat we want that they will not agree to? DNR public hearing to develop plan (which is currently part of ACT 312)Why is that so important? 2 reasons Validates the plan by being an open and transparent process Only mechanism to consider RECAP as alternative to 29-B besides landowner consent
    21. 21. Why can’t a compromise be reachedWhat are they saying is wrong with what we want Costs - This will be an unfair burden on plaintiff to try the case 2 times - very expensive ANSWER - all plaintiff costs are covered by the party admitting responsibility currently under ACT 312 - so there is no additional costs. Also, ACT 312 currently requires a public hearing as part of the determination of the plan Primary Jurisdiction - Another way to get around to primary jurisdiction ANSWER - There is no change in the jurisdiction of the trial, nor is there any change in authority of the district court in approval of the plan or their standard of review of the plan
    22. 22. How ACT 312 was intended to work Responsible Party Regulatory “Other” Damages Determination Remediation Determination Determination Jury Party DNR Approval of Private “Extra”Decides Admits Regulatory Plans Damages Remediation How ACT 312 has worked Damages Regulatory Responsible Party Determination Remediation Determination Determination Regulatory Damages Jury Party DNR Approval of Private “Extra” Regulatory PlansDecides Admits Damages Remediation
    23. 23. THE PROCESS LANDOWNER FILES LAWSUIT FORCONTAMINATION
    24. 24. THE PROCESS LANDOWNER FILES LAWSUIT FORCONTAMINATION
    25. 25. THE PROCESS LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS FOR BEEN FILED ISCONTAMINATION SENT TO OOC AND AG R.S. 30:29 B(1)
    26. 26. THE PROCESS OPERATORS ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS FOR BEEN FILED IS R.S. 30:29 C(1)CONTAMINATION SENT TO OOC AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY
    27. 27. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITHCONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY
    28. 28. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITHCONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY PLANS RECEIVED BY COURT AND OOC R.S. 30:29 C(1)
    29. 29. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITHCONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY LANDOWNER OR OTHER PLANS PARTIES RECEIVED BY SUMBIT PLAN(S) COURT AND TO OOC/COURT OOC ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1) R.S. 30:29 C(1)
    30. 30. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITHCONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY LANDOWNER OR OTHER OOC REVIEWS PLANS PARTIES PLAN AND GIVES RECEIVED BY SUMBIT PLAN(S) ESTIMATE OF COURT AND TO OOC/COURT REVIEW AND OOC ALONG WITH COSTS TO ESTIMATED COURT COSTS R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    31. 31. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITHCONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY LANDOWNER OR OTHER OOC REVIEWS PLANS PARTIES OOC CONDUCTS PLAN AND GIVES RECEIVED BY SUMBIT PLAN(S) PUBLIC HEARING ESTIMATE OF COURT AND TO OOC/COURT ON THE PLAN(S) REVIEW AND OOC ALONG WITH COSTS TO ESTIMATED COURT COSTS R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    32. 32. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITHCONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTY LANDOWNER OR OTHER OOC REVIEWS OOC SELECTS PLANS PARTIES OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH COSTS TO ESTIMATED COURT COSTS R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    33. 33. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITH CONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTYR.S. 30:29 C(5) COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    34. 34. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITH CONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTYR.S. 30:29 C(5) COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1) COURT ORDERS RESPONSIBLE PARTY TO FUND THE PLANR.S. 30:29 C(5)
    35. 35. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITH CONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTYR.S. 30:29 C(5) COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1) COURT RESPONSIBLE ORDERS PARTY DEPOSITS RESPONSIBLE MONEY INTO THE PARTY TO REGISTRY OF THE FUND THE COURT PLANR.S. 30:29 C(5) R.S. 30:29 C(6)a
    36. 36. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITH CONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTYR.S. 30:29 C(5) COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1) COURT RESPONSIBLE ORDERS PARTY DEPOSITS COURT RESPONSIBLE MONEY INTO THE DETERMINES PARTY TO REGISTRY OF THE DAMAGES FUND THE COURT PLANR.S. 30:29 C(5) R.S. 30:29 C(6)a
    37. 37. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITH CONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTYR.S. 30:29 C(5) COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1) COURT RESPONSIBLE ORDERS PARTY DEPOSITS COURT RESPONSIBLE REMEDIATION MONEY INTO THE DETERMINES PARTY TO TAKES PLACE REGISTRY OF THE DAMAGES FUND THE COURT PLANR.S. 30:29 C(5) R.S. 30:29 C(6)a
    38. 38. THE PROCESS OPERATORS R.S. 30:29 C(1) ADMITS LIABILITY FOR ALL DAMAGES LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS PARTY SUBMITS PLAN FOR BEEN FILED IS R.S. 30:29 C(1) TO OOC ALONG WITH CONTAMINATION SENT TO OOC ESTIMATED COSTS AND AG COURT DETERMINES R.S. 30:29 B(1) RESPONSIBLE PARTYR.S. 30:29 C(5) COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1) COURT EXCESS RESPONSIBLE ORDERS REMEDIATION PARTY DEPOSITS COURT RESPONSIBLE REMEDIATION FUNDS ARE MONEY INTO THE DETERMINES PARTY TO TAKES PLACE RETURNED TO REGISTRY OF THE DAMAGES FUND THE RESPONSIBLE COURT PLAN PARTYR.S. 30:29 C(5) R.S. 30:29 C(6)a R.S. 30:29 D(4)
    39. 39. Reality LANDOWNER FILES LAWSUIT FORCONTAMINATION
    40. 40. Reality LANDOWNER FILES LAWSUIT FORCONTAMINATION
    41. 41. Reality LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS FOR BEEN FILED ISCONTAMINATION SENT TO OOC AND AG R.S. 30:29 B(1)
    42. 42. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO OPERATOR TO REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) FOR BEEN FILED ISCONTAMINATION SENT TO OOC AND AG TRIAL ON MERITS R.S. 30:29 B(1)
    43. 43. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) FOR BEEN FILED ISCONTAMINATION SENT TO OOC AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) REGULATORY
    44. 44. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TOCONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) REGULATORY
    45. 45. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TOCONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLAN TO OOC ALONG WITH ESTIMATED COSTS PLANS R.S. 30:29 C(1) RECEIVED BY COURT AND OOC LANDOWNER OR OTHER R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1)
    46. 46. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TOCONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLAN TO OOC ALONG WITH ESTIMATED COSTS OOC REVIEWS PLANS R.S. 30:29 C(1) PLAN AND GIVES RECEIVED BY ESTIMATE OF COURT AND REVIEW AND OOC COSTS TO COURT LANDOWNER OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1)
    47. 47. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TOCONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLAN TO OOC ALONG WITH ESTIMATED COSTS OOC REVIEWS PLANS R.S. 30:29 C(1) OOC CONDUCTS PLAN AND GIVES RECEIVED BY PUBLIC HEARING ESTIMATE OF COURT AND ON THE PLAN(S) REVIEW AND OOC COSTS TO COURT LANDOWNER R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1)
    48. 48. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TOCONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLAN TO OOC ALONG WITH ESTIMATED COSTS OOC SELECTS OOC REVIEWS PLANS R.S. 30:29 C(1) OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND ON THE PLAN(S) REVIEW AND COURT OOC COSTS TO COURT LANDOWNER R.S. 30:29 C(2) R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1)
    49. 49. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TO CONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLANR.S. 30:29 C(5) TO OOC ALONG WITH ESTIMATED COSTS COURT SHALL ADOPT PLAN OOC SELECTS OOC REVIEWS PLANS R.S. 30:29 C(1) SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC OF EVIDENCE COSTS TO AGAINST COURT IT LANDOWNER R.S. 30:29 C(2) R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1)
    50. 50. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TO CONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLANR.S. 30:29 C(5) TO OOC ALONG WITH ESTIMATED COSTS COURT SHALL ADOPT PLAN OOC SELECTS OOC REVIEWS PLANS R.S. 30:29 C(1) SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC OF EVIDENCE COSTS TO AGAINST COURT IT LANDOWNER R.S. 30:29 C(2) R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COURT COSTS ORDERS RESPONSIBLE R.S. 30:29 C(1) PARTY TO FUND THE PLANR.S. 30:29 C(5)
    51. 51. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TO CONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLANR.S. 30:29 C(5) TO OOC ALONG WITH ESTIMATED COSTS COURT SHALL ADOPT PLAN OOC SELECTS OOC REVIEWS PLANS R.S. 30:29 C(1) SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC OF EVIDENCE COSTS TO AGAINST COURT IT LANDOWNER R.S. 30:29 C(2) R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COURT COSTS RESPONSIBLE ORDERS PARTY DEPOSITS RESPONSIBLE MONEY INTO THE R.S. 30:29 C(1) PARTY TO REGISTRY OF THE FUND THE COURT PLANR.S. 30:29 C(5) R.S. 30:29 C(6)a
    52. 52. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TO CONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLANR.S. 30:29 C(5) TO OOC ALONG WITH ESTIMATED COSTS COURT SHALL ADOPT PLAN OOC SELECTS OOC REVIEWS PLANS R.S. 30:29 C(1) SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC OF EVIDENCE COSTS TO AGAINST COURT IT LANDOWNER R.S. 30:29 C(2) R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COURT COSTS RESPONSIBLE ORDERS PARTY DEPOSITS REMEDIATION RESPONSIBLE MONEY INTO THE TAKES PLACE R.S. 30:29 C(1) PARTY TO REGISTRY OF THE FUND THE COURT PLANR.S. 30:29 C(5) R.S. 30:29 C(6)a
    53. 53. Reality LANDOWNER SETTLES SUIT GIVES CONSENT TO REMEDIATION OPERATOR TO TAKES PLACE REMEDIATE ACCORDING TO OPERATORS PLAN LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS R.S. 30:29 J(1) COURT REFERS FOR BEEN FILED IS THE MATTER TO CONTAMINATION SENT TO OOC THE DEPARTMENT AND AG COURT DETERMINES TRIAL ON DAMAGES - MERITS PRIVATE AND R.S. 30:29 B(1) RESPONSIBLE REGULATORY PARTY SUBMITS PLANR.S. 30:29 C(5) TO OOC ALONG WITH ESTIMATED COSTS COURT SHALL ADOPT PLAN OOC SELECTS OOC REVIEWS PLANS R.S. 30:29 C(1) SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC OF EVIDENCE COSTS TO AGAINST COURT IT LANDOWNER R.S. 30:29 C(2) R.S. 30:29 C(2) OR OTHER R.S. 30:29 C(1) R.S. 30:29 C(1) PARTIES SUMBIT PLAN(S) TO OOC/COURT ALONG WITH ESTIMATED COURT EXCESS COSTS RESPONSIBLE ORDERS PARTY DEPOSITS REMEDIATION REMEDIATION RESPONSIBLE MONEY INTO THE TAKES PLACE FUNDS ARE R.S. 30:29 C(1) PARTY TO REGISTRY OF THE RETURNED TO FUND THE COURT RESPONSIBLE PLAN PARTYR.S. 30:29 C(5) R.S. 30:29 C(6)a R.S. 30:29 D(4)
    54. 54. Proposed Solution to ACT 312 Regulatory “Other” Damages Remediation Determination Determination Party DNR Approval of Private “Extra” Admits Regulatory Plans Damages RemediationResponsible Party Determination Jury Decides Damages Regulatory Determination Remediation Determination Regulatory Damages DNR Approval of Private “Extra” Regulatory Plans Damages Remediation
    55. 55. The Solution LANDOWNER FILES LAWSUIT FORCONTAMINATION
    56. 56. The Solution LANDOWNER FILES LAWSUIT FORCONTAMINATION
    57. 57. The Solution LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS FOR BEEN FILED ISCONTAMINATION SENT TO OOC AND AG R.S. 30:29 B(1)
    58. 58. The Solution LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS OPERATORS FOR BEEN FILED IS ADMITSCONTAMINATION SENT TO OOC LIABILITY FOR AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY
    59. 59. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages LANDOWNER NOTIFICATION FILES LAWSUIT THAT SUIT HAS OPERATORS FOR BEEN FILED IS ADMITSCONTAMINATION SENT TO OOC LIABILITY FOR AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY
    60. 60. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITHCONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY
    61. 61. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITHCONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY PLANS RECEIVED BY COURT AND OOC R.S. 30:29 C(1)
    62. 62. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITHCONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY LANDOWNER OR OTHER PLANS PARTIES RECEIVED BY SUMBIT PLAN(S) COURT AND TO OOC/COURT OOC ALONG WITH ESTIMATED COSTS R.S. 30:29 C(1) R.S. 30:29 C(1)
    63. 63. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITHCONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY LANDOWNER OR OTHER OOC REVIEWS PLANS PARTIES PLAN AND GIVES RECEIVED BY SUMBIT PLAN(S) ESTIMATE OF COURT AND TO OOC/COURT REVIEW AND OOC ALONG WITH COSTS TO ESTIMATED COURT COSTS R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    64. 64. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITHCONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY LANDOWNER OR OTHER OOC REVIEWS PLANS PARTIES OOC CONDUCTS PLAN AND GIVES RECEIVED BY SUMBIT PLAN(S) PUBLIC HEARING ESTIMATE OF COURT AND TO OOC/COURT ON THE PLAN(S) REVIEW AND OOC ALONG WITH COSTS TO ESTIMATED COURT COSTS R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    65. 65. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITHCONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURT DETERMINES RESPONSIBLE PARTY LANDOWNER OR OTHER OOC REVIEWS OOC SELECTS PLANS PARTIES OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH COSTS TO ESTIMATED COURT COSTS R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)
    66. 66. R.S. 30:29.2The Solution Defendant limits admission to regulatory damages R.S. 30:29 C(1) LANDOWNER NOTIFICATION RESPONSIBLE FILES LAWSUIT THAT SUIT HAS OPERATORS PARTY SUBMITS PLAN FOR BEEN FILED IS ADMITS TO OOC ALONG WITH CONTAMINATION SENT TO OOC LIABILITY FOR ESTIMATED COSTS AND AG ALL DAMAGES R.S. 30:29 C(1) R.S. 30:29 B(1) COURTR.S. 30:29 C(5) DETERMINES RESPONSIBLE PARTY COURT LANDOWNER SHALL OR OTHER ADOPT PLAN OOC REVIEWS OOC SELECTS PLANS PARTIES SENT BY OOC OOC CONDUCTS PLAN AND GIVES PLAN AND RECEIVED BY SUMBIT PLAN(S) UNLESS THERE IS A PUBLIC HEARING ESTIMATE OF SUBMITS TO COURT AND TO OOC/COURT PREPONDERANCE ON THE PLAN(S) REVIEW AND COURT OOC ALONG WITH OF EVIDENCE COSTS TO ESTIMATED AGAINST COURT COSTS IT R.S. 30:29 C(2) R.S. 30:29 C(2) R.S. 30:29 C(1) R.S. 30:29 C(1) R.S. 30:29 C(1)

    ×