    PM 101 Training PMP - Presentation Transcript

    1. PM Training 101 John P Vajda Project Manager, PMP
    2. Project Manager Training 101 Agenda
      • The Evolution of a Project Manager
      • Understanding the Phases of a Project
      • Managing In a Matrix Organization
      • Being a Resource and a PM on a Project
    3. The Evolution of a PM
    4. The Evolution of a PM: Status Chaser > Expeditor > Coordinator > Scheduler > Project Manager
      • What is a project exactly?
      • simply:
      • A project is a temporary activity with a start date and a fixed end date
      • A project has specific goals and conditions, defined responsibilities, a budget, and a plan
      • A project has multiple parties involved
      • A project is a series of activities increasing in complexity 
    5. The Evolution of a PM: Status Chaser > Expeditor > Coordinator > Scheduler > Project Manager
      • You can perform many functions as a Project Manager, but what do you consider yourself?
      • Just chasing status is not project managing
      • Just forwarding emails is not project managing
      • Planning in only Excel is not project managing
      • Just scheduling meetings is not project managing
      • Taking credit for your team’s work is not project managing
    6. The Evolution of a PM: Status Chaser > Expeditor > Coordinator > Scheduler > Project Manager
      • So What does a Project Manager do?
      • We get work done through others
      • We create the game plan for the project based on our experiences
      • We coach, mentor, train, lead, organize, and drive the team
      • We solve problems and remove road blocks with qualitative and quantitative analysis
      • We manage stakeholders and scope, protect our teams, and always do what is best for the project’s success
      • We don’t get political
      • We keep it human
    7. The Evolution of a PM: Status Chaser > Expeditor > Coordinator > Scheduler > Project Manager
      • What are the Project
      • Manager’s deliverables?
    8. The Phases of a Project
    9. The Phases: Initiation > Planning > Execution > Monitoring & Controlling > Closing
      • 5 core phases of Project Management in (PMP)
        • Initiation
        • Planning
        • Execution
        • Monitoring & Controlling
        • Closing
      • FYI: different phases are used in different methodologies or processes
    10. The Phases: Initiation > Planning > Execution > Monitoring & Controlling > Closing
      • Your success depends on you understanding of what occurs in these phases
      • Know what inputs and outputs are critical to each phase
      • Be consistent, don’t take the easy road
      • Planning is your “game plan”, without it you have no game
    11. The Phases: Initiation > Planning > Execution > Monitoring & Controlling > Closing Proper Distribution of Time as PM: How you may be spending your time as a PM:
    12. Phase I: Initiation
    13. Gathering Requirements Core Project Team Sponsors
      • Proper requirement gathering techniques allow you to define your scope
      • Engaging all key potential project members defines your scope
      • Be prepared for uncertainty, and learn how to plan for it
      Stakeholders Uncertainty & Assumptions
      • Early gathering, allows you to create a statement of work
      Scope
    14. Initiation: Charter & SOW > Preliminary Scope > Final Scope Statement > Kick-Off Meeting
      • A Statement of Work (SOW) should be provided by your customer or sponsor
      • A Charter and Funding of project should be confirmed prior to starting your PM activity
      • A Charter authorizes you to work on the project, and give you authority
      • Funding provides you a budget and identifies your key sponsors. “Who is paying?”
    15. Initiation: Charter & SOW > Preliminary Scope > Final Scope Statement > Kick-Off Meeting
      • What’s in a Statement of Work?
      • Project and Product Objectives
      • Product Acceptance Criteria
      • Schedule Milestones
      • Approval and Reporting Requirements
      • Order of Magnitude cost Estimate (OME )
    16. Initiation: Charter & SOW > Preliminary Scope > Final Scope Statement > Kick-Off Meeting
      • What’s in a Charter?
      • Project Description
      • Project requirements (high level)
      • Assigned Project Manager, and authority level
      • Summary of milestones schedule
      • External assumptions and constraints
      • Business case (high level)
      • Signature of sponsors, or approval workflow
      • Initial Project Organization
    17. Initiation: Charter & Funding > Preliminary Scope > Final Scope Statement > Kick-Off Meeting
      • What’s in a Preliminary Scope Statement?
      • Project and Product Objectives
      • Product or Service Requirements and Characteristics
      • Product Acceptance Criteria
      • Project Boundaries
      • Project Deliverables
      • Project Constraints and Assumptions
      • Initial Defined Risks
      • Schedule Milestones
      • Order of Magnitude initial cost Estimate (OME)
      • Project Configuration Management Requirements (level of change control)
      • Approval and Reporting Requirements
    18. Initiation: Charter & SOW > Preliminary Scope > Final Scope Statement > Kick-Off Meeting
      • What’s in a Final Scope Statement?
      • Project and Product Objectives
      • Product Scope Description
      • Project Requirements
      • Project Boundaries
      • Project Deliverables
      • Product acceptance Criteria
      • Project Constraints and Assumptions
      • Initial Project Organization
      • Confirmed Risks
      • Schedule Milestones
      • Order of Magnitude initial cost Estimate (OME)
      • Project Configuration Management Requirements (level of change control)
      • Approval and Reporting Requirements
    19. Initiation: Charter & Funding > Preliminary Scope > Final Scope Statement > Kick-Off Meeting
      • What’s happens during a Project Kick-Off Meeting?
      • Kick-offs should last no longer then 2 hours
      • A team Introduction
      • Preliminary Roles & responsibilities review
      • Review all aspects of the final scope statement and agree as a team
      • Review any supporting documentation to define the scope
      • Review chosen project management methodology
      • Review preliminary project plans & schedules
      • Agree to project documentation to be used
      • Discuss project tools to be used
      • Set and agree to reoccurring project meeting times
      • Discuss project next steps
    20. Phase II: Planning
    21. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Proper planning takes time, don’t rush it or cut corners
      • Your managers/sponsors must give you time to plan
      • Don’t schedule in a silo, you need input from your core project team to define your activities
      • Embrace the WBS (Work Breakdown Structure)
      • Always define team responsibilities (RACI) “Who does what”
      • Use 21 st century social media techniques to keep the team “informed”
    22. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Project Plans aren’t schedules!
      • Scope Management Plan
      • Risk Management Plan
      • Communication Management Plan
      • Quality Management Plan
      • Time Management Plan
      • Resource Management Plan
      • Cost Management Plan
      • Procurement Management Plan
      • Integration Management Plan
    23. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Work Breakdown Structure (WBS)
      • Visual list of activities by deliverable or phase
      • Avoid trying to sequence these, or put time on them right away
      • This is a team activity!
      • Helps identify “forgotten” activities
      • Use this as a input to build your schedule
    24. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Estimating: Different Projects call for different types of estimating!
      • Single point estimates : 5 days
      • 3 point estimates : uses 3 duration estimates to represent the optimistic, most likely and pessimistic scenarios: 5, 7, 10 days
      • Range Estimates : (low and high range) 5 to 10 days
      • Planning Poker (crowd) Estimates: Team members give a number for estimates of a task, you debate the high vs. low estimates to come to a realistic conclusion. Requires strict PM moderation: ~6.5 days
    25. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Scheduling
      • Don’t do this in excel. Use a proper PM tool like MS Projects, Liquid Planner or applications that allow you build a timeline, Gantt charts, network diagrams, etc.
      • Sequence your activities properly
      • Review with your team as much as possible
      • Keep real time status of each deliverable and milestone
      • Update your schedules everyday!
      • Build activities/tasks around deliverables
      • Have deliverables role up into milestones
      • Understand task dependencies, predecessors, successors, lead (overlap) time, lag (delay) time, padding etc.
    26. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Example:
      • 1.3 is the WBS number
      • Technical Design is a Milestone
      • Task Activities role up into this milestone
      • A completion summary activity is marked as “0” days in green
      • Task sequencing is properly defined
      • Resources have been indicated
      • Percentage complete is maintained
      • Use 1.3.5 as a Predecessor to other tasks
    27. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Identify and Manage Risks
      • Risks need to be managed throughout the Project Lifecycle
      • Use a Risk Register! (tracking document)
      • Rank your risks based on quantitative & qualitative data
      • Have the team participate in Risk Management
      • Always assign owners of risks
      • Some risks are opportunities and can be a positive risk 
      • Risks always have a cost, use EMV to figure it out (% x cost = expected monetary value)
    28. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • What is a Risk Register?
      • Simply : A list of risks, and how you will respond to them
    29. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • Roles & Responsibilities who does what?
      • Never assume your project team knows all their responsibilities during the entire PLC
      • Break it down in RACI format by deliverable or phase, use your WBS as a guide
      • RACI = Responsible, Accountable, Consulted, Informed, know the difference between these terms
      • R&R can change from project to project depending on your team resources, deliverables, etc
      • Maintain an active roster of Stakeholders, Sponsors and Core team members for proper project communication
    30. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • What is a RACI Chart?
      • Simply: A chart outlining who is responsible for what and at what level based on deliverables.
    31. Planning: Project Management Plans > WBS > Scheduling > Risk Identification & Analysis > Roles & Responsibilities
      • What if I want to be more detailed?
      You can be as detailed as you need to be!
    32. Phase III: Execution
    33. Execution: Direct & Manage Project Work > Project Baseline > Information Distribution >
      • Be actively engaged daily in your team’s work, but don’t micro manage  (unless you have too)
      • Pay attention to “threads” going back and forth in different communication mediums, you may need to remove a road block, or help problem solve. People won’t always ask for your help.
      • Be ready to adjust to delays or resource issues, have contingencies/mitigation plans ready!
      • Use 21 st century Project Management techniques!
    34. Execution: Direct & Manage Project Work > Project Baseline > Information Distribution >
      • What is Social Networking Project Management?
      • Simply: embracing group dynamics and crowd sourcing during the PLC
      • How do I do it?
      • Work to add generalized specialists to your teams who can offer input on a range of topics from business to design to development
      • Look for a Cross-Pollination of ideas. Pull from your greater community the solutions to project problems
      • Use existing internal communication mediums to do this!
      • Push your teams to embrace new technology, evangelize this concept.
      • 21st century Project Management is about collaboration not control
    35. Execution: Direct & Manage Project Work > Project Baseline > Information Distribution >
      • 21 st Century Project Management Techniques
    36. Execution: Direct & Manage Project Work > Project Baseline > Information Distribution >
      • What Tools do I use to Direct and Manage Work?
      • Maintain a current & accurate schedule
      • Hold consistent time controlled status meetings (frequency = as much as needed)
      • Provide meeting agendas and meeting notes for every meeting
      • Use 21 st century collaboration tools
      • Use face to face interactions or conference calls over email
      • Obtain work performance information daily
      • Release progress reports and timely project status
      • Develop your resource management techniques & leadership skills
      • Always look to develop your team’s skills
      • Ask for help from your team’s functional managers
    37. Execution: Direct & Manage Project Work > Project Baseline > Information Distribution >
      • What is a Project Baseline?
      • A baseline is a set of original project estimates. This set consists of the original task, resource, assignment, and cost estimates that you enter into your schedule.
      • A baseline is essential for tracking progress. The original estimates it contains are permanent reference points used for comparison and variance analysis throughout the PLC
      • Store base lined schedules in your pre-determined OFO Directory for reference
      • Baseline activities also means you update all your project plans as necessary!
    38. Execution: Direct & Manage Project Work > Project Baseline > Information Distribution >
      • What is Information Distribution?
      • Simply: The way you collect and distribute accurate project data and information during the PLC
      • How do I do this?
      • Get accurate information from your teams and publish it in a consistent manner. (wiki updates, status emails, progress reports etc.)
      • Determine which stakeholders need to see what level of detail
      • Determine project color status weekly: Green , Yellow , Red
      • Never hide a red project issue, make it known to the stakeholders if the project is going red
      • Flag changes in scope or major issues and risks
    39. Phase IV: Monitoring & Controlling
    40. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Monitoring & Controlling happens while you execute project work
      • It’s ongoing and is critical to the success of your project
      • As a PM, this is your responsibility during execution of tasks!
      • Never stop asking questions during the PLC
      • Remember the triple constraint and how changes effect your project goals
      Execution Monitoring Controlling
    41. Monitoring & Controlling: Scope Control > Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Controlling scope is critical during the Monitoring & Controlling Phase
      • Set up a Change Control Process during your Planning Phase in the Scope Management Plan
      • Determine who is on your Change Control Board (CCB)
      • Always use variance analysis to assess changes to your scope
      • Remember to properly vet changes as nice to haves, or core functionality
      • Don’t forget the triple constraint!
    42. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • It is responsibility of the PM to control the schedule and keep it current and accurate
      • Understand how to maximize your schedule by using resource leveling, fast tracking, de-scoping, and changes in deadlines or budget.
      • Know how to apply critical path method!
      • Simply: the longest path of planned activities to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer.
      Task set A: 1,2,4,5 = 12 days Task set B: 1,3,5,6 = 15 days Conclusion: Task 2 and 4 aren’t on the critcal path
    43. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Monitoring and Controlling project work is a PM’s biggest responsibility during execution
      • Establish usable processes, make the processes easily repeatable
      • Be highly organized and continually update your documents in your project document repository
      • Learn how to decipher roadblocks and project “hang-ups” by honing your listening and observation skills
      • Always be problem solving using analytical thinking techniques
      • Never stop asking questions
    44. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Yes, Baseline updates are still needed during this stage! Remember Execution is underway while Monitoring and Controlling occurs
      • Things are constantly changing around the project, so your project has to adapt and “stay current”
      Execution Monitoring Controlling
    45. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Write a Communication Plan so there is no doubts about how communication will work during your PLC, refer back to it when needed
      • Remember ~90% of A PM’s job is communication. To make sure it’s effectively done you need to learn to properly encode and decode messages
      • Understand your lines of communication and who needs what type of information: Formula : n * ( n -1) / 2 = x (n * x ) /2 = Lines of communication Example: 7 people = 7 * ( 7 -1) / 2 = ( 7 * 6 ) /2 = 21 Lines
      • 7 People = the complete team including stakeholders and you. You subtract 1, since you don’t communicate to yourself, this can tell you how much time you will spend communicating. The bigger the number the harder it will be to communicate on the project.
    46. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Be consistent! Use your Project Tracking Documents and Meeting Notes/Agenda to update your Wiki Pages (high level project status) and build accurate progress reports.
      • How is it done?
    47. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • What is variance analysis in project management?
      • Simply: the difference between a budgeted or planned work and the actual work that has occurred.
      • 3 Main Types:
      • Estimate to Planned. This is the difference between what we quoted and how we actually planned to do the work.
      • Planned to Actual. This variance looks at the difference between how work is planned and how it actually is executed
      • Estimate to Actual. Here, we compare what we quoted to what we actually did
    48. Monitoring & Controlling: Scope Control> Schedule Control> Monitor & Control Project Work > Baseline Updates > Communication Control > Variance Analysis
      • Earned Value Management: a technique for measuring project progress in an objective manner. It has the ability to combine measurements of scope, schedule, and cost in a single integrated system. When properly applied, EVM provides an early warning of performance problems.
      • BAC (Budget at Completion)
      • AC (Actual Cost)
      • Formulas:
      • PV (Planned Value): BAC x Planned % complete
      • EV (Earned Value): BAC x Actual % complete
      • SPI (Schedule Performance Index): EV/PV
      • SV (Schedule Variance): EV – PV
      • CPI (Cost Performance Index): EV/AC
      • CV (Cost Variance): EV – AC
      • EAC (Estimate at Completion): BAC/CPI
      • VAC (Variance at Completion): BAC – EAC
    49. Phase V: Closing
    50. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate!
      • Always update your documentation and organize you Project Document Repository prior to closing a project
      • Plan a Lessons Learned session and indentify major gaps in the project, use these to improve project and organizational processes
      • Always (when in budget) plan a project celebration, whether it’s a lunch, some gift cards, it’s goes a long way to show appreciate for your team
      • Define a handoff now the project is closed. Projects have start and end dates, project mangers shouldn’t be the owner of ongoing operational maintenance activities. We must move onto other projects 
    51. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate!
      • It’s time to go live! Now what do you do?
      • The biggest mistake organizations make is not allow project managers to transition off a project
      • Set up a clear handoff to an operational maintenance team or person once a project is live. Plan for this prior to the go live date
      • Review project metrics to make sure the project was a success. Refer back to your scope documents, check your budget, validate you delivered what the customer asked for
    52. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate!
      • The entire team is responsible to update and finalize all project documentation
      • Be sure to organize your Project Document Repository and update your Project Tracking System as needed
    53. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate!
      • The cataloging of Project Lesson Learned should be ongoing through the PLC. A successful Lessons-Learned program will help project teams:
      • Repeat desirable outcomes
      • Avoid undesirable outcomes
      • As you flag major issues, you should keep an active log of what you feel the project team can address at the end of the project
      • Address major issues as soon as possible, don’t wait to use Lesson Learned techniques!
      • At regular intervals, reflect on how to become more effective and adjust your behavior accordingly.
      • This information should be categorized as by Project or Organization . Not all your lesson learned are in your control as a project manager
      • Develop a process to provide input to your managers to act on organizational lessons learned
    54. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate!
      • It is important to create a detailed final report for the project. This can encompass several areas. Your Stakeholders can tell you what they need to see
      • This report should be released to the core team as well as the stakeholder community and sponsors
      • It can include the following topics:
      • Project Summary
      • Measurable Goals & Metrics
      • Accomplishments, both individual and project related
      • Summary of Lesson Learned
      • Major Issues and recommendations
      • Future Directions, Phases, etc
    55. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate!
      • Discuss with your functional managers how long you will have your project team after the project goes live.
      • You should plan some “buffer” time to have them available in case issues arise
      • Determine a clear date when the team will be disbanded
      • Always follow organizational internal process for release a project team member, it could be a simple as saying “your all done!” or as complex as using a resource management application
    56. Closing: Go Live > Finalize Project Documentation > Lessons Learned > Closing Project > Release Project Team > Celebrate !
      • Discuss a budget with your manager for a project celebration
      • Create a fair system of recognition and reward. Metrics are “supposed” to be met, not completely unobtainable
      • Plan a lunch, dinner, or simply a nice gift for your core team members
      • Recognize above and beyond effort. Reward that work with incentives
      • Always thank your team! remember you get work done through others 
    57. Managing in a Matrix Organization
    58. Managing in a Matrix Organization
      • Understanding how an organization is structured is key to your success as a PM
      • Below is a chart showing Organizational Structure Influences on Projects
    59. Managing in a Matrix Organization
      • Matrix Organization: a type of organizational management in which people with similar skills are pooled for work assignment.
      • * Weak Matrix Organizations are not show here
      Strong Balanced
    60. Managing in a Matrix Organization
      • Disadvantages of Matrix Management:
      • Employees can become confused due to conflicting loyalties and poor information sharing
      • Unclear organizational goals leads to inefficiency
      • Multi-Reporting structure leads to the tendency to “repeat” status to many different people
      • Burn out, or over allocation of tasks. Wearing too many hats if roles and responsibilities are not defined.
      • A PM can be reduced to a coordinator if they allow themselves to be overshadowed by functional managers and executives
      • Advantages to Matrix Management:
      • Allows team members to share information more readily across task boundaries.
      • Allows for specialization that can increase depth of knowledge (Generalized Specialists)
      • Allows to pool resources from many organizations to maximize headcount
      • PMO organizations can directly report to a executive
      • Different PM authority level can be determined for different types of projects
    61. Managing in a Matrix Organization
      • How do I project manage in this type of environment?
      • Share resources effectively by accurately tracking workload and understand your teams tasks and activities.
      • Reduce conflict and confusion by creating collaborative social networking workspaces for better information sharing
      • Balance time and performance with cost. Understand how long it takes your team to do something, and how well they are executing their tasks.
      • Properly share authority and responsibility with your team leads
      • Provide Roles and Responsibilities to your team. “Who does what”
      • Create accurate work performance reports so you don’t have to repeat yourself to several different managers 
      • Establish your PM authority early on in the PLC
    SlideShare Zeitgeist 2009

    + John VajdaJohn Vajda Nominate

    custom

    316 views, 2 favs, 0 embeds more stats

    Introduction training for PMP style project managem more

    More info about this document

    © All Rights Reserved

    Go to text version

    • Total Views 316
      • 316 on SlideShare
      • 0 from embeds
    • Comments 0
    • Favorites 2
    • Downloads 51
    Most viewed embeds

    more

    All embeds

    less

    Flagged as inappropriate Flag as inappropriate
    Flag as inappropriate

    Select your reason for flagging this presentation as inappropriate. If needed, use the feedback form to let us know more details.

    Cancel
    File a copyright complaint
    Having problems? Go to our helpdesk?

    Categories