    Sound Transit 6/17/09 Noise And Construction Meeting - Presentation Transcript

    1. Agenda
      • 6:00 Open House
      • 6:30 Presentations
          • Welcome (Ron Endlich)
          • Project Overview (Michelle Ginder)
            • Construction sequence and activity
            • Construction Updates (ped safety, site walls)
          • Nighttime Construction Noise (Jeff Munnoch)
            • Noise Variance Process
            • Noise Impacts and Mitigation
            • Community Involvement and Next Steps
      • 7:15 Q & A
      • 7:45 Return to Open House
    2. Sound Transit Capitol Hill Station Construction Noise and Project Update June 17, 2009 6:00 – 8:00 PM
    3. Agenda
      • 6:00 Open House
      • 6:30 Presentations
          • Welcome (Ron Endlich)
          • Project Overview (Michelle Ginder)
            • Construction sequence and activity
            • Construction Updates (ped safety, site walls)
          • Nighttime Construction Noise (Jeff Munnoch)
            • Noise Variance Process
            • Noise Impacts and Mitigation
            • Community Involvement and Next Steps
      • 7:15 Q & A
      • 7:45 Return to Open House
      • 3.15-mile extension of Initial Segment and Airport Link
        • Capitol Hill Station
        • UW Station and crossover
      • Schedule
        • Design: completed
        • Construction: 6.5 years
        • System testing: 6 months
        • Open for Service: 2016
      • Adds 70,000 daily riders, 114,000 riders systemwide (2030)
      University Link
    4. Capitol Hill Station
      • Underground station with 3 entrances
      • Staging area - station and tunnel excavation at site
      • Ridership: 14,000 daily boardings
      • Travel time:
        • 6 minutes to downtown Seattle (University St.)
        • 3 minutes to UW Station
    5. Capitol Hill Station Schedule 1 2 3 4
      • Demolition and Remediation
      • Jan. 2009 to mid-2009
      • 75% Recycling and salvage goal being met
      • Construction trailers
      • Site will be lowered, paved and remain fenced
    6. Recycled and Salvaged Items
      • A large amount of materials that otherwise would have been taken to landfills has been removed for re-use.
      • Recycled Demolition Material to Date: 2,890 Tons
    7. 2. I-5 Undercrossing Work
      • I-5 undercrossing contract awarded in February
      • Prepares I-5 structures for future tunnel boring machines
        • Work being done now to avoid conflicts with other WSDOT freeway work and later U-Link contracts
        • Coordinated agency outreach to public on ramp closures
        • Contractor incentives to complete the work early
      Paramount Theater Convention Place Station PINE STREET BOREN STREET NB I-5 SB I-5 Work Area Work Area
    8. I-5 Ramp Closures Pine Street Pike Street Detour info at www.soundtransit.org/u -link   
    9. 3. Station Excavation, Tunneling
      • Jan. 2010 to Dec. 2012
      • Fenced work sites
      • Denny Way and parts of Nagle Place closed to traffic
      • Sidewalks open
        • Will be few short term closures
      • Single Tunnel Boring Machine (TBM)
      • 24/7 surface activity to support tunneling
      • High truck volumes
    10. Construction Walls
      • Plywood walls will surround and screen main construction site perimeter 2010-2015
      • Wall Height:
        • 8 ft. tall along Broadway
        • 16 ft. tall along 10 th Ave
        • Transition from 8 to 16 ft. along northern (John St.) and southern borders
      • Contractor required to maintain fence (repaint annually, graffiti removal within 24 hours)
      • Appearance will include ST Art program elements, ST project information, and Capitol Hill business marketing elements
    11. Truck Haul Routes (beginning 2010)
      • High visibility crossing signs
      • Re-stripe crosswalks
      • Restrict parking at intersections
    12. SDOT Pedestrian Improvements
      • Crosswalk and warning signs on the east leg of Summit Ave and Denny Way
      • Curb bulb on the SW corner of E Denny Way and Boylston Ave.
      • Further options to improve the crossing of Olive Way at Boylston Ave. are under consideration
    13. 4. Station Construction
      • Jan. 2013 to Dec. 2015
      • Less trucking activity
      • Sidewalks open
        • Will be few short term closures
      • Cut and cover pedestrian tunnel across Broadway (6 months)
        • Roadway remains open
        • Parking restrictions near work
    14. Capitol Hill Station Construction Noise Variance for Nighttime Construction
    15. Why must work occur at night?
        • Anticipate two years of 24/7 construction activity to support tunneling work at Capitol Hill site beginning in early 2011
        • Certain activities are required for tunnel worker safety
        • Maximizes project safety, efficiency, duration and cost
      • What goes on at night?
      • No high impact equipment (jackhammers, concrete saws, etc.)
      • Type of Equipment :
      • Tunnel ventilation fans, pumps, air compressors
      • Generators
      • Vehicles
        • hauling and delivery trucks
        • muck haul trucks
        • front-end loaders, backhoe
        • loaders, excavators
    16. Noise Mitigation Requirements Solid plywood construction screening wall between 8-16’ tall around site
    17. Stationary equipment (compressors, generators) enclosed in noise reducing material Noise Mitigation Requirements
      • Nighttime Truck Operations
        • No tonal back up alarms
        • Engine idle limit of 5 minutes
        • Haul trucks prohibited on 10 th Ave E during night hours
        • No compression brakes
        • Muck haul bins lined with noise dampening material
      Noise Mitigation Requirements
    18. Existing noise on 10 th Ave Existing noise on Broadway
    19. Nightime Noise Predictions Hourly night-time average 54 dba existing 65 dba construction + 0 to11 dba 65 dba existing 70 dba construction + 0 to 5 dba
    20. Monitoring and Responding to Complaints
      • Continuous sound monitoring stations
      • 24 - hour construction hotline: 1-888-298-2395
      • Independent response by City Noise Abatement Specialist
      • City, ST and contractor will investigate, determine how to prevent future incidents, and respond back to caller
      • City review after 1 year
    21. Capitol Hill Site Noise Variance
        • Requires application for Major Public Project Construction Noise Variance from City of Seattle
        • Noise variance establishes noise limits for contractor work between 10pm - 7am weekdays, 10pm - 9am weekends, holidays
        • Daytime construction activities will comply with City’s construction noise limits
    22. Next Steps
      • Receive comments and questions tonight
      • ST to incorporate feedback into variance application
      • City of Seattle (DPD) will hold a public meeting to receive comments late summer
      • City will decide whether to approve a noise variance within 60 days after public comment is received
      • Contractor will prepare a detailed noise management plan
      • Follow-up information at meeting(s) later this year
      • Tunnel construction activities begin – early 2011
    23. Staying Informed
      • Monthly electronic newsletters www.soundtransit.org /subscribe
      • Printed and electronic construction alerts
      • Regular construction update meetings
      • Full time outreach staff
      • 24 hour construction hotline 1-888-298-2395
    24. Questions?

    + jseattlejseattle, 7 months ago

    custom

    375 views, 0 favs, 2 embeds more stats

    More info about this presentation

    © All Rights Reserved

    • Total Views 375
      • 311 on SlideShare
      • 64 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 3
    Most viewed embeds
    • 57 views on http://www.capitolhillseattle.com
    • 7 views on http://capitolhillseattle.com

    more

    All embeds
    • 57 views on http://www.capitolhillseattle.com
    • 7 views on http://capitolhillseattle.com

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories