    1. University Link Project I-5 Ramp Closure Update Capitol Hill Open House May 7, 2009
    2. Agenda 6:00 PM - Open House 6:30 PM - Presentation • University Link, Capitol Hill Station and I-5 Construction – Ron Endlich, Deputy Project Director, Sound Transit • Q&A 7:30 PM - Return to Open House 8:00 PM - Close 2
    3. University Link • 3.15-mile extension of Initial Segment and Airport Link – Capitol Hill Station – UW Station and crossover • Schedule – Design: completed early 2009 – Construction: 6.5 years – System testing: 6 months – Open for Service: 2016 • Adds 70,000 daily riders, 114,000 riders systemwide (2030) 3
    4. Capitol Hill Station • Underground station with 3 entrances • Staging area - station and N tunnel excavation at site • Ridership: 14,000 daily boardings • Travel time: – 6 minutes to downtown Seattle (University St.) – 3 minutes to UW Station 4
    5. Capitol Hill Station Schedule 1 2 3 4 5
    6. 1. Demolition and Remediation • Jan. 2009 to mid-2009 • 75% Recycling and salvage goal • Denny remains open • Sidewalks remain open – Will be few short term closures • Site will be paved and remain fenced 6
    7. Recycled and Salvaged Items A large amount of materials that otherwise would have been taken to landfills was removed for re-use. Among some of the items salvaged were: *Recycled Demolition Material to Date: 1,450 Tons • 224 doors • 180 cabinets • 18 restaurant booths • 50 light fixtures • 29 ranges • 31 refrigerators • 13 claw foot tubs • 21 sinks and toilets • 60 radiator fins • 121 ft. wrought iron railing • 90 ft. wood railing • Hundreds of feet of trim and molding • 3500 sq. ft. fir flooring • 500 sq. ft. tin ceiling panels 7
    8. 2. I-5 Undercrossing Work Vicinity I-5 undercrossing contract awarded in February Convention Place Station T EE TR BO ES PIN -Prepares I-5 structures for future tunnel RE W N ST ork A NB I- RE boring machines 5 SB I- ET Work Area re a 5 -Work being done now to avoid conflicts with other WSDOT freeway work and later Paramount Theater U-Link contracts -Coordinated agency outreach to public on ramp closures -Contractor incentives to complete the work early 8
    9. Work Pit Locations ve. nA re Bo SBE Pit NBE Pit NB I -5 SBW Pit SB I- St. 5 NBW Pit e Pin 9
    10. 10
    11. I-5 Ramp Closures Pine Street Pike Street t ee Str y err Ch 11
    12. Olive Way Off-Ramp Closure Detour 12
    13. Cherry Street On-Ramp Detours ϖ Cherry St. express lane on-ramp will be open to all traffic (currently only HOV) during detour 13
    14. Agency Coordination & Public Outreach Efforts • Coordination with WSDOT, SDOT and KC Metro • Sound Transit website • U-Link Website www.soundtransit.org/u-link • E-mail alerts • WSDOT construction information website • SDOT construction webpage • Portable Vehicle Messaging Systems along I-5 • Highway Advisory Radio System (HARS) • Vehicle Message System with notification of closures • Detour cards for businesses affected by closure to educate patrons • Door-to-door business outreach 14
    15. 3. Station Excavation, Tunneling • Jan. 2010 to Dec. 2012 • Plywood wall surrounding site • Denny and parts of Nagle closed to traffic • Sidewalks open – Will be few short term closures • Single Tunnel Boring Machine (TBM) • 24/7 surface activity to support tunneling • High truck volumes 15
    16. Capitol Hill Site Noise Variance •Sound Transit preparing noise variance application for the Capitol Hill site -Construction wall will contain most but not all work noise -24/7 site activities to support tunneling work -Work activities and equipment restrictions, other mitigation •Noise informational meeting June 3, 2009 •DPD will schedule a public meeting on the technical noise variance in late Summer 2009 16
    17. 4. Station Construction • Jan. 2013 to Dec. 2015 • Less trucking activity • Sidewalks open – Will be few short term closures • Cut and cover pedestrian tunnel across Broadway (6 months) – Roadway remains open – Parking restrictions near work 17
    18. Transit Oriented Development (TOD) • 4-5 sites available for TOD • TOD community forums scheduled during 2009 – June 24th forum on housing and retail • Developer(s) to be selected in 2012-2013 • Construction of some sites could begin prior to station opening (2015) 18 N
    19. Questions? 19
    20. Staying Informed • Monthly electronic newsletters www.soundtransit.org/subscribe • Printed and electronic construction alerts • Regular construction update meetings • Full time outreach staff • 24 hour construction hotline 1-888-298-2395 • www.soundtransit.org/u-link 20
    21. Truck Haul Route (beginning 2010) 21

    + jseattlejseattle, 6 months ago

    custom

    227 views, 0 favs, 3 embeds more stats

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 227
      • 141 on SlideShare
      • 86 from embeds
    • Comments 0
    • Favorites 0
    • Downloads 1
    Most viewed embeds
    • 64 views on http://www.capitolhillseattle.com
    • 20 views on http://capitolhillseattle.com
    • 2 views on http://blog.capitolhillseattle.com

    more

    All embeds
    • 64 views on http://www.capitolhillseattle.com
    • 20 views on http://capitolhillseattle.com
    • 2 views on http://blog.capitolhillseattle.com

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories