SlideShare a Scribd company logo
1 of 32
Download to read offline
Proposed Changes to RCRA
Todd Houts
Director, EHS
University of Missouri
A basic understanding of RCRA is assumed in this presentation.
 On September, 25, 2015, EPA published a
lengthy set of “improvements” to RCRA
 A large portion is simply reorganization to
make them more “user friendly”
 But there are also significant changes
proposed
 Comment period ends Dec 24, 2015
Generator Status # of Facilities Total HW
Generated (tons)
% ofTotal HW
Generation
CESQGs 293,000-470,000 59,000-144,000 <1%
SQGs 46,000-60,000 70,000-152,000 <1%
LQGs 14,300 34,500,000 99%
Total 353,300-544,300 34,800,000 100%
 Items to note:
 Impact of new rules mostly benefits SQGs and
CESQGs and mostly adds new rules to LQGs
 My opinion: this is a “fix” for <1% HW generated
and new burdens for the majority
 EPA is proposing to change CESQG toVSGQ
 Very Small Quantity Generator
 “Exempt” may be a misleading word
 This presentation uses current CESQG term
for clarity and consistency
 Consolidation of CESQGWaste at LQGs
 Episodic Generation
 Labeling
 SatelliteAccumulation Areas
 Hazardous Waste Determinations
 Benefits for user:
 Can consolidate and ship from one location
 Permit not required to accept from owned
CESQGs
 Benefits for EPA:
 CESQG waste is managed under LQG restrictions
▪ More environmentally sound
 Restrictions
 CESQG and LQG must be “controlled” by same
“person” (as defined in RCRA)
 Requirements
 Notify state of specific participation
 Recordkeeping for these transfers (shipments)
 Report under LQG Biennial Report
 Note this is only a problem for CESQGs and
SQGs (less than 1% of total HW generated)
 Would allow once/calendar year event (can
petition for a second) for planned event
(clean out)
 Requirements for all:
 Notify EPA or state before planned event
 45 days to complete event (30 day extension
possible)
 Additional Requirements for CESQG:
 Obtain RCRA ID number
 Use HW Manifest to ship episodic waste to facility
 Label episodic containers
 Identify an emergency coordinator
 Maintain records re: episodic event
 EPA concerned current labelling doesn’t
require hazard communication
 (OSHA HazCom doesn’t apply to HW)
 This is an intentional “loophole” (per EPA’s own
design) as those dealing with HW have training
not necessarily required for good material
▪ 29 states do not have state implementation of OSHA
leaving all state agencies out of compliance technically
for good materials
▪ But we haven’t seemed to have needed to “solve” that
lack of state OSHA-required labeling either
 Would apply to SAA, CAA &Transfer facilites
 Containers, tanks, drip pads, containment
buildings
 Require hazard label (options)
 Require “plain English” content labeling
 Note this essentially removes the “or” of SAA
[262.34(c)]
 Label with “HazardousWaste” “words that
describe the waste”
 Opinion on requiring more labeling than
currently required (haz waste + plain English
+ hazard communication term):
 Eerily similar to Missouri PML requirements to
satisfy emergency responder’s concerns of a
“problem” already solved by other requirements
 Allows containers to remain open under
limited circumstances
 e.g., piranha waste (builds up pressure)
 e.g., continuous flow waste from instrumentation
 Add maximum weight (in addition to volume
as defined Federally) at each SAA
 Clarify “3 days” is calendar not working days
 Circling back to labeling at SAA…
 Essentially would force some generators
from following SAA at point to generation to
following hazcom
 Why? Because the “spent” solvents from one lab,
could be re-tasked as cleaning solvents elsewhere
at the same generator
 Forcing HWD to point of generation in complex
organizations may lead to EPA losing areas they
can inspect
 For labs one of the…
 EPA claims: “Generators consistently fail to
make a correct hazardous waste
determination leading to mismanagement of
hazardous waste”
 Then EPA goes on to say: “Non-compliance
rates range from 10 to 30 percent”
 So then… compliance ranges up to 90%?
 And we need to fix it?
 Currently require documentationWHEN
determined to be HW, but not when you
determine it is NOT HW
 Proposal would require documentation of all
evaluations (solid wastes in 40 CFR 261.2)
regardless of the outcome
 Spent materials, sludges, byproducts, discarded
commercial chemical products
 Discarded commercial chemical products and
variable lab waste streams are the
aforementioned elephant
 The are more than 10 million chemical
products and when concentration is
considered – there are billions
 Emergency Planning and Preparedness
 Reporting
 Waiver to 50-foot Requirement
 Closure
 Contingency Plans are lengthy
 Emergency responders may have difficulty
extracting most important information
 Change:
 New LQGs must include executive summary as
part of Contingency Plan
 As proposed, existing LQGs are not required to
add an executive summary
▪ Opinion: Emergency responders will expect from all
 Types/Amounts of hazardous waste
 Maps of site and surrounding area
 Water supply location
 Identify on-site notification systems available
 Emergency contact
 Acknowledges existence of LEPC (local
emergency planning committees)
 Requires submitting Contingency Plan (or
Executive Summary for new LQGs) to LEPC
 Clarifications:
 Only applies to areas where HW is accumulated
 Removes requiring personal information in record
 Acknowledge modern technology (i.e.: land line
not required)
 Allows contractors to clean up releases
 EPA doesn’t know how many SQGs exist
 No re-notification requirement
 Many were one time generators (but still being
counted)
 Require SQGs to re-notify every two years
 Provide electronic option
 CFR regulations don’t match biennial report
instructions
 Solution:
 Remove CFR instructions – refer to form
instructions
 Additional changes – minimal impact in Missouri
due to state reporting requirements
 Storing reactive or ignitable waste 50-feet
from property line may not be possible in
some areas, especially urban setting
 Proposed: allow generator to seek a waiver
from Fire Department if facility has taken
precautions that don’t include 50-foot rule
 LQGs accumulating in containers only that
fail to achieve clean closure have no failsafe
requirement
 For those accumulating in tanks, drip pads
and containment buildings currently require
to be closed as a landfill if no clean closure
 Expand the acute threshold to accommodate
spill cleanup.The threshold becomes:
 ≤ 1 kg acute hazardous waste, and
 ≤ 100 kg residue or contaminated soil, water or
other debris resulting from the cleanup of a spill…
of any acute hazardous waste
 Greater than either of these = LQG
 Failure to comply with an exemption
condition would result in loss of exemption.
 EPA says (80 FR 57934): “…they would be
considered an operatingTSDF with a permit
and/or in violation of the storage facility operating
standards…”
Todd Houts
Director, EHS
University of Missouri
houtst@missouri.edu

More Related Content

Viewers also liked

14 april 2016 sab ki khabren
14 april 2016 sab ki khabren14 april 2016 sab ki khabren
14 april 2016 sab ki khabrenSantosh Tiwari
 
Como subir un video a youtube
Como subir un video a youtubeComo subir un video a youtube
Como subir un video a youtubeDanielaSuarz
 
Myslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccion
Myslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccionMyslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccion
Myslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccionSAMIR AUGUSTO AREVALO VIDAL
 
Complementary and alternative therapies for obesity
Complementary and alternative therapies for obesityComplementary and alternative therapies for obesity
Complementary and alternative therapies for obesityNaina Mohamed, PhD
 
Memoria descriptiva para elaboración de expediente técnico.
Memoria descriptiva para elaboración de expediente técnico.Memoria descriptiva para elaboración de expediente técnico.
Memoria descriptiva para elaboración de expediente técnico.Pedro Cornelio
 
Nervous tissue (Histology)
Nervous tissue (Histology)Nervous tissue (Histology)
Nervous tissue (Histology)ozhin araz
 

Viewers also liked (11)

Werner bischof
Werner bischofWerner bischof
Werner bischof
 
14 april 2016 sab ki khabren
14 april 2016 sab ki khabren14 april 2016 sab ki khabren
14 april 2016 sab ki khabren
 
Ppt cap3 obras
Ppt cap3 obrasPpt cap3 obras
Ppt cap3 obras
 
Como subir un video a youtube
Como subir un video a youtubeComo subir un video a youtube
Como subir un video a youtube
 
El Dengue
El Dengue El Dengue
El Dengue
 
Intercambio usa galileo galilei
Intercambio usa galileo galileiIntercambio usa galileo galilei
Intercambio usa galileo galilei
 
Energy security
Energy security Energy security
Energy security
 
Myslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccion
Myslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccionMyslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccion
Myslide.es miguel salinas-seminario-costos-y-presupuestos-en-construccion
 
Complementary and alternative therapies for obesity
Complementary and alternative therapies for obesityComplementary and alternative therapies for obesity
Complementary and alternative therapies for obesity
 
Memoria descriptiva para elaboración de expediente técnico.
Memoria descriptiva para elaboración de expediente técnico.Memoria descriptiva para elaboración de expediente técnico.
Memoria descriptiva para elaboración de expediente técnico.
 
Nervous tissue (Histology)
Nervous tissue (Histology)Nervous tissue (Histology)
Nervous tissue (Histology)
 

Similar to Todd Houts, University of Missouri, Proposed Changes to RCRA, Hazardous Waste Generator Improvements, Missouri Hazardous Waste Seminar, November 5, 2015

Air Permitting Biomass Combustion Units
Air Permitting Biomass Combustion UnitsAir Permitting Biomass Combustion Units
Air Permitting Biomass Combustion UnitsAll4 Inc.
 
August 2015 reg update ch2m
August 2015 reg update ch2mAugust 2015 reg update ch2m
August 2015 reg update ch2mDoug Huxley
 
Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...
Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...
Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...Kevin Perry
 
Enforcement Penalty ProcessUniversity of HartfordApril 16,.docx
Enforcement Penalty ProcessUniversity of HartfordApril 16,.docxEnforcement Penalty ProcessUniversity of HartfordApril 16,.docx
Enforcement Penalty ProcessUniversity of HartfordApril 16,.docxgidmanmary
 
Ask the Expert: The Hazardous Waste Generator Improvements Rule
Ask the Expert: The Hazardous Waste Generator Improvements RuleAsk the Expert: The Hazardous Waste Generator Improvements Rule
Ask the Expert: The Hazardous Waste Generator Improvements RuleTriumvirate Environmental
 
Air Emission Permitting and Reporting Requirements Under Environmental Laws
Air Emission Permitting and Reporting Requirements Under Environmental LawsAir Emission Permitting and Reporting Requirements Under Environmental Laws
Air Emission Permitting and Reporting Requirements Under Environmental Lawssbligh0101
 
Assent Compliance Guide for 2011 REACH/RoHS
Assent Compliance Guide for 2011 REACH/RoHSAssent Compliance Guide for 2011 REACH/RoHS
Assent Compliance Guide for 2011 REACH/RoHSMatt Whitteker
 
Backflow Best Practices and Standard Details: Part 3
Backflow Best Practices and Standard Details: Part 3Backflow Best Practices and Standard Details: Part 3
Backflow Best Practices and Standard Details: Part 3Safe-T-Cover
 
Overview of halt a paradigm shift for rev3
Overview of halt a  paradigm shift for   rev3Overview of halt a  paradigm shift for   rev3
Overview of halt a paradigm shift for rev3Accendo Reliability
 
CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...
CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...
CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...KirkGray
 
Microsoft PowerPoint - Ch106606.PDF
Microsoft PowerPoint - Ch106606.PDFMicrosoft PowerPoint - Ch106606.PDF
Microsoft PowerPoint - Ch106606.PDFhesam ahmadian
 
Wireless Measurement and Control - AIChE New Orleans
Wireless Measurement and Control - AIChE New OrleansWireless Measurement and Control - AIChE New Orleans
Wireless Measurement and Control - AIChE New OrleansJim Cahill
 
CDCV Webinar Feb 191
CDCV Webinar Feb 191CDCV Webinar Feb 191
CDCV Webinar Feb 191matt_UCI
 
BESTFinalReport
BESTFinalReportBESTFinalReport
BESTFinalReportEvan Crall
 
Industrial Hygienists and Facility Managers: Potentially Productive Partners
Industrial Hygienists and Facility Managers: Potentially Productive PartnersIndustrial Hygienists and Facility Managers: Potentially Productive Partners
Industrial Hygienists and Facility Managers: Potentially Productive PartnersSentry Air Systems, Inc.
 
Regulatory Update 2015
Regulatory Update 2015Regulatory Update 2015
Regulatory Update 2015Jane Besch
 

Similar to Todd Houts, University of Missouri, Proposed Changes to RCRA, Hazardous Waste Generator Improvements, Missouri Hazardous Waste Seminar, November 5, 2015 (20)

Air Permitting Biomass Combustion Units
Air Permitting Biomass Combustion UnitsAir Permitting Biomass Combustion Units
Air Permitting Biomass Combustion Units
 
August 2015 reg update ch2m
August 2015 reg update ch2mAugust 2015 reg update ch2m
August 2015 reg update ch2m
 
Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...
Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...
Liane Hetherington-Ward, Trinity Consultants, The Changing Landscape for RCRA...
 
Enforcement Penalty ProcessUniversity of HartfordApril 16,.docx
Enforcement Penalty ProcessUniversity of HartfordApril 16,.docxEnforcement Penalty ProcessUniversity of HartfordApril 16,.docx
Enforcement Penalty ProcessUniversity of HartfordApril 16,.docx
 
Ask the Expert: The Hazardous Waste Generator Improvements Rule
Ask the Expert: The Hazardous Waste Generator Improvements RuleAsk the Expert: The Hazardous Waste Generator Improvements Rule
Ask the Expert: The Hazardous Waste Generator Improvements Rule
 
Air Emission Permitting and Reporting Requirements Under Environmental Laws
Air Emission Permitting and Reporting Requirements Under Environmental LawsAir Emission Permitting and Reporting Requirements Under Environmental Laws
Air Emission Permitting and Reporting Requirements Under Environmental Laws
 
Assent Compliance Guide for 2011 REACH/RoHS
Assent Compliance Guide for 2011 REACH/RoHSAssent Compliance Guide for 2011 REACH/RoHS
Assent Compliance Guide for 2011 REACH/RoHS
 
10 Common Hazardous Waste Violations
10 Common Hazardous Waste Violations10 Common Hazardous Waste Violations
10 Common Hazardous Waste Violations
 
Backflow Best Practices and Standard Details: Part 3
Backflow Best Practices and Standard Details: Part 3Backflow Best Practices and Standard Details: Part 3
Backflow Best Practices and Standard Details: Part 3
 
Overview of halt a paradigm shift for rev3
Overview of halt a  paradigm shift for   rev3Overview of halt a  paradigm shift for   rev3
Overview of halt a paradigm shift for rev3
 
CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...
CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...
CTEA Test Symposium Presentation: Overview of HALT and HASS: A Major Paradigm...
 
Microsoft PowerPoint - Ch106606.PDF
Microsoft PowerPoint - Ch106606.PDFMicrosoft PowerPoint - Ch106606.PDF
Microsoft PowerPoint - Ch106606.PDF
 
Luke Marshall - One Number to Prioritise Work?
Luke Marshall - One Number to Prioritise Work?Luke Marshall - One Number to Prioritise Work?
Luke Marshall - One Number to Prioritise Work?
 
National policy, standards and knowledge sharing
National policy, standards and knowledge sharingNational policy, standards and knowledge sharing
National policy, standards and knowledge sharing
 
Wireless Measurement and Control - AIChE New Orleans
Wireless Measurement and Control - AIChE New OrleansWireless Measurement and Control - AIChE New Orleans
Wireless Measurement and Control - AIChE New Orleans
 
CDCV Webinar Feb 191
CDCV Webinar Feb 191CDCV Webinar Feb 191
CDCV Webinar Feb 191
 
BESTFinalReport
BESTFinalReportBESTFinalReport
BESTFinalReport
 
Industrial Hygienists and Facility Managers: Potentially Productive Partners
Industrial Hygienists and Facility Managers: Potentially Productive PartnersIndustrial Hygienists and Facility Managers: Potentially Productive Partners
Industrial Hygienists and Facility Managers: Potentially Productive Partners
 
Regulatory Update 2015
Regulatory Update 2015Regulatory Update 2015
Regulatory Update 2015
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 

More from Kevin Perry

Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, 2016, Overland Park
Brunetti, Rick, KDHE, Regional Air Issues Roundtable,  MECC, 2016, Overland ParkBrunetti, Rick, KDHE, Regional Air Issues Roundtable,  MECC, 2016, Overland Park
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, 2016, Overland ParkKevin Perry
 
Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...
Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...
Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...Kevin Perry
 
Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...
Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...
Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...Kevin Perry
 
Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...
Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...
Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...Kevin Perry
 
Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...
Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...
Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...Kevin Perry
 
Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...
Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...
Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...Kevin Perry
 
Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...
Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...
Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...Kevin Perry
 
Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...
Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...
Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...Kevin Perry
 
Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...
Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...
Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...Kevin Perry
 
Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...
Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...
Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...Kevin Perry
 
Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...
Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...
Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...Kevin Perry
 
Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...
Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...
Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...Kevin Perry
 
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland ParkHieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland ParkKevin Perry
 
Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...
Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...
Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...Kevin Perry
 
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...Kevin Perry
 
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas City
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas CityBrunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas City
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas CityKevin Perry
 
Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...
Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...
Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...Kevin Perry
 
Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...
Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...
Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...Kevin Perry
 
Jay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas City
Jay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas CityJay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas City
Jay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas CityKevin Perry
 
Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...
Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...
Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...Kevin Perry
 

More from Kevin Perry (20)

Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, 2016, Overland Park
Brunetti, Rick, KDHE, Regional Air Issues Roundtable,  MECC, 2016, Overland ParkBrunetti, Rick, KDHE, Regional Air Issues Roundtable,  MECC, 2016, Overland Park
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, 2016, Overland Park
 
Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...
Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...
Shanahan, Matt, Burns & McDonnell, RCRA Update Proposed Hazardous Waste Gener...
 
Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...
Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...
Hiatt, Jennifer, GHD Services, Spill Plans Made Simple, Avoiding Noncomplianc...
 
Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...
Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...
Chavez, Nikki, iSi Environmental, Form R Tips and Trip Ups, MECC, 2016, Overl...
 
Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...
Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...
Sturgess, Steve, MDNR, Missouri Risk-Based Corrective Action Long-Term Stewar...
 
Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...
Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...
Gronstal Anderson, Ingrid, PAL Case Study Plant-Wide Applicability Limit for ...
 
Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...
Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...
Muth, Emily, OPPD, Environmental Compliance and Information Systems, MECC, 20...
 
Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...
Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...
Wanzenried, Brian, Gavilon, Strategic Planning for Environmental Staffing, ME...
 
Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...
Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...
Cozad, David, US EPA, Dernovish, David, KDHE, Duggan, Tim, MO AGO, Tormey, Ed...
 
Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...
Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...
Pendergrass, Gary, GeoEngineers, CCR Rule Compliance Innovative Geophysics to...
 
Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...
Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...
Hindin, David, US EPA, OECI, Next Generation Compliance Water and Waste Examp...
 
Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...
Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...
Meerian, Marcus, KDHE, Overview of Revisions to the UST Regulations, MECC, 20...
 
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland ParkHieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
Hieb, Wendy, IDNR, Hot Topics in NPDES Permitting, MECC, 2016, Overland Park
 
Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...
Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...
Johnson, Susan, IDNR, Making Hazardous/Non-Hazardous Waste Determinations, ME...
 
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
 
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas City
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas CityBrunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas City
Brunetti, Rick, KDHE, Regional Air Issues Roundtable, MECC, Kansas City
 
Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...
Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...
Funderburg, Lisa, Stinson Leonard Street, Compliance Tools Top Ten Tips When ...
 
Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...
Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...
Grice, Lisa, Ramboll, Corporate Sustainability Where the Rest of the Company ...
 
Jay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas City
Jay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas CityJay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas City
Jay, Mike, US EPA, Regional Air Issues Roundtable, MECC, Kansas City
 
Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...
Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...
Morrison, Rob, Barr Engineering, Using Mixing Zones Higher in the Watershed, ...
 

Recently uploaded

Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girlsssuser7cb4ff
 
WindEurope - Wind energy in Europe - 2023.pdf
WindEurope - Wind energy in Europe - 2023.pdfWindEurope - Wind energy in Europe - 2023.pdf
WindEurope - Wind energy in Europe - 2023.pdfShingoAramaki
 
Available to Promise Oracle R12 ATP.pptx
Available to Promise Oracle R12 ATP.pptxAvailable to Promise Oracle R12 ATP.pptx
Available to Promise Oracle R12 ATP.pptxbskumar_slideshare
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdfsrivastavaakshat51
 
Water Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfggggggggggggggggggggggggggggggggggggggWater Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfggggggggggggggggggggggggggggggggggggggkhulekanimkhize2
 
Delivering nature-based solution outcomes by addressing policy, institutiona...
Delivering nature-based solution outcomes by addressing  policy, institutiona...Delivering nature-based solution outcomes by addressing  policy, institutiona...
Delivering nature-based solution outcomes by addressing policy, institutiona...CIFOR-ICRAF
 
See How do animals kill their prey for food
See How do animals kill their prey for foodSee How do animals kill their prey for food
See How do animals kill their prey for fooddrsk203
 
885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Educationz xss
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170simranguptaxx69
 
BIODIVERSITY QUIZ ELIMINATION ROUND.pptx
BIODIVERSITY QUIZ ELIMINATION ROUND.pptxBIODIVERSITY QUIZ ELIMINATION ROUND.pptx
BIODIVERSITY QUIZ ELIMINATION ROUND.pptxROLANARIBATO3
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...Aqsa Yasmin
 
EMP (Environment Management Plan . .pptx
EMP (Environment Management Plan . .pptxEMP (Environment Management Plan . .pptx
EMP (Environment Management Plan . .pptxSarmad Naeem
 
Group 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfGroup 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfs2015004
 
Asexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptxAsexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptxMyBrightestStarParkJ
 
Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作
Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作
Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作f3774p8b
 

Recently uploaded (20)

Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
 
WindEurope - Wind energy in Europe - 2023.pdf
WindEurope - Wind energy in Europe - 2023.pdfWindEurope - Wind energy in Europe - 2023.pdf
WindEurope - Wind energy in Europe - 2023.pdf
 
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
 
FULL ENJOY Call Girls In kashmiri gate (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In  kashmiri gate (Delhi) Call Us 9953056974FULL ENJOY Call Girls In  kashmiri gate (Delhi) Call Us 9953056974
FULL ENJOY Call Girls In kashmiri gate (Delhi) Call Us 9953056974
 
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
 
Available to Promise Oracle R12 ATP.pptx
Available to Promise Oracle R12 ATP.pptxAvailable to Promise Oracle R12 ATP.pptx
Available to Promise Oracle R12 ATP.pptx
 
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
5 Wondrous Places You Should Visit at Least Once in Your Lifetime (1).pdf
 
Water Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfggggggggggggggggggggggggggggggggggggggWater Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
Water Conservation.pptxfgggggggggggggggggggggggggggggggggggggg
 
Delivering nature-based solution outcomes by addressing policy, institutiona...
Delivering nature-based solution outcomes by addressing  policy, institutiona...Delivering nature-based solution outcomes by addressing  policy, institutiona...
Delivering nature-based solution outcomes by addressing policy, institutiona...
 
See How do animals kill their prey for food
See How do animals kill their prey for foodSee How do animals kill their prey for food
See How do animals kill their prey for food
 
885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education885MTAMount DMU University Bachelor's Diploma in Education
885MTAMount DMU University Bachelor's Diploma in Education
 
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
 
BIODIVERSITY QUIZ ELIMINATION ROUND.pptx
BIODIVERSITY QUIZ ELIMINATION ROUND.pptxBIODIVERSITY QUIZ ELIMINATION ROUND.pptx
BIODIVERSITY QUIZ ELIMINATION ROUND.pptx
 
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
EARTH DAY Slide show EARTHDAY.ORG is unwavering in our commitment to end plas...
 
EMP (Environment Management Plan . .pptx
EMP (Environment Management Plan . .pptxEMP (Environment Management Plan . .pptx
EMP (Environment Management Plan . .pptx
 
Group 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdfGroup 4The Species of the Atlantic Forest.pdf
Group 4The Species of the Atlantic Forest.pdf
 
Asexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptxAsexual-and-Sexual-Reproduction.huhupptx
Asexual-and-Sexual-Reproduction.huhupptx
 
Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作
Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作
Düsseldorf U学位证,杜塞尔多夫大学毕业证书1:1制作
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 

Todd Houts, University of Missouri, Proposed Changes to RCRA, Hazardous Waste Generator Improvements, Missouri Hazardous Waste Seminar, November 5, 2015

  • 1. Proposed Changes to RCRA Todd Houts Director, EHS University of Missouri
  • 2. A basic understanding of RCRA is assumed in this presentation.  On September, 25, 2015, EPA published a lengthy set of “improvements” to RCRA  A large portion is simply reorganization to make them more “user friendly”  But there are also significant changes proposed  Comment period ends Dec 24, 2015
  • 3. Generator Status # of Facilities Total HW Generated (tons) % ofTotal HW Generation CESQGs 293,000-470,000 59,000-144,000 <1% SQGs 46,000-60,000 70,000-152,000 <1% LQGs 14,300 34,500,000 99% Total 353,300-544,300 34,800,000 100%  Items to note:  Impact of new rules mostly benefits SQGs and CESQGs and mostly adds new rules to LQGs  My opinion: this is a “fix” for <1% HW generated and new burdens for the majority
  • 4.  EPA is proposing to change CESQG toVSGQ  Very Small Quantity Generator  “Exempt” may be a misleading word  This presentation uses current CESQG term for clarity and consistency
  • 5.
  • 6.  Consolidation of CESQGWaste at LQGs  Episodic Generation  Labeling  SatelliteAccumulation Areas  Hazardous Waste Determinations
  • 7.  Benefits for user:  Can consolidate and ship from one location  Permit not required to accept from owned CESQGs  Benefits for EPA:  CESQG waste is managed under LQG restrictions ▪ More environmentally sound
  • 8.  Restrictions  CESQG and LQG must be “controlled” by same “person” (as defined in RCRA)  Requirements  Notify state of specific participation  Recordkeeping for these transfers (shipments)  Report under LQG Biennial Report
  • 9.  Note this is only a problem for CESQGs and SQGs (less than 1% of total HW generated)  Would allow once/calendar year event (can petition for a second) for planned event (clean out)  Requirements for all:  Notify EPA or state before planned event  45 days to complete event (30 day extension possible)
  • 10.  Additional Requirements for CESQG:  Obtain RCRA ID number  Use HW Manifest to ship episodic waste to facility  Label episodic containers  Identify an emergency coordinator  Maintain records re: episodic event
  • 11.  EPA concerned current labelling doesn’t require hazard communication  (OSHA HazCom doesn’t apply to HW)  This is an intentional “loophole” (per EPA’s own design) as those dealing with HW have training not necessarily required for good material ▪ 29 states do not have state implementation of OSHA leaving all state agencies out of compliance technically for good materials ▪ But we haven’t seemed to have needed to “solve” that lack of state OSHA-required labeling either
  • 12.  Would apply to SAA, CAA &Transfer facilites  Containers, tanks, drip pads, containment buildings  Require hazard label (options)  Require “plain English” content labeling  Note this essentially removes the “or” of SAA [262.34(c)]  Label with “HazardousWaste” “words that describe the waste”
  • 13.  Opinion on requiring more labeling than currently required (haz waste + plain English + hazard communication term):  Eerily similar to Missouri PML requirements to satisfy emergency responder’s concerns of a “problem” already solved by other requirements
  • 14.  Allows containers to remain open under limited circumstances  e.g., piranha waste (builds up pressure)  e.g., continuous flow waste from instrumentation  Add maximum weight (in addition to volume as defined Federally) at each SAA  Clarify “3 days” is calendar not working days
  • 15.  Circling back to labeling at SAA…  Essentially would force some generators from following SAA at point to generation to following hazcom  Why? Because the “spent” solvents from one lab, could be re-tasked as cleaning solvents elsewhere at the same generator  Forcing HWD to point of generation in complex organizations may lead to EPA losing areas they can inspect
  • 16.  For labs one of the…
  • 17.  EPA claims: “Generators consistently fail to make a correct hazardous waste determination leading to mismanagement of hazardous waste”  Then EPA goes on to say: “Non-compliance rates range from 10 to 30 percent”  So then… compliance ranges up to 90%?  And we need to fix it?
  • 18.  Currently require documentationWHEN determined to be HW, but not when you determine it is NOT HW  Proposal would require documentation of all evaluations (solid wastes in 40 CFR 261.2) regardless of the outcome  Spent materials, sludges, byproducts, discarded commercial chemical products
  • 19.  Discarded commercial chemical products and variable lab waste streams are the aforementioned elephant  The are more than 10 million chemical products and when concentration is considered – there are billions
  • 20.
  • 21.  Emergency Planning and Preparedness  Reporting  Waiver to 50-foot Requirement  Closure
  • 22.  Contingency Plans are lengthy  Emergency responders may have difficulty extracting most important information  Change:  New LQGs must include executive summary as part of Contingency Plan  As proposed, existing LQGs are not required to add an executive summary ▪ Opinion: Emergency responders will expect from all
  • 23.  Types/Amounts of hazardous waste  Maps of site and surrounding area  Water supply location  Identify on-site notification systems available  Emergency contact
  • 24.  Acknowledges existence of LEPC (local emergency planning committees)  Requires submitting Contingency Plan (or Executive Summary for new LQGs) to LEPC  Clarifications:  Only applies to areas where HW is accumulated  Removes requiring personal information in record  Acknowledge modern technology (i.e.: land line not required)  Allows contractors to clean up releases
  • 25.  EPA doesn’t know how many SQGs exist  No re-notification requirement  Many were one time generators (but still being counted)  Require SQGs to re-notify every two years  Provide electronic option
  • 26.  CFR regulations don’t match biennial report instructions  Solution:  Remove CFR instructions – refer to form instructions  Additional changes – minimal impact in Missouri due to state reporting requirements
  • 27.  Storing reactive or ignitable waste 50-feet from property line may not be possible in some areas, especially urban setting  Proposed: allow generator to seek a waiver from Fire Department if facility has taken precautions that don’t include 50-foot rule
  • 28.  LQGs accumulating in containers only that fail to achieve clean closure have no failsafe requirement  For those accumulating in tanks, drip pads and containment buildings currently require to be closed as a landfill if no clean closure
  • 29.
  • 30.  Expand the acute threshold to accommodate spill cleanup.The threshold becomes:  ≤ 1 kg acute hazardous waste, and  ≤ 100 kg residue or contaminated soil, water or other debris resulting from the cleanup of a spill… of any acute hazardous waste  Greater than either of these = LQG
  • 31.  Failure to comply with an exemption condition would result in loss of exemption.  EPA says (80 FR 57934): “…they would be considered an operatingTSDF with a permit and/or in violation of the storage facility operating standards…”
  • 32. Todd Houts Director, EHS University of Missouri houtst@missouri.edu